Resolved
Resolved, that Cabinet: A) Noted the 2024-25 Quarter One Financial Performance report. Agreed by assent.
Cabinet noted this item on Thursday 12 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved, that Cabinet: A) Noted the 2024-25 Quarter One Financial Performance report. Agreed by assent.
FOREST OF DEAN DISTRICT COUNCIL
Name and date of Cabinet: 12 September 2024 Committee
Report Number F.696
Subject Financial Performance Report 2024-25 Quarter One
Wards affected All
Accountable member Cllr Andy Moore – Cabinet Member for Assets, Finance and Waste Tel: 01594 810000 Email: [email protected]
Accountable officer Andrew Knott – Chief Finance (S151) Officer Tel: 01594 812416 Email: [email protected]
Summary/Purpose This report provides details of the Council’s financial performance for 2024- 25 Quarter One. The report enables Councillors to assess financial performance and to be assured that progress is being made in achieving the Council’s Medium Term Finance Strategy.
Annexes Annex A – Cost centre analysis
Recommendation It is recommended that: (a) The 2024-25 Quarter One Financial Performance report is noted 1. Develop a vibrant economy that is resilient and future proofed Corporate priorities 2. Deliver great services through ensuring financial sustainability Key Decision 1.1. No
Exempt 1.2. No 1. BACKGROUND
1.1Each quarter, the Council monitors its progress towards achieving its aims and priorities as set out in the Corporate Plan including the financial performance of the Council.
2. FINANCIAL PERFORMANCE
2.1Within Annex A, there is a breakdown of the forecasted yearly performance for each cost centre following a review of the financial performance by the Business Partner Accountants and Chief Accountants within Publica. This shows the areas where forecasts have changed since the original revenue budget was set.
2.2In Quarter 1 2024/25, a number of areas have been identified as issues within the financial performance. These are mainly due to income challenges and more information known since the budget was set in February 2024.
2.3There will not be a budget virement made in Q1 2023/24 as the numbers that are provided in this report need to be developed further and major items like pay awards are still to be agreed.
2.4There are currently 7 areas of change. These are as follows:
2.4.1. External Audit Costs - These are higher than expected due to more work required on the Housing Benefit Audit than originally expected.
2.4.2. Forest Lottery Income – This is lower than budgeted at present and is expected to come in below budget for the rest of the year.
2.4.3. Publica – There is currently expected to be a saving of £34k against the £30k savings challenge for Publica this financial year as at Q1.
2.4.4. Waste Income and Cost – Moving to Ubico was expected to make a saving of around £50k however this is currently forecasted as £10k due to additional costs for leasing and insuring of the Depot however expected increased income has been able to mitigate the majority of these costs.
2.4.5. Environmental Protection – Income is expected to be slightly down within this area however a review is needed to understand if anything can be done to improve this situation.
2.4.6. Building Control – Income is expected to be lower by £160k however more detail is needed around this as there will be staff savings to mitigate some of this and more information is needed around what can be done to increase revenue going forward especially when the service is returned to the Council.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
F.696 Annex A: Cost centre AnalysisAppendix | 372 KB | Download |
PDF |
Financial Performance Report 2024-25: Q1Report | 443 KB | DownloadRead as text |
Follow Cabinet at Forest of Dean and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Introduction of James watch to Forest Linkline & Cotswold Careline product rangeResolved , that Cabinet: 1. Approves the introduction of the James Watch service within Forest Linkline and Cotswold ... | Approved | Open |
| 10 Sep 2026 | Health and Safety PoliciesResolved , that Cabinet; 1. Approves the implementation of the attached Health and Safety Delegated Responsibility Fr... | Approved | Open |
| 10 Sep 2026 | Quarter Performance Report - Period OneResolved, that Cabinet: 1. Notes overall progress on the Council priorities and service performance for 2026-27 Q1. A... | Agreed | Open |
| 10 Sep 2026 | Financial Performance Report - Period OneResolved, that Cabinet; 1. Notes the 2026-27 Quarter One Financial Performance report and, 2. That the Business Rates... | Agreed | Open |
| 9 Jul 2026 | Conservation Areas SWOT Analysis: Explorer Hubs and Summary SheetsResolved, that Cabinet: Noted the value of the analysis undertaken and support its appropriate use and application in... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.