RESOLVED - ( i ) That the submission of an outline application to the ERDF Axis 5 Climate Change to support the delivery of phase 2 of the proposed Team Valley Flood Alleviation and Water Meadows project be approved. (ii) That it be noted that the outline application does not commit the Council to a contractual undertaking prior to the development of the full ERDF application. (iii) That a further report be submitted to Cabinet outlining the detail of the proposed interventions, alongside identification of the project impact and implications during construction and post completion and that this report be submitted in advance of seeking approval for the Full ERDF application (due on 30 September 2017). The above decisions have been made for the following reasons: (A) Significant flood risk will be reduced to 343 properties. (B) To prevent reputational damage to Team Valley Trading Estate (TVTE), resulting in businesses relocating and/ or closing. (C) To enable new industrial development on the TVTE. (D) To protect and enhance business rate income. (E) To enable e xpansion of the existing nature reserve at Lamesley Pastures, including 30 hectares of wetland and new public access, which could become a visitor attraction. (F) Improvements to the water quality status of the River Team which is a failing water body under the European Water Framework Directive; reducing the risk of future, costly council clean-ups resulting from flooding.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. To approve the submission of an outline application to the ERDF Axis 5 Climate Change to support the delivery of phase 2 of the proposed Team Valley Flood Alleviation and Water Meadows (TVFA) project. The proposal is for the Council to act as the accountable body for the ERDF funding with the Environment Agency the lead delivery partner.
2. In making this decision the Council will be committing resources to support the development of the Full ERDF application by the 1 September 2017.
Background
3. Following significant flooding on the Team Valley Trading Estate (TVTE) in June and September 2012, the Council and the Environment Agency (EA) have been working in partnership to consider catchment-wide options for flood risk management. This project also combines flood alleviation benefits with habitat creation and water meadows expansion.
4. Team Valley is of significant importance as a trading estate to the local, regional and national economy, supporting over 700 businesses and employing over 24,000 people. Modelling exercises for the ‘do nothing approach’ show that 464 non- residential properties and 14 residential properties are at risk from a 1 in a 100 year flood event. There are currently no formal flood defences in the Team Valley Trading Estate. Many businesses have stated that they are at serious risk of closure or relocation if further flood events occur.
5. In terms of qualifying the scope of flood intervention measures required to reduce the flood risk on the Team Valley Trading estate, Capita was commissioned in 2015 by the Environment Agency, to undertake an options appraisal. This work revealed that a package of catchment wide approaches is required to ensure that flooding from all sources in the Team Valley are better managed.
6. An opportunity has been identified to seek ERDF funding to help facilitate the delivery of the proposed work given the strategic fit of the proposed works with the priorities outlined within the funding call, particularly given the investment will benefit sustainable economic growth and business. However, whilst the EA are considered a key partner and the information within the funding call is targeted towards areas highlighted as a risk by the EA, they are not eligible to apply for this funding stream directly.
1 of 5 7. The ERDF component of the project, the Water Meadows Project at Lamesley will provide increased protection to 343 businesses by storing water upstream and acting as a key catalyst for further phases of work. It is important to stress that the delivery of all interventions is required and that each phase of project delivery will reduce risk both in terms of removing the risk for some properties and reducing the level of flood water in extreme events.
Proposal
6. The scope of work currently proposed is divided into three phases of development and it is proposed that the Core Scheme and Phase 2 described in the table below are delivered in the period up to September 2019.
7. The ERDF Outline Application deadline is 28 April 2017. The ERDF Full Application deadline is 1 September 2017. A total of £2,713,000 of ERDF funding is being requested for the Water Meadows at Lamesley (Phase 2) and it is proposed that the Council act as the accountable body for the project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.