Resolved – That Cabinet: a) Approves the Design & Build approach for the main contract of work; b) Approves the Two-Stage open market procurement option to identify a main contractor early in the design process; c) Delegates authority to implement this procurement strategy, appointing a main contractor and entering into a Pre-Construction Agreement to the Head of Paid Services, in consultation with the Section 151 Officer, Head of Legal Services, Group Manager Property & Regeneration, the Deputy Leader and Cabinet Member for Communities.
Word for word from the decision Forest of Dean published for this meeting.Source: meetings.fdean.gov.uk
FODDC Council name Name and date of CABINET – 13 OCTOBER 2022 Committee Report Number LD.697 Subject Five Acres Community Leisure Hub – Main contractor procurement Wards affected Berry Hill Accountable Cllr Paul Hiett Deputy Leader and Cabinet Member for Communities member Tel: 01594 810000 Email: [email protected] Accountable officer Wendy Jackson, Regeneration Manager Tel: 01594 812645 Email: [email protected] Summary/Purpose The Five Acres Levelling Up redevelopment project is underway. This report seeks Cabinet approval to prepare for the construction stage, identify a main contractor early in the design process and provide officers with the delegated authority to proceed with the first phase of development. A Cabinet and possibly a Full Council decision will be needed in December 2022 to approve the budget estimate from the contractor prior to any further work commencing on site. Recommendations That Cabinet resolves to: a) Approve the Design & Build approach for the main contract of work; b) Approve the Two-Stage open market procurement option to identify a main contractor early in the design process; c) Delegate authority to implement this procurement strategy, appointing a main contractor and entering into a Pre-Construction Agreement to the Head of Paid Services, in consultation with the Section 151 Officer, Head of Legal Services, Group Manager Property & Regeneration, the Deputy Leader and Cabinet Member for Communities. Corporate priorities 1.1. COMMUNITY: Improve community, wellbeing, supporting and celebrating our distinctiveness. 1.2. ECONOMY: Develop a vibrant economy that is resilient and future proof. 1.3. ENVIRONMENT: Protect and enhance the local environment and address the climate emergency. 1.4. SERVICES & FINANCE: Deliver great services through achieving financial sustainability. Key Decision 1.5. NO Exempt 1.6. NO Consultees/ 1.7. Cabinet members Consultation
BACKGROUND 1.8. The Five Acres site is the former further education and leisure centre site in Berry Hill on the outskirts of Coleford. The Council acquired the site from Homes England in 2021. The site forms part of a £20m multiple project Levelling Up Fund (LUF) regeneration project for the District Council. A total of approximately £10.7m funding is currently available for the Five Acres project - £9.2m LUF funding and £1.57m Council funding. The eligible LUF expenditure period runs from April 2021 through to March 2025. 1.9. The project includes the refurbishment of the existing Speedwell building to create a new community sports/leisure/education hub with ancillary car parking; refurbishment of existing tennis courts; a new build 4-court sports hall also suitable for use as a performance venue, a 3G artificial sports pitch; sports pavilion; cycle hub; external sports equipment storage facility; car parking to include electric vehicle charge points. FoDDC is looking to refurbish and build to a high environmental specification to meet the local zero carbon 2030 target and the LUF funding terms and conditions. 1.10. The project will be approached in two distinct phases. Phase 1 is to include Speedwell House, new Leisure Centre and associated external works. Phase 2 is to include the 3G pitch, pavilion, tennis courts and associated external works.
2. PROCUREMENT ROUTES 2.1. To decide which procurement route to proceed with, the Council needs to be aware of the advantages and disadvantages of both Traditional and Design & Build procurement routes, and also single stage versus two stage tendering along with how much control over design the Council wish to retain. 2.2. Consideration is also required on the selection of the design consultants to support the project. The following is a summary of the inherent features of the alternative approaches and their advantages and disadvantages.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Quarter Performance Report - Period OneResolved, that Cabinet: 1. Notes overall progress on the Council priorities and service performance for 2026-27 Q1. A...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.