Quarter Performance Report - Period Three

Noted Executive 2 papers

AI summaryCabinet noted Forest of Dean's Q3 2025-26 performance, with planning, waste and leisure exceeding targets while benefit processing, land charges and FOI responses trailed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted overall progress on priorities and services
MoneyNoneReport states no direct financial implications
What happens nextRecovery actions underwayLand charges and FOI performance being addressed
Who it affectsAll wardsCouncil-wide services and residents

What was decided

Cabinet noted overall progress on the Council's priorities and service performance for 2025-26 Quarter Three. Report P1

Why

Most services performed strongly: customer satisfaction reached 99.22% against a 90% target, 100% of major planning applications were determined in time, and leisure centre visits hit 114,522 against a 72,500 target. Report 5.1, P14

Some services fell short: Housing Benefit change of circumstances averaged 8.45 days against a 4-day target, Land Charges searches within 10 days fell to 43.01% against 90%, and FOI response within 20 days was 81.48% against 90%. Report 5.3, P18, P19

What happens next

Land Charges performance is recovering, rising from 13% in September to 60% in December after additional administrative support was brought in. Report P18

The Council is reviewing FOI processes, streamlining request handling and reinforcing awareness of statutory response times. Report P19

Progress on the Council Plan, including EV charging rollout, Five Acres regeneration, Local Area Energy Planning and the Active Wellbeing Strategy, will continue to be tracked quarterly in the Delivery Plan. Report 2.3, 2.4

Options considered

  • Chosen: Note the Q3 2025-26 performance report. Standard quarterly performance oversight by Cabinet Report P1

Implications

  • Legal: A failure to meet statutory deadlines or standards in some services may expose the Council to legal challenge and financial liability. Report P26
  • Climate: Increasing digital service provision may reduce residents' need to travel to Council offices, cutting district carbon emissions. Report P29
  • Financial: No direct financial implications arise from the report itself. Report P25
  • Risk: The Publica Partnerships risk score has increased to reflect potential cost pressures from the company's financial rebasing; shareholder directors have been appointed and a new operational performance forum is in place. Report P12

Who and where

  • All residents across the Forest of Dean district Report P1
  • Households receiving Housing Benefit or Council Tax Support Report 5.3
  • Applicants for planning permissions and land charge searches Report 5.1, P18
  • Business ratepayers and council taxpayers Report 5.2
  • Users of the Council's leisure centres Report 5.1

Timeline

  • 14th December 2023: Full Council approved the 2024-2028 Council Plan
  • November: Community Safety Partnership met to focus on youth diversion and ambulance service collaboration Report 2.3
  • December: Cabinet approved the Active Wellbeing Strategy, moving it into delivery Report 2.3
  • January: Cabinet approved the draft Biodiversity Duty Action Plan Report 2.3
  • February 2026: Further EV charging car park site scheduled for completion; new covered market planned for Cinderford Report 2.3
  • March: Community engagement events scheduled to launch Active Wellbeing Strategy implementation Report 2.3
  • 12 March 2026: Cabinet considered the Q3 2025-26 performance report Report P1

Plain English for the jargon

  • KPI: Key Performance Indicator, a measurable value showing how well a service is performing
  • FOI: Freedom of Information request, a statutory right to access information held by public bodies
  • DFG: Disabled Facilities Grant, funding for home adaptations to help disabled people live independently
  • DELTA: Government online platform used to collect Disabled Facilities Grants data from local authorities
  • UKSPF: UK Shared Prosperity Fund, central government funding for local growth projects
  • LIFT: Low Income Family Tracker, a council tool for identifying households needing financial support
  • Publica: A shared services company providing functions to the Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

Resolved, that Cabinet: 1. Noted the overall progress on the Council priorities and service performance for 2025-26 Q3. Agreed by assent.
Word for word from the decision Forest of Dean published for this meeting. Source: meetings.fdean.gov.uk

Follow this further

Built from Forest of Dean's papers

What the report saysPro

Report to Cabinet

Name and date of CABINET – 12 MARCH 2026 Committee Report number HPS.162 Subject SERVICE PERFORMANCE REPORT 2025-26 QUARTER THREE Wards affected All Accountable member Adrian Birch – Leader of the Council Email: [email protected] Accountable officer Nigel Brinn – Chief Executive Tel: 01594 812300 Email: [email protected] Report author Alison Borrett – Senior Performance Analyst Email: [email protected] Summary/Purpose To provide an update on progress on the Council’s priorities and service performance Annexes Annex A – Performance Report Recommendation(s) That Cabinet resolves to: 1. Note overall progress on the Council priorities and service performance for 2025-26 Q3.

Corporate priorities  Foster resilient and inclusive communities that are motivated and competent to adapt to the challenges and opportunities posed by the climate and nature emergencies  Protect and enhance the Forest of Deans natural environment and be on target to be carbon neutral by 2030  Foster economic prosperity while ensuring environmental sustainability and social well-being Key Decision NO Exempt NO Consultees/ Publica Directors, Business Managers, Service Managers and Service Consultation Leads. 1. BACKGROUND 1.1 In October 2023, the Cabinet approved an enhanced Performance Framework that affords a more complete picture of corporate performance and includes a more visual way to show how Council performance is progressing. The Framework, depicted below, broadens the focus from Service based KPIs to include performance relating to the Corporate Plan, place- based measures, Risk and Project Management.

1.2The approved framework incorporates key principles that embody the behaviours and attitudes necessary for success. These principles include:

 Data-Driven: Our decisions are based on accurate and timely performance data.  Transparent: We are constructive and open about our successes and areas that need improvement, current performance data is shared with everyone in the partnership.  Accountable: There are clear roles and responsibilities for defining, analysing and managing performance.  Engagement: Everyone should have an opportunity to engage in performance assessment, by ensuring we focus on relevant things and publish current performance.  Continuous Improvement: We celebrate good performance as an opportunity to learn and weaker performance as an opportunity to enhance services and innovate.

1.3Effective governance of the framework is maintained through clearly defined roles and responsibilities. These roles ensure that success is well-defined, performance is reported accurately, and day-to-day management is consistent. Specifically:

 Cabinets and Executives: Define local priorities, strategic measures of success and agree the strategic approach to performance assurance.  Data and Performance Capability: Support the development of strategic indicators, collect, analyse and report performance.  Assistant Directors & Business Managers: Implementation of the Performance Framework within their areas and ensure that performance is effectively managed to the agreed standard.  Staff: Contribute to setting and achieving performance objectives through their work and teams.

1.4The Council’s Chief Executive is responsible for reviewing and approving the information provided in this report prior to its publication.

2. COUNCIL PLAN PRIORITY ACTIONS AND PROJECT ASSURANCE 2.1 A new Council Plan for 2024-2028 was approved by Full Council on 14th December 2023 where a Delivery Plan, setting out how the priorities within the Council Plan will be delivered, followed. In this Delivery Plan each of the three priorities have workstreams against them detailing the actions being taken to deliver them.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
HPS.162 Annex A: Performance ReportAppendix 6.7 MB Download
PDF
Quarter Performance Report: Period ThreeReport 580 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 19 attended
JF
Councillor Jackie FraserCommittee Member, in attendance
AM
Councillor Andy MooreVice Chair, present
AB
Councillor Adrian BirchChair, present
JL
Councillor Johnathan LaneCommittee Member, present
CM
Councillor Chris McFarlingCommittee Member, present
SP
Councillor Sid PhelpsCommittee Member, present
AB
Andy BargeOfficer, in attendance
NB
Nigel BrinnChief Executive Officer, in attendance
AK
Andrew KnottOfficer, in attendance
SR
Sue RobusOfficer, in attendance
JD
Councillor Jackie DaleCommittee Member, present
HC
Helen ClarkeOfficer, in attendance

All 19 on the meeting page

On this subject at Forest of Dean

Search all
  1. Quarter Performance Report - Period ThreeThis decision
  2. Quarter Performance Report - Period OneAgreed
  3. Quarter Performance Report - Period FourAgreed
  4. 2025/26 treasury management activity and performance as at 30 september 2025, and treasury management prudential indicators - quarter twoApproved
  5. Quarter Performance Report - Period twoNoted
  6. Quarter Performance Report - Period oneAgreed

More from Forest of Dean Cabinet

All decisions
MeetingDecisionOutcome
10 Sep 2026 Introduction of James watch to Forest Linkline & Cotswold Careline product rangeResolved , that Cabinet: 1. Approves the introduction of the James Watch service within Forest Linkline and Cotswold ... Approved Open
10 Sep 2026 Health and Safety PoliciesResolved , that Cabinet; 1. Approves the implementation of the attached Health and Safety Delegated Responsibility Fr... Approved Open
10 Sep 2026 Quarter Performance Report - Period OneResolved, that Cabinet: 1. Notes overall progress on the Council priorities and service performance for 2026-27 Q1. A... Agreed Open
10 Sep 2026 Financial Performance Report - Period OneResolved, that Cabinet; 1. Notes the 2026-27 Quarter One Financial Performance report and, 2. That the Business Rates... Agreed Open
9 Jul 2026 Conservation Areas SWOT Analysis: Explorer Hubs and Summary SheetsResolved, that Cabinet: Noted the value of the analysis undertaken and support its appropriate use and application in... Noted Open