Resolved
It was agreed that the use of a bulletin board would be a useful tool to update members on progress. The committee noted the update.
Overview and Scrutiny Committee agreed this item on Thursday 25 March 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
It was agreed that the use of a bulletin board would be a useful tool to update members on progress. The committee noted the update.
Work to accelerate the Five Acres project started last spring and the project brief was clarified to ensure options explored would deliver against the Council’s ambitions for the site to provide sport, leisure and community focussed development supported by commercial development that was fitting for that location. The Council wishes to deliver against its priorities which include supporting community wellbeing; promoting active and healthy lifestyles and promoting a network of health and leisure facilities which deliver an asset based approach to community development. Where practical the Council wants to support plans for the Five Acres site set out in the Neighbourhood development plan.
Work that had been carried out previously on the project was reviewed and this identified certain actions, including closer engagement with West Dean Parish Council and the need to seek a site acquisition agreement with Homes England that did not include terms which placed the Council at an unacceptable financial risk.
In September soft market testing was commissioned to identify the commercial interest in the site. As expected the Covid-19 pandemic was affecting commercial interest and many businesses in the leisure, entertainment, hotel and food and beverage industries were pausing or scaling back expansion and some have closed some premises or ceased trading.
The original business case for the site which was prepared in 2018 was predicated on the destination leisure facility being financially underpinned by a hotel and catering (or some other form of enabling development) offer as the leisure facility would not cover its costs in its own right. At that time there were a number of enabling developments and projects available to us that were being investigated and would have provided the necessary financial return.
The Council previously agreed to acquire the site subject to an acceptable business case being developed. Once the Council acquires the site it will start incurring costs and therefore it requires a clear and viable plan to redevelop the site before it proceeds to purchase Five Acres.
Financial position
The Council sees the project as a regeneration project, one which will provide valuable facilities, create new jobs and attract visitor spend for local communities. This means the development needs to try and achieve a break even position, not necessarily generate a profit and provide a net income to the Council. The Council can also take into account the social and community value in any redevelopment or regeneration. However if the development will operate at a loss then a deficit in revenue income will need to be met either by the Council or by some other means. Any extra spend by the Council may have a detrimental effect to other council services as the Council does not have a substantial pot of money it can use to plug this funding gap.
Any business case for site development needs to include:
Capital costs Demolition and site clearance, Project management, consultancy and costs in obtaining planning permission and other consents. Construction or renovation of new or existing buildings The cost of borrowing that capital, with loan repayments incorporated into annual costs over a loan period of 50 years
Revenue Costs Running costs - business rates, utility costs, maintenance, repairs, kit & equipment Management costs - staffing and other overheads
Income Any funding that may be attracted - S.106 contributions, external grant funding Customer payments for leisure services or memberships Renting space to groups or businesses
Development of options
The soft market testing demonstrated that there was little current commercial interest in the site that would provide the income needed to deliver a destination leisure facility. The Council therefore developed a number of options to consider a scaled back leisure facility with some community space which could be used flexibly to meet local needs.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Five Acres UpdateReport | 174 KB | DownloadRead as text |
Follow Overview and Scrutiny Committee at Forest of Dean and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Jul 2023 | The Scrutiny PlanAgreed by assent. Clarification was sought if participants on the panel, were expected to attend all the sessions? If... | Agreed | Open |
| 20 Jul 2023 | Performance Service Report - 2022-23 Quarter FourAgreed by assent. | Agreed | Open |
| 20 Jul 2023 | Performance and Finance PanelAgreed by assent | Agreed | Open |
| 7 Jul 2022 | The scrutiny planAgreed by assent to postpone Item 9 Biffa Update. Members queried why was there no representative present? Apologies ... | Agreed | Open |
| 3 Mar 2022 | Cinderford Northern QuarterIt was agreed, that a further Cinderford Northern Quarter Inquiry evidence gathering session would be held on Monday,... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.