RESOLVED - ( i ) That the estimated final outturn relating to the integrated transport capital programme for 2015/16 as set out in appendix 2 to the report be approved. (ii) That the programme for 2016/17 as set out in appendix 3 to the report be approved. (iii) That the Service Director, Development & Public Protection be authorised to award the relevant works to the Service Director, Construction Services under the terms of the Highways, Drainage & Street Lighting Maintenance Contract. (iv) That the Service Director, Development & Public Protection be authorised to make changes to the approved indicative programme following consultation with the Cabinet Member for Environment and Transport as and when the need arises. The above decisions have been made to enable the design and implementation of transport schemes in support of the Tyne and Wear Local Transport Plan and the Council’s policy objectives.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. The report provides an update on progress with the Local Transport Plan (LTP) integrated transport (IT) capital programme. It includes a review of implementing the 2015/16 programme together with the in-year changes that have had to be made, and an outline of the 2016/17 programme for approval. Also covered is an outline of the LTP funding proposals and how they fit in with other funding sources.
Background
2. The LTP provides the main source of capital funding for local transport improvements. This includes both structural maintenance of highways and structures and integrated transport improvements. The latter covers a range of works including bus priority, new and improved cycleways, better facilities for pedestrians and disabled people, safer routes to school, traffic calming and road safety improvements.
3. The financial year 2016/17 will be the sixth year of LTP3, which is the third Local Transport Plan for Tyne and Wear and covers the period from 2011 to 2021. The main priorities of LTP3 are; to maintain and develop the transport networks; support the growth of the economy of Tyne and Wear; reduce transport carbon emissions; and contribute to making communities in Tyne and Wear healthier and safer.
Proposal
4. Some changes to the 2015/16 programme which was approved by Cabinet in March 2015 were required. This reflects changes to the delivery programmes on a number of schemes as a result of the need to meet revised cost estimates following detailed design, results of extensive consultation, revised priorities and unforeseen circumstances during construction.
5. The LTP Integrated Transport capital settlement for the period 2015/16 to 2017/18 and indicative allocations for the period 2018/19 to 2020/21 was announced by the Department for Transport (DfT) in July 2014. The funding
1 of 14 allocated to Tyne and Wear for all financial years within the above period was set as £9,465,000 per annum: This is a 46% reduction when compared to the allocation in 2014/15 Gateshead is set to receive £1,280,916 of the Tyne and Wear allocation
The devolution deal under consideration by authorities in the North East could see responsibilities for this funding devolved to the North East Combined Authority. This could have implications for the amount of funding received by Gateshead in future years.
6. A letter has been received from the DfT setting out draft LTP capital maintenance allocations for future years. This follows announcements relating to changes to the levels of funding and revisions to the formula used to allocate this between local authorities.
7. The provisional allocation for Gateshead for 2016/17 is £2,511,000. The figure represents only the ‘needs’ based element of maintenance funding. A further £152,000 should be available based on the DfT’s new performance based approach, and this is the maximum additional funding that could be claimed for 2016/17. The total allocation is £2,662,000.
8. Appendix 1 provides further background to the above together with details of external funding that has been secured to use in conjunction with the LTP funding bringing significant levels of betterment to the Borough.
9. Appendix 2 provides the projected outturn for the 2015/16 programme, while the 2016/17 programme is attached as appendix 3. The initial programme will be reviewed during the year and may be subject to change depending upon delivery progress and the outcome of consultation.
Recommendations
10. It is recommended that Cabinet:
(i) approves the estimated final outturn relating to the integrated transport capital programme for 2015/16 as set out in appendix 2;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.