RESOLVED - ( i ) That the estimated final outturn relating to the transport capital programme for 2016/17 as set out in appendix 3 to the report be approved. (ii) That the proposed programme for 2017/18 as set out in appendices 4-6 be approved subject to it being noted that there may be a need to review scheme priorities during the course of the financial year in line with the available resources (iii) That the Service Director, Development, Transport and Public Protection be authorised to award the relevant works to the Service Director, Street Scene under the terms of the Highways, Drainage & Street Lighting Maintenance Contract. (iv) That the Service Director, Development, Transport and Public Protection be authorised to make changes to the approved indicative programme following consultation with the Cabinet Member for Environment and Transport as and when the need arises. The above decisions have been made to enable the design and implementation of transport schemes in support of the Tyne and Wear Local Transport Plan and the Council’s policy objectives.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. The report provides an update on progress with the Council’s programme of investment in the local transport network, including funding received through the Local Transport Plan (LTP) process. It includes a review of implementing the 2016/17 programme and an outline of the 2017/18 programme for approval.
Background
2. The LTP provides an important source of capital funding for local transport improvements. This includes both structural maintenance of highways and structures and integrated transport improvements. The latter covers a range of works including bus priority, new and improved cycleways, better facilities for pedestrians and disabled people, safer routes to school, traffic calming and road safety improvements. This funding is supplemented wherever possible by funding from Council or other sources such as developer contributions and other capital grants.
3. The financial year 2017/18 will be the seventh year of LTP3, which is the third Local Transport Plan for Tyne and Wear and covers the period from 2011 to 2021. The main priorities of LTP3 are; to maintain and develop the transport network; support the growth of the economy of Tyne and Wear; reduce transport carbon emissions; and contribute to making communities in Tyne and Wear healthier and safer.
4. Investment in the Council’s highways infrastructure is identified and prioritised in accordance with the principles outlined within the Council’s agreed Highways Asset Management Plan and helps to deliver the LTP priorities.
Proposal
5. A number of in year changes to the 2016/17 programme (approved by Cabinet in March 2016) were required. The reasons for these changes were variations in cost estimates following detailed design, alterations to design as a result of extensive consultation, revised priorities and unforeseen circumstances during construction. The programme is managed in a flexible 1 of 27 manner and often includes an element of over-programming to ensure that additional schemes can be accelerated where new issues are encountered.
6. The LTP Integrated Transport capital settlement for the period 2015/16 to 2017/18 and indicative allocations for the period 2018/19 to 2020/21 was announced by the DFT in July 2014 to assist with multi-year planning. The funding allocated to the Tyne and Wear area for all financial years within the above period was set as £9,465,000 per annum:
This is a 46% reduction when compared to the allocation in 2014/15 Gateshead is set to receive £1.233 million of the Tyne and Wear allocation.
7. The LTP maintenance allocation for Gateshead for 2017/18 is £2,640,000, which is based on the Council achieving band 2 status through the DfT’s new performance based approach.
8. The performance based approach considers the Council’s approach towards asset management, resilience, customer input and consultation, benchmarking and efficiency and operational delivery, with the aim of ensuring that the highway infrastructure asset is managed effectively. Band 2 status means that the Council can demonstrate that outputs are being produced that support the implementation of key areas that will lead towards improvement.
9. The Council has also received an allocation of £772,000 for 2017/18 for transport from the National Productivity Investment Fund. This funding is available for local transport schemes to improve access to employment and housing to develop economic and job creation opportunities. This funding is being used to supplement the LTP funding and will be utilised in accordance with the proposed priorities as part of the overall planned investment in the highway network.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.