Resolved
AGREED to note the report.
AI summaryCabinet noted a Wisbech High Street project update, with a revised cost of £3.3M and a potential £600,000 FDC funding gap. A planning decision is expected in July 2026 and a Go/No Go decision is due at September Cabinet.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
AGREED to note the report.
Agenda Item 8 No:
Committee: Cabinet
Date: 13 July 2026
Report Title: Wisbech High Street Update
1 Purpose / Summary 1.1 To provide Cabinet with a monthly update regarding the pre-construction design and planning work for 11-12 High Street, Wisbech and associated funding opportunities
2 Key Issues 2.1 The required detailed design work has now reached an initial conclusion with plans submitted to the FDC Planning Dept and a decision on the application is expected in July. 2.2 The cost estimate prepared by quantity surveyors in the design team has seen an increase from an initial estimate of £3M to a revised figure now of £3.3M and this based on various factors including costings taken from 24 High Street and general pricing trends in the construction sector. We continue to work with funding providers including, but not limited to, NHLF and CPCA with additional options also being considered. 2.3 CPCA have indicated that their initial offer of monies in the sum of approximately £1.5m towards the project remains a possibility however a business case will be required, and this will need to go through the CPCA Shared Assurance Framework approval process. To this end, a fee quote for the works of preparing the specialist business case is being obtained and will be circulated to members prior to approval. This document is to be drafted in such a way that it will not only be suitable for submission to the CPCA but to the other identified sources of external funding 2.4 The completion of the planning submission has allowed the design team to concentrate on the preparation of the tender documents for circulation through the summer period. Once both the tenders and planning consent are received members will be asked to agree on the project next steps, i.e. do we proceed to construction or not. 2.5 The works to date is all being undertaken via different but parallel work streams and therefore the initially suggested target date for completion of the project of Autumn 2027 remains viable. 3 Funding Opportunities 3.1 We continue to work with funding providers including, but not limited to, NHLF and CPCA with additional options also being considered and progress in this respect is set out in greater detail below.
Potential Funding Source Amount CPCA £1,500,000 Town Board £200,000
NHLF £1,000,000 Total Potential Funding from External Partners £2,700,000 Projected Deficit for FDC to fund £600,000 (based on current projected cost estimate of £3.3M)
3.1CPCA 3.1.1 FDC Officers are currently working with Avison Young to prepare a full business case for the scheme to present to CPCA, Town Board and the NLHF. Avison Young have completed a draft Concept Paper in consultation with the CPCA and their requirements which is currently with the CPCA Economic Development team. Feedback once received will be circulated to CMT. 3.1.2 Over the past weeks, Avison Young have had helpful discussions with Judith Barker and, separately, Domenico Cirillo at CPCA. They set out the process for applying for CPCA funding. The key points are:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Wisbech High Street UpdateReport | 675 KB | DownloadRead as text |
Follow Cabinet at Fenland and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Nov 2026 | Review of District Wide Public Space Protection Orders (Dog Control)AGREED to: · Note the public and agency feedback in paragraph 4 and Appendix 1. · Approve the proposed Public Space P... | Agreed | Open |
| 16 Nov 2026 | Investment Board Update and Review of the Commercial and Investment StrategyAGREED: · To note the Investment Board report · That the ongoing review of the current Commercial and Investment Stra... | Agreed | Open |
| 16 Nov 2026 | Impact of LGR UncertaintyAGREED to: · Note the challenges that LGR is causing the Council; · Give some focus to the budget setting process for... | Agreed | Open |
| 19 Oct 2026 | Manor Leisure Centre UpdateAGREED to: · Note the progress made since February 2026; · Note that costs and delivery programme will be revised for... | Agreed | Open |
| 19 Oct 2026 | National Planning Scheme of DelegationAGREED to recommend to Council to: · Note the forthcoming implementation of a National Scheme of Delegation for plann... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.