CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Fenland District Council
Cabinet, Monday 14 September 2026 at 2.00pm

Wisbech High Street Update

Agreed Executive 1 paper

AI summaryFenland Cabinet authorises officers to award contracts worth up to £3.48M to complete the Wisbech High Street project through to handover at 11-12 High Street.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedS151 Officer with two portfolio holders, up to RIBA Stage 6
MoneyUp to £3.48MContract award value to project completion
What happens nextS151 Officer to approve contract awardsIn consultation with Finance and Social Mobility portfolio holders
Who it affectsMedworth wardWisbech High Street area

What was decided

Cabinet noted the monthly update report on pre-construction design and planning work for 11-12 High Street, Wisbech. Report 7.1

Cabinet authorised the Section 151 Officer, in consultation with the Portfolio Holder for Finance and the Portfolio Holder for Social Mobility and Heritage, to approve contract awards for the project up to the value of £3.48M, covering delivery through to the completion of RIBA Stage 6 (handover). Report 7.2

Why

The report is a monthly update on the pre-construction design and planning work for 11-12 High Street, Wisbech and associated funding opportunities. Report 7.1

Previous Cabinet and Council reports on 24 High Street and the Fenland Inspire! project provide background context for the 11-12 High Street work. Report P6, P7, P8

What happens next

The Section 151 Officer will consult with the relevant portfolio holders and approve the award of contracts to take the project through to RIBA Stage 6 handover. Report 7.2

The money

  • £3.48M Maximum value of contract awards authorised to project completion (RIBA Stage 6 handover) Report 7.2

Implications

  • Financial: Contract spend of up to £3.48M is approved in principle, subject to S151 Officer sign-off after consultation with portfolio holders. Report 7.2
  • Governance: Decision-making on contract awards is delegated from Cabinet to the S151 Officer working with named portfolio holders. Report 7.2

Who and where

  • Medworth ward Report 7.2
  • Wisbech High Street (11-12 and 24 High Street) area Report P6, P7, P8

Timeline

  • 2026-09-14: Cabinet decision to authorise contract awards up to £3.48M

Plain English for the jargon

  • RIBA Stage 6: The Royal Institute of British Architects design stage covering handover of the building on completion.
  • S151 Officer: The council's statutory chief finance officer, responsible for proper administration of financial affairs.
  • Forward Plan KEY/12AUG26/01: The council's published notice of the key decision to be taken.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCAB18/26

Resolved

AGREED that: · the report be noted; and · authorisation be given to the Section 151 Officer in consultation with the Portfolio Holder for Finance and Social Mobility and Heritage to approve the award of contracts for the delivery of the project to the completion of RIBA Stage 6 (handover) up to the value of £3.48M.
Word for word from the decision Fenland published for this meeting. Source: moderngov.fenland.gov.uk

Follow this further

Built from Fenland's papers

What the report saysPro

Report to Cabinet

Agenda Item 7 No:

Committee: Cabinet

Date: 14 September 2026

Report Title: Wisbech High Street Update

1 Purpose / Summary

1.1To provide Cabinet with a monthly update regarding the pre-construction design and planning work for 11-12 High Street, Wisbech and associated funding opportunities.

2 Design Update

2.1A full planning application is with the planning team and validated with a projected decision due to go before Members at the 23 September 2026 Planning Committee meeting. Consultations on the application have resulted in three queries / requirements to date:

• The FDC Conservation Officer has requested amendments to the rainwater goods design on the front elevation to ensure it is in keeping with the historic nature of the area. This has been actioned and a redesign submitted for approval; • The FDC Ecology Officer has requested a bat survey to ensure there are no bats present on site which would be impacted by any development. Disturbing bats has strict legal implications for any developer and is not allowed. These visits have been completed (3-week interval between visits as required under the legal requirements) with no evidence of bats and a report submitted to this effect; • Anglian Water are objecting on the basis they do not want discharging to the mains and have asked why a soakaway solution was not used. Our engineers have responded on this pointing out the high-water table in Wisbech makes this solution unworkable.

2.2The cost estimate prepared by quantity surveyors in the design team has seen an increase from an initial estimate of £3M to a revised figure now of £3.3M and this is based on various factors including costings taken from 24 High St and general pricing trends in the construction sector.

2.3The tenders are now being progressed via the FDC procurement team. A government framework is being employed to ensure procurement compliance and pre-approved bidders thus reducing the tender period required. This is subject to there being enough interest in the project to receive adequate competitive bids. Alternative solutions are being looked at should further companies need to be approached. 2.4 The work to date is all being undertaken via different but parallel work streams and therefore the initially suggested target date for completion of the project of Autumn 2027 remains viable and officers are clearly aware and minded that a hard delivery date of 2027 is required to fulfil members expectations under the Inspire project.

3 Funding Opportunities

3.1We continue to work with funding providers including but not limited to NHLF and CPCA with additional options also being considered and progress in this respect is set out in greater detail below.

Potential Funding Source Amount CPCA £1,500,000 Town Board £ NIL

NHLF £1,000,000 Total Potential Funding from External Partners £2,500,000 Projected Deficit for FDC to fund £800,000 (based on current projected cost estimate of £3.3M)

3.1CPCA

3.1.1 A concept paper and full business case has now been submitted to the CPCA for the £1.5m portion of funding towards the project.

3.1.2 Next steps:

• The concept paper and business case was submitted to CPCA in June and August respectively. The concept paper is scheduled to be presented by CPCA officers at the next Funding Panel meeting on 22 September.

• Subject to approval, it will then progress to the Funding Committee on 12 October and subsequently to the Combined Authority Board on 25 November.

• Based on this timetable and discussions with CPCA, it is anticipated that the earliest FDC will be in receipt of a GFA will be January 2027.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Wisbech High Street UpdateReport 135 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
CB
Councillor Chris BodenChairman, present
MJ
Councillor Mrs Jan FrenchVice-Chairman, present
GC
Councillor Gary ChristyCommittee Member, apologies
SC
Councillor Steve CountCommittee Member, apologies
MS
Councillor Miss Samantha HoyCommittee Member, present
SI
Councillor Sidney ImafidonCommittee Member, present
MD
Councillor Mrs Dee LawsCommittee Member, present
CS
Councillor Christopher SeatonCommittee Member, present
ST
Councillor Steve TierneyCommittee Member, present
SW
Councillor Susan WallworkCommittee Member, present
LA
Linda AlbonOfficer, expected

On this subject at Fenland

Search all
  1. Wisbech High Street UpdateThis decision
  2. Wisbech High Street UpdateAgreed
  3. Wisbech High Street UpdateAgreed
  4. Wisbech High Street UpdateAgreed

More from Fenland Cabinet

All decisions
MeetingDecisionOutcome
16 Nov 2026 Review of District Wide Public Space Protection Orders (Dog Control)AGREED to: · Note the public and agency feedback in paragraph 4 and Appendix 1. · Approve the proposed Public Space P... Agreed Open
16 Nov 2026 Investment Board Update and Review of the Commercial and Investment StrategyAGREED: · To note the Investment Board report · That the ongoing review of the current Commercial and Investment Stra... Agreed Open
16 Nov 2026 Impact of LGR UncertaintyAGREED to: · Note the challenges that LGR is causing the Council; · Give some focus to the budget setting process for... Agreed Open
19 Oct 2026 Manor Leisure Centre UpdateAGREED to: · Note the progress made since February 2026; · Note that costs and delivery programme will be revised for... Agreed Open
19 Oct 2026 National Planning Scheme of DelegationAGREED to recommend to Council to: · Note the forthcoming implementation of a National Scheme of Delegation for plann... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies