Fareham Town Centre Masterplan Delivery - Fareham Shopping Centre Investment - shopping arcade, entrances and associated improvement works
ApprovedExecutive2 papers
AI summaryFareham Executive approves up to £9.447 million capital spend for Fareham Shopping Centre refurbishment, with detailed design starting August 2026 and site works from February 2027.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDirector of Planning and Regeneration to lead delivery
Money£9,447,000 maximum capitalPart funded from receipts and reserves, rest borrowed
What happens nextDesign from August 2026Site start planned for February 2027
Who it affectsFareham Shopping Centre usersEntrances, arcade, squares, public toilets
What was decided
The Executive noted the emerging design approach and delegated authority to the Director of Planning and Regeneration to take forward detailed design, planning applications, procurement and tenant negotiations, in consultation with the Executive Member for Policy and Resources. Report P7
The Executive approved a maximum capital expenditure of £9,447,000 for the works, with the Director authorised to award individual contracts up to £250,000 without further approval and to consult the S151 Officer for awards above that threshold. Report P8, P9
Why
The investment is the first visible phase of the Fareham Town Centre Masterplan and is intended to improve the appearance, functionality and long-term viability of the retained parts of Fareham Shopping Centre ahead of larger redevelopment proposals. Report P1, P22, P23, P25
Officers argued that targeted investment in entrances, the shopping arcade, Thackeray and Westbury Squares, public toilets and maintenance is needed to attract footfall, retain occupiers and support the evening economy, building on the success of Fareham Live. Report P30, P31, P36, P39, P55
What happens next
Officers will progress detailed design to RIBA 3 in August 2026, submit a planning application in September 2026 and issue a works tender in September 2026, with contract award in December 2026 and start on site in February 2027. Report P72
Funding sources of £3,655,000 have been identified from 2026/27 capital receipts and a reclassification of part of the Council's spending reserve, with the remaining balance funded by borrowing; borrowing costs for Phase One and maintenance are judged affordable within the Medium-Term Finance Strategy. Report P12, P75, P77
Further design work will address environmental comfort, wind impact, seating, accessibility and the long-term management and maintenance of the arcade, ahead of the Shadow Authority elections expected in May 2027 and the new Unitary Authority coming into effect in April 2028. Report P46, P47, P88, P90
The money
£9,447,000 Maximum capital expenditure approved for delivery of the works Report P8, P12, P70
£3,655,000 Funding from 2026/27 capital receipts and reclassification of part of the Council's spending reserve Report P12, P75
£5,792,000 Balance to be funded from borrowing Report P12
£3,185,880 Borrowing cost element for Phase One and maintenance Report P77
£2,606,120 Phase Two (retained East and West FSC and Delme Square) cost Report P74, P78
£250,000 Threshold above which the S151 Officer must be consulted on individual contract awards Report P9
Options considered
Chosen: Approve the £9,447,000 capital budget and delegate delivery to the Director of Planning and Regeneration. Secures budgets for an early, visible phase of Masterplan delivery while maintaining momentum and financial certainty Report P5, P7, P8, P11
Rejected: Reject or delay the investment in the retained parts of Fareham Shopping Centre. Officers warned that failure to invest risks declining footfall, increased vacancies, reduced investor confidence and weaker positioning ahead of the larger redevelopment Report P39
Implications
Financial: Up to £9,447,000 of capital expenditure is approved, with £3,655,000 from receipts and reserve reclassification and the balance from borrowing; borrowing for Phase One and maintenance is judged affordable, while Phase Two funding may need to be weighed against future capital priorities. Report P12, P75, P77, P78
Equalities: New WC provision is designed to be modern, accessible and inclusive for families, older people and people with disabilities, supporting the Council's accessibility commitments. Report P58, P59
Climate: The scheme adopts a 'reuse first' approach, retaining and recladding existing structures, specifying low-energy LED lighting with intelligent controls and embedding environmental criteria in procurement to reduce embodied and operational carbon. Report P4, P79, P80, P81, P83, P84, P85
Risk: Confidential appendices have been withheld under Schedule 12A of the Local Government Act 1972 to protect the Council's negotiating position on commercial terms and future contracts. Report P14, P15
Other: Delivery is shaped by Local Government Reorganisation: a Shadow Authority is expected to be elected in May 2027 and a new Unitary Authority will come into effect in April 2028, with defined oversight over major or long-term decisions to be set out in a Structural Change Order; works are expected to be on site before the Shadow Authority takes effect. Report P88, P89, P90
Who and where
Visitors, residents and shoppers using Fareham Shopping Centre and the surrounding town centre Report P3, P5, P37
Existing and prospective occupiers and investors in Fareham Shopping Centre Report P3, P34, P38
Tenants, partners and stakeholders affected by the refurbishment and ongoing negotiations Report P7
Fareham Borough Council and the future Shadow Authority and Unitary Authority Report P88, P89, P90
Evening economy businesses on West Street linked to the Fareham Live route Report P31, P33
Timeline
August 2026: Design development to RIBA 3 Report P72
September 2026: Planning submission and tender issued for works Report P72
December 2026: Contract for works signed Report P72
February 2027: Start on site Report P72
May 2027: Elections to the Shadow Authority expected Report P88, P90
April 2028: New Unitary Authority expected to come into effect Report P88
Plain English for the jargon
FSC: Fareham Shopping Centre, the pedestrianised retail centre at the heart of West Street.
RIBA 3: Stage 3 of the Royal Institute of British Architects' Plan of Work, covering developed design and coordinated design information.
S151 Officer: The local authority officer with statutory responsibility for the proper administration of the Council's financial affairs under section 151 of the Local Government Act 1972.
Shadow Authority: An interim authority established to oversee the transition to a new Unitary Council ahead of it taking on full powers.
LGR: Local Government Reorganisation, the restructuring of local authorities in the area.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9(1)
Resolved
RESOLVED that the Executive: (a) notes the emerging design approach for the FSC entrances, arcade, squares, WC relocation, maintenance and wider refurbishment works and delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, to progress all aspects of delivery, including detailed design development, submission of planning applications (as required), procurement of contractor/s, technical assessments and all necessary ongoing negotiations with partners, stakeholders and affected tenants as required; and (b) subject to the approval of recommendation (a) above, approves a maximum capital expenditure of £9,447,000 for the delivery of works and delegates authority to the Director of Planning and Regeneration to enter into contracts to secure this, within the agreed budget as follows: · individual contracts for £250,000 and under, or · following consultation with the Section 151 Officer for any individual contract awards over £250,000.
Word for word from the decision Fareham published for this meeting.Source: moderngov.fareham.gov.uk
This report seeks Executive approval to progress the next stage of investment in Fareham Shopping Centre (FSC) as an early and visible phase of the Fareham Town Centre Masterplan. The proposals will support the Council’s ambition to accelerate town centre regeneration, enhance visitor experience, strengthen the local economy and improve the long-term viability of the retained elements of FSC.
The investment will deliver a programme of refurbishment and improvement works focused on four key areas: upgraded shopping centre entrances, the creation of an enhanced shopping arcade and improvements to Thackeray and Westbury Squares, relocation and modernisation of public toilet facilities, and essential maintenance works across the centre. A second phase will extend refurbishment works to the retained eastern and western sections of FSC and Delme Square, creating a consistent and attractive environment throughout the centre.
The proposals are intended to improve the quality, appearance and functionality of FSC, increasing footfall, supporting existing businesses, attracting new occupiers and reinforcing Fareham’s role as a retail, leisure and cultural destination. The design approach draws on Fareham’s heritage while delivering a contemporary and commercially attractive environment.
A capital budget of £9,447,000 is required to progress detailed design, planning, procurement and delivery of the works. The proposals adopt a sustainability-led, “reuse first” approach, maximising retention of existing structures, preserving embodied carbon and improving long-term environmental performance.
Approving these recommendations will maintain momentum, provide financial certainty, and ensure continued delivery of a comprehensive, phased regeneration programme that strengthens Fareham’s economy, enhances public spaces, increases housing supply, and creates a more vibrant, accessible and resilient town centre for residents, businesses and visitors.
Recommendation: It is recommended that the Executive:
(a) notes the emerging design approach for the FSC entrances, arcade, squares, WC relocation, maintenance and wider refurbishment works and delegates authority to the Director of Planning and Regeneration, following consultation with the Executive Member for Policy and Resources, to progress all aspects of delivery, including detailed design development, submission of planning applications (as required), procurement of contractor/s, technical assessments and all necessary ongoing negotiations with partners, stakeholders and affected tenants as required;
(b) subject to the approval of recommendation (a) above, approves a maximum capital expenditure of £9,447,000 for the delivery of works and delegates authority to the Director of Planning and Regeneration to enter into contracts to secure this, within the agreed budget as follows:
• individual contracts for £250,000 and under, or • following consultation with the S151 officer for any individual contract awards over £250,000.
Reason:
To secure the capital budgets required to deliver an early phase of the Masterplan delivery related to FSC entrances, arcade, squares, WC relocation, maintenance and wider refurbishment works.
Financial implications
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
9(1)Fareham Town Centre Masterplan Delivery - Fareham Shopping Centre Investment - shopping arcade, entrances and associated improvement worksThis decision
Fareham Town Centre Masterplan Delivery - Fareham Shopping Centre Investment - shopping arcade, entrances and associated improvement worksThis decision
Corporate Complaints Handling PolicyRESOLVED that the Executive: (a) agrees the updated Council’s Complaint Policy as attached at Appendix A to the repor...
References from Other CommitteesIt was RESOLVED that, in order for Officers to answer Members questions about the contractual arrangements for the cu...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.