What was decided
Cabinet noted the report and progress of the project at the end of RIBA Stage 3, and noted the expectation of a firm cost and a construct or do not construct decision in June 2026. Report P9
Cabinet noted the significant financial pressures on the Council and was asked to pay close attention to the financial assessment in the report. Report P8, P9
Cabinet authorised the Monitoring Officer, in advance of the June 2026 decision, to prepare all legal and procurement documentation so the Council can move promptly into the main Development Management Agreement if construction is approved. Report P9
Why
The existing pool and 1974 sports hall buildings are beyond their useful life, with conditions survey work to keep them running estimated at £4.5m, which Cabinet rejected in 2025 in favour of a longer term redevelopment. Report P6, P15, P30
The redevelopment is intended to provide a facility fit for purpose for 20+ years, broaden its appeal beyond sport, and attract more users while keeping operating costs low. Report P6, P15
The report highlights significant borrowing costs of around £82.91k per year for every £1m borrowed over 30 years, against a structural budget deficit of £2.615m, requiring close financial scrutiny. Report P8, P35
What happens next
Officers will complete RIBA Stage 4 detailed design by May 2026 and present a firm cost to Cabinet in June 2026. Report P6, P7, P20
A planning decision is targeted for late April or early May 2026, with the Council awaiting an outcome on a £2m Sport England grant application and approaching the Cambridgeshire and Peterborough Combined Authority for support. Report P7, P20
If construction is approved, the main works would start on site in August 2026, with the new facility opening in December 2027, followed by demolition of the old sports hall and a new car park by March 2028. Report P6
The money
- £18.67m Total estimated project budget including pre-construction costs and Sport England enhancements Report P6, P8, P20, P32
- £17.676m End of RIBA Stage 3 construction cost estimate, excluding pre-construction spend Report P20, P27
- £4.5m Conditions survey cost to keep existing buildings running, allowing for inflation Report P6, P15
- £2m Potential grant from Sport England the Council is bidding for Report P20
- £82.91k Estimated annual borrowing cost for every £1m borrowed over 30 years Report P8, P35
- £345,154 p.a. Estimated annual cost of the additional net borrowing required for the project Report P35
- £2.615m Structural deficit in the Council's budget that needs to be addressed Report P8
- £489,700 Estimated construction cost of the covered padel courts Report P25, 8.2
Options considered
- Chosen: Full redevelopment of the Manor Leisure Centre. Provides a facility fit for purpose for 20+ years, broadens appeal, and replaces a do minimum option Cabinet rejected in 2025 Report P6, P15, P30
- Rejected: Conditions survey investment of around £4.5m to keep existing buildings running. Considered wasted money on a facility beyond its useful life that would not serve the community for 20+ years Report P6, P30
- Rejected: Build a new facility adjacent to the current buildings. Estimated to cost around £10m more and deemed unaffordable Report P29
Implications
- Financial: Total estimated project cost is £18.67m, with annual borrowing costs of around £82.91k per £1m over 30 years, against an existing £2.615m structural budget deficit. Report P8, P20, P35
- Financial: Freedom Leisure is expected to pay an increased management fee, with anticipated uplift of £345,000 per year (excluding padel income) that could fund borrowing of £4.16m. Report P7
- Legal: The Monitoring Officer is authorised to prepare all legal and procurement documentation in advance so the Council can move promptly into the Development Management Agreement if Cabinet approves construction in June 2026. Report P9
- Equalities: Sport England design enhancements include improved changing provision and disabled access, with the redevelopment said to significantly enhance equality of use and access. Report P20, P29, 12.11
- Risk: Inflation of 4% per year could add around £707,000 or £59,000 per month of delay, and delay in signing contracts may increase construction costs.
- Risk: Risk register flags Local Government Reorganisation, planning conditions, utility diversions, ground conditions, and the outcome of the Sport England funding bid among the key live risks. Report P75, P76, P77, P58, P59, P60, P68, P69, P70
Who and where
- Residents of Whittlesey and surrounding villages Report P10, P29
- Leisure users travelling from the March area and Peterborough Report P6, P10
- Operator Freedom Leisure, which will run the new facility under a varied contract Report P7
- Users of the existing Manor Field, skate park, padel courts, play park, bowling, tennis, cricket and netball facilities Report P6
- Around 200 members of the local rifle club using the retained rifle range Report P31
Timeline
- December 2025: RIBA Stage 3 completed and planning application submitted Report P7, P16
- Late April / early May 2026: Target date for planning decision Report P7
- May 2026: RIBA Stage 4 detailed design completes, with firm cost and management fee uplift agreed Report P6
- June 2026: Cabinet decision on whether to proceed with construction Report P6
- Late July / early August 2026: Gym moves into former sports hall and pool building closes, then start on site
- January 2027: New padel courts and skate park completed and open for daylight use
- December 2027: Main redevelopment work completes and new facility opens Report P6
- January 2028: Demolition of former sports hall begins
- March 2028: New car park completed on former sports hall footprint
Plain English for the jargon
- RIBA: Royal Institute of British Architects. RIBA Stages 0 to 7 cover the design and construction process. Stage 3 is the developed design stage and Stage 4 is the technical design stage.
- MRP: Minimum Revenue Provision, the amount councils must set aside each year to repay borrowing.
- CPCA: Cambridgeshire and Peterborough Combined Authority, which the Council is approaching for potential financial support.