Financial Performance Report - Period Three

Approved Executive 4 papers

AI summaryForest of Dean Cabinet notes Quarter Three financial performance showing a £156,130 underspend forecast for 2025-26, with the surplus to be moved to reserves.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCabinet noted 2025-26 Q3 performance and a virement
Money£156,130 forecast underspendNet cost of services less than original budget
What happens nextSurplus to be transferred to reservesMovements to Publica, Maintenance, Planning, Deficit reserves
Who it affectsAll wards in Forest of DeanCouncil-wide revenue and capital budgets

What was decided

Cabinet noted the 2025-26 Quarter Three Financial Performance report. Report P9

Cabinet noted the budget virement in Annex B that the Chief Finance (S151) Officer had approved. Report P9

The forecast net cost of services for 2025-26 is £156,130 below the current budget, with the surplus to be moved into reserves. Report 2.3, P24

Why

The council monitors progress each quarter against its Corporate Plan and Medium Term Financial Strategy. Report P10, P7

Quarterly updates help ensure a balanced budget can be set and maintained. Report P22, P23

Cost centre reviews by Business Partner Accountants and Chief Accountants identified changed forecasts since the original revenue budget was set. Report P11, 2.2

What happens next

The forecast surplus of £156,130 will be transferred to reserves, including £100,000 back to the Publica Review Reserve, £76,000 to the Maintenance Reserve, £40,000 to the Planning Equalisation Reserve and £14,930 to the Budget Deficit Reserve. Report 2.3, P24

Capital spending on Five Acres and vehicle purchases is likely to be moved into 2026/27, confirmed through the budget setting process. Report P21

A full review of higher than expected cemetery team costs is underway.

The money

  • £156,130 Forecast underspend on net cost of services for 2025-26 Report 2.3, P13
  • £10,000 Shortfall in Forest Lottery income
  • £8,000 Shortfall in Land Charges income
  • £25,000 Shortfall in court fees from Council Tax collection
  • £40,000 Less car parking direct income, partly offset by £10,000 extra from permits
  • £5,000 Shortfall in green waste licences income
  • £2,240 Shortfall in refuse bag sales
  • £4,500 Shortfall in textiles sale income
  • £107,560 Additional Extended Producer Responsibility funding for 2025-26, bringing total to £1,501,426
  • £5,000 Shortfall in environmental protection sampling income
  • £40,000 Additional Planning Fees income, moved to Planning Equalisation Reserve
  • £60,000 Shortfall in treasury management investment income
  • £109,800 Additional business rates pooling income from Gloucester Business Rates Pool
  • £10,000 Additional election expenditure from district and parish by-elections
  • £12,000 Saving in Emergency Planning
  • £40,000 Additional cost for a new HR advisor following the Publica review
  • £90,000 Saving against Ubico budget
  • £50,000 Additional cemetery team costs
  • £14,000 Additional bank charges from more online and card payments
  • £12,500 Additional cost for tree works across the council estate
  • £20,000 Additional cost for bin purchases
  • £115,680 Additional building control staff costs, partly offset by £46,970 of extra income
  • £25,000 Saving in communications, with the budget retained for 2026/27
  • £25,000 Savings from borrowing not required in 2025-26
  • £100,000 Moved back to the Publica Review Reserve
  • £76,000 Moved back to the Maintenance Reserve for 2026/27
  • £14,930 Allocated to the Budget Deficit Reserve from Q3 savings
  • £405,502 Total MTFS savings and income achieved in 2025-26, 61% of the £668,110 target Report P20
  • over £11m Spent on Five Acres across the three Levelling Up partners since funding was confirmed Report P21

Options considered

  • Chosen: Note the 2025-26 Quarter Three Financial Performance report. Recommended action to allow Cabinet to assess financial performance and progress against the Medium Term Financial Strategy. Report P9
  • Chosen: Note the budget virement in Annex B approved by the S151 Officer. Recommended action to record virements signed off by the Chief Finance Officer. Report P9

Implications

  • Financial: Forecast net cost of services is £156,130 below the current budget, with the surplus to be transferred to earmarked reserves. Report 2.3, P24
  • Financial: Three red and two amber savings targets remain in the 2025-26 MTFS, with budget amendments made in Q3 for the amber items. Report P15
  • Financial: Land Charges, Food Safety and Licensing income targets are uncertain and were amended at Q2 budget monitoring. Report P15
  • Risk: Regular quarterly reporting is needed to understand variances and protect future years' budgets if savings targets are missed. Report P23
  • Legal: The council has a duty to set a balanced budget, supported by regular quarterly updates. Report P22
  • Staffing: An additional £40,000 cost for a new HR advisor follows phases 1 and 2 of the Publica review.

Who and where

  • All wards in the Forest of Dean district Report P4
  • Council tax and business rate payers through financing lines Report P13
  • Residents using car parking, planning, waste, refuse, green waste and cemetery services

Timeline

  • 12 March 2026: Cabinet noted the Q3 financial performance report Report P1
  • 2025-26 Quarter Three: Forecast net expenditure £156,130 below budget; £40,000 extra in building control agency costs Report 2.3
  • By 31st of March 2026: Expected parish Council by-elections contributing to £10,000 extra election costs
  • 2026/27: Comms budget of £25,000 carried forward; £76,000 maintenance reserve to be spent; Five Acres and vehicle capital likely to be moved here

Plain English for the jargon

  • MTFS: Medium Term Financial Strategy, the council's plan for balancing its budget over several years.
  • S151 Officer: The local authority's Chief Finance Officer, with statutory responsibility for financial administration.
  • Virement: Movement of budget between cost centres, approved here by the S151 Officer.
  • EPR: Extended Producer Responsibility, a funding mechanism for waste services.
  • CT/NNDR: Council Tax and National Non-Domestic Rates (business rates).
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

Resolved , that Cabinet notes; a) The 2025-26 Quarter Three Financial Performance report; and b) The budget virement in Annex B approved by the Chief Finance (S151) Officer . Agreed by assent.
Word for word from the decision Forest of Dean published for this meeting. Source: meetings.fdean.gov.uk

Follow this further

Built from Forest of Dean's papers

What the report saysPro

Report to Cabinet

Name and date of CABINET: 12 MARCH 2026 Committee

Report Number F.773

Subject FINANCIAL PERFORMANCE REPORT 2025-26 QUARTER THREE

Wards affected All

Accountable member Cllr Andy Moore – Cabinet Member for Assets and Finance Email: [email protected]

Accountable officer Andrew Knott – Chief Finance (S151) Officer Tel: 01594 812416 Email: [email protected]

Summary/Purpose This report provides details of the Council’s financial performance for 2025- 26 Quarter three. The report enables Councillors to assess financial performance and whether progress is being made in achieving the Council’s Medium Term Finance Strategy.

Annexes Annex A – Cost Centre Analysis Annex B – Budget virements Annex C – Latest Capital Programme

Recommendation It is recommended that Cabinet notes: (a) The 2025-26 Quarter Three Financial Performance report; and (b) The budget virement in Annex B approved by the Chief Finance (S151) Officer 1. Develop a vibrant economy that is resilient and future proofed Corporate priorities 2. Deliver great services through ensuring financial sustainability Key Decision No

Exempt No 1. BACKGROUND 1.0. Each quarter, the Council monitors its progress towards achieving its aims and priorities as set out in the Corporate Plan including the financial performance of the Council.

2. FINANCIAL PERFORMANCE 2.1. Within Annex A, there is a breakdown of the forecasted yearly performance for each cost centre following a review of the financial performance by the Business Partner Accountants and Chief Accountants within the Forest of Dean and Publica. This shows the areas where forecasts have changed since the original revenue budget was set.

2.2A Summary of this is below:

Cost of Services Original Current Forecast Year End Cost Centre Description Budget Budget Budget Variance Strategy 4,788,500 4,592,850 4,537,830 (55,020) Built Environment 791,600 824,350 849,350 25,000 Finance 5,761,030 5,999,910 5,864,590 (135,320) Nature Emergency 337,430 337,430 342,930 5,500 Sustainable Economy 411,510 385,440 385,440 - Climate Emergency 721,120 753,780 753,780 - Local Plan 854,840 1,045,630 1,074,340 28,710 Thriving Communities 1,056,730 1,180,470 1,155,470 (25,000) Net Cost of Services 14,722,760 15,119,860 14,963,730 (156,130) Financed by Capital Charges (308,900) (308,900) (308,900) - Interest and Investment Income and Expenditure (823,950) (823,950) (788,950) 35,000 Transfers to / from (-) Earmarked Reserves (531,320) (759,220) (528,290) 230,930 CT/NNDR and Government Grants (13,058,590) (13,227,790) (13,337,590) (109,800) Financing (14,722,760) (15,119,860) (14,963,730) 156,130

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
F.773: Annex A: Cost Centre AnalysisAppendix 182 KB Download
PDF
F.773: Annex B: Q3 Budget VirementAppendix 36 KB Download
PDF
F.773: Annex C: Capital ProgrammeAppendix 15 KB Download
PDF
Financial Performance Report: Period ThreeReport 233 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
JF
Councillor Jackie FraserCommittee Member, in attendance
AM
Councillor Andy MooreVice Chair, present
AB
Councillor Adrian BirchChair, present
JL
Councillor Johnathan LaneCommittee Member, present
CM
Councillor Chris McFarlingCommittee Member, present
SP
Councillor Sid PhelpsCommittee Member, present
AB
Andy BargeOfficer, in attendance
NB
Nigel BrinnChief Executive Officer, in attendance
AK
Andrew KnottOfficer, in attendance
SR
Sue RobusOfficer, in attendance
JD
Councillor Jackie DaleCommittee Member, present
HC
Helen ClarkeOfficer, in attendance

All 19 on the meeting page

On this subject at Forest of Dean

Search all
  1. Financial Performance Report - Period ThreeThis decision
  2. Financial Performance Report - Period OneAgreed
  3. Financial Performance Report - Period FourApproved
  4. Financial Performance Report - Period twoNoted
  5. Financial Performance Report - Period oneAgreed
  6. Financial Performance Report - Period fourApproved

More from Forest of Dean Cabinet

All decisions
MeetingDecisionOutcome
10 Sep 2026 Introduction of James watch to Forest Linkline & Cotswold Careline product rangeResolved , that Cabinet: 1. Approves the introduction of the James Watch service within Forest Linkline and Cotswold ... Approved Open
10 Sep 2026 Health and Safety PoliciesResolved , that Cabinet; 1. Approves the implementation of the attached Health and Safety Delegated Responsibility Fr... Approved Open
10 Sep 2026 Quarter Performance Report - Period OneResolved, that Cabinet: 1. Notes overall progress on the Council priorities and service performance for 2026-27 Q1. A... Agreed Open
10 Sep 2026 Financial Performance Report - Period OneResolved, that Cabinet; 1. Notes the 2026-27 Quarter One Financial Performance report and, 2. That the Business Rates... Agreed Open
9 Jul 2026 Conservation Areas SWOT Analysis: Explorer Hubs and Summary SheetsResolved, that Cabinet: Noted the value of the analysis undertaken and support its appropriate use and application in... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies