Fenland Transport Economic Assessment including March to Wisbech Rail Funding from CPCA
AgreedExecutive1 paper
AI summaryFenland Cabinet has agreed to accept £500,000 from the Cambridgeshire and Peterborough Combined Authority for an 18-month transport study covering the Wisbech to March rail link and other major Fenland infrastructure schemes.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet accepted £500,000 and set up a Project Board
Money£500,000From CPCA between 2026 and 2028
What happens nextProcurement from April 2026Procurement April to June 2026, then 18-month study
Who it affectsFenland transport schemesMajor schemes including Wisbech to March rail
What was decided
Cabinet accepted £500,000 from CPCA, payable between 2026 and 2028, to fund the Fenland Transport Economic Assessment Project. Report P62
Cabinet confirmed the creation of a Project Board to oversee the business case project, along with its remit, terms of reference and membership as set out in the report. Report P52, P67, P54
Cabinet noted the procurement exercise to appoint a contractor and delegated authority to award the contract to the Portfolio Holder for Transport and the S151 Officer, and to sign the Grant Funding Agreement to the Portfolio Holder for Finance and the S151 Officer.
Why
Major Fenland transport projects have struggled to progress beyond early business case stage because of high costs and poor value-for-money scores under the government five-case business model. Report P56, P58
The 2023-24 Network Rail Options Assessment found all Wisbech to March rail options had very low benefit to cost ratios of between 0.10 and 0.27, well below the 1.5 threshold normally needed to justify investment. Report P3
The CPCA Transport Committee in November 2024 asked for broader scope, including a possible extension towards Chatteris and better integration with projects such as the Anglian Water Fens Reservoir. Report P5, P59
What happens next
CPCA is expected to give final funding confirmation by February 2026, with the Grant Funding Agreement between CPCA and FDC signed in February or March 2026. Report P49, P62
Procurement of a contractor is scheduled for April to June 2026, with consultants and FDC delivering Phase 1, the context and benchmarking stage, from July to October 2026. Report P49
Phase 2, covering scenario development and testing, is scheduled for October 2026 to September 2027, with progress reported to the CPCA Transport Committee and FDC Cabinet between October 2026 and December 2027. Report P49
The money
£500,000 CPCA grant to FDC to deliver the Fenland Transport Economic Assessment Project between 2026 and 2028 Report P62
Implications
Financial: Third-party CPCA funding of £500,000 between 2026 and 2028 covers the cost of the study, with no direct FDC contribution identified in the papers. Report P62
Legal: A Grant Funding Agreement between CPCA and FDC must be signed before the arrangement takes effect, and procurement will be carried out for the contractor. Report P48
Staffing: A Project Board will be set up with the FDC Portfolio Holder for Transport as chair, plus the FDC Leader and Portfolio Holder for Finance, the FDC Portfolio Holder for Planning and an FDC representative on the CPCA Transport Committee, meeting at least every three months. Report P52, P67, P71
Risk: Previous rail scheme assessments have produced benefit to cost ratios far below the level normally required to justify investment, and the new study is intended to address this. Report P3, P58
Other: The study will inform future decisions on delivering the Wisbech to March rail link and other Fenland transport schemes, including possible extensions, the A47 dualling, Whittlesey Relief Road and integration with the Fens Reservoir. Report P33, P35, P9, P30
Who and where
Residents, businesses and developers in Fenland, particularly in Wisbech, March, Whittlesey and Chatteris Report P7, P9, P24, P27
Cambridgeshire and Peterborough Combined Authority, as funder, Local Transport Authority and project partner Report P1, P50, P62
Network Rail and Greater Anglia, as railway infrastructure owner and local station asset manager Report P50
Anglian Water, as proposer of the Fens Reservoir near Chatteris Report P30, P50
National Highways, responsible for the A47 Report P50
Cambridgeshire County Council, as Local Highway Authority for Cambridgeshire Report P50
Peterborough City Council, as Local Highway Authority for adjoining Whittlesey Report P50
Timeline
Jul - Oct 2025: Scoping and early project development by CPCA and FDC Report P49
Dec 2025 - Feb 2026: Expected CPCA funding approval and final confirmation Report P49
Feb 2026: FDC Cabinet decision Report P49
Feb/March 2026: Grant Funding Agreement to be signed by CPCA and FDC Report P49
Apr - June 2026: Procurement of contractor to deliver the study Report P49
July - October 2026: Phase 1 study on context and benchmarking, led by consultants and FDC with CPCA support Report P49
Oct 2026 - Sept 2027: Phase 2 study on scenario development and testing, led by consultants and FDC with CPCA support Report P49
October 2026 - December 2027: Progress reports to CPCA Transport Committee and FDC Cabinet Report P49
Plain English for the jargon
BCR: Benefit to Cost Ratio, a measure of scheme value for money where 1.5 or higher is generally considered viable
CPCA: Cambridgeshire and Peterborough Combined Authority, the Local Transport Authority
CCC: Cambridgeshire County Council, the Local Highway Authority for Cambridgeshire
FDC: Fenland District Council, the Local Planning Authority
LGR: Local Government Reorganisation
MATS: March Area Transport Strategy
S151 Officer: The council's chief finance officer, designated under section 151 of the Local Government Act 1972
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB56/25
Resolved
AGREED to: · Subject to the final confirmation from CPCA, confirm the acceptance of £500,000 between 2026 and 2028 from CPCA for FDC to deliver the Fenland Transport Economic Assessment Project. · Confirm the establishment of the Project Board to oversee the business case project, confirm the board’s remit, including its terms of reference and membership. · Note the procurement exercise to select a contractor to deliver the Fenland Transport Economic Assessment project and give approval for delegated authority to the Portfolio Holder for Transport and the S151 Officer to award the contract. · Subject to the final confirmation from CPCA, third party funding has been approved for this work. A Grant Funding Agreement between CPCA and FDC is required. Delegate approval to the Portfolio Holder for Finance and S151 Officer to sign the agreement on behalf of FDC and complete all other documentation necessary to bring this arrangement into effect.
Word for word from the decision Fenland published for this meeting.Source: moderngov.fenland.gov.uk
Fenland Transport Economic Assessment including Wisbech Report Title: to March Rail
1 Purpose / Summary 1.1 This report relates to the Fenland Transport Economic Assessment project including Wisbech to March Rail. Subject to final confirmation of the third- party funding from CPCA Members are requested to: • Confirm the acceptance of £500,000 between April 2026 and March 2028 from CPCA for FDC to deliver the Fenland Transport Economic Assessment Project. • Appoint a Project Board including setting its remit, its terms of reference and membership • Note the procurement exercise to select a contractor to deliver the Fenland Transport Economic Project. Approval of delegated authority to the Portfolio Holder for Transport and S151 Officer is requested to award the contract following completion of the procurement • Subject to final confirmation, third party funding being approved from CPCA. A Grant Funding Agreement between CPCA and FDC is required. Delegated approval to the Portfolio Holder for Transport and S151 Officer is requested to approve and sign the agreement on behalf of FDC.
2 Key Issues 2.1 Subject to final confirmation, FDC has been awarded £500,000 by CPCA to deliver the Fenland Transport Economic Assessment project including Wisbech to March Railway Line. 2.2 There are larger scale essential transport projects desperately needed in Fenland which struggle to demonstrate significant benefits due to cost, ground conditions, lower land values and the need for regeneration. This infrastructure is pivotal to support the delivery of new homes and jobs within Fenland that are a requirement of the Local Plan (2014). The transport challenges in Fenland need to be addressed to deliver the new homes and jobs. This includes demonstrating value for money and unlocking wider economic benefits to support transport scheme delivery. Projects such as March to Wisbech Rail Line have not demonstrated this in accordance with Government business case models to date. This is significant for unlocking the barriers, and secure funding to enable these transport schemes to be constructed. 2.3 This project aims to identify what is required to help facilitate the delivery of the Wisbech to March railway scheme and other essential transport infrastructure for Fenland. By developing and testing a range of scenarios around the economic viability of the Wisbech to March railway scheme, it is hoped to engage decision makers in conversation, about delivering the growth to finance this scheme and other major transport infrastructure in Fenland. Options for testing will include the Wisbech railway proposal as the core transport infrastructure needed, whilst setting this in the context of wider transport infrastructure as a network, major development and the growth needs of the district. Other specific schemes include A47 dualling, Wisbech Access Strategy, March Area Transport Strategy, Whittlesey Relief Road and the Fens Reservoir. A range of economic proposals will be developed for discussion with decision makers. A scoping paper setting out more details about the proposed project can be found in appendix 1 of this report. 2.4 It is proposed to set up a Project Board to oversee the governance and delivery of this project. The approach being suggested is already in operation for several CPCA funded projects in Fenland District including Fenland Stations Regeneration (Whittlesea Stn OBC) and Whittlesey Relief Road. Draft terms of reference are attached at appendix 2 for Cabinet discussion and approval. 2.5 A procurement exercise will be required to appoint a contractor to complete the economic assessment project. This will be managed and overseen by the Project Board. 2.6 A Grant funding agreement will be required between CPCA and FDC for the funding. Delegate authority is requested to approve and sign the agreement on behalf of FDC. 2.7 The project is expected to complete by March 2028.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
National Planning Scheme of DelegationAGREED to recommend to Council to: · Note the forthcoming implementation of a National Scheme of Delegation for plann...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.