RESOLVED - ( i ) That the proposed development of seven 2 bed, 4 person Council houses at Seymour Street, Dunston, to be let at affordable rents and to be designed by the Council’s Housing, Design and Technical Services Team and the construction to be delivered by The Gateshead Housing Company (formerly Construction Services) be approved. (ii) That application for Affordable Homes Grant funding from the Homes and Communities Agency to support the project be approved. The above decisions have been made for the following reasons: (A) To increase the provision of much needed affordable housing for rent utilising external grant. (B) To contribute to the further sustainability of the Housing Revenue Account.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report is to seek approval for a new affordable housing development within the Housing Revenue Account (HRA) and to pursue Affordable Homes Grant funding from the Homes and Communities Agency (HCA) to support the project described within this report.
Background
2. There is a clear need and ambition for the Council to increase the provision of new affordable homes across the borough through a programme of internal development and housebuilding. A number of proposals are being taken forward through the Gateshead Trading Company (GTC) that will combine commercial housebuilding with a commitment to deliver affordable provision as part of the commercial developments.
3. In addition to the sites being delivered through GTC, a number of sites are being considered for new council homes to be developed within the HRA. One of the sites identified and the first to be taken forward is a development site at Seymour Street, Dunston and is shown at appendix 2.
Proposal
4. The proposal for the site at Seymour Street, is to provide seven 2 bed 4 person council houses to be let at affordable rents. The site sits adjacent to other social housing and is within a council owned housing estate. A number of neighbouring properties have transferred to private ownership under the right to buy but there is still a strong management presence through the Gateshead Housing Company (TGHC).
5. The proposed development has been subject to a desktop appraisal to determine financial viability and the proposal meets the strategic needs of the Council in terms of housing provision, planning requirements and local demand.
6. Pre-Application planning advice has been obtained for the proposals ahead of a full planning application which is being progressed.
7. The cost of the proposals is estimated to be in the region of £1.2m. Capital funding for the scheme would be provided via the Housing Revenue Account Capital Programme. It is proposed that a contract for Affordable Homes Grant be entered into with the HCA to supplement the build costs through the HCA’s continuous
1 of 6 market engagement route. Initial discussions with the HCA have indicated that they would be supportive of a grant allocation to increase the provision of affordable homes. As a condition of grant, the properties would be let at an affordable rent. Typically this would equate to 80% of market rent in the locality. Exact rent levels and level of grant would be determined through the application process.
8. The provision of new Council housing within the HRA helps sustain the future of the HRA.
9. It is proposed that the scheme would be designed by the Council’s Council Housing, Design and Technical Services and the construction be delivered by TGHC (formerly Construction Services).
Recommendations
Cabinet is recommended to approve:
(i) The proposed development of seven Council houses at Seymour Street, Dunston.
(ii) The application of Affordable Homes Grant funding from the Homes and Communities Agency to support the project described within this report.
For the following reasons:
(i) To increase the provision of much needed affordable housing for rent utilising external grant.
(ii) To contribute to the further sustainability of the Housing Revenue Account.
CONTACT: Phil Gallagher Extension 2735
2 of 6 APPENDIX 1
Policy Context
1. The proposal outlined in this report is very much seen as being complementary to other development across the borough and some of the benefits are outlined below.
The proposal for the Council to act as housing developer directly contributes to the Vision 2030 and the Council Plan aspirations for ‘Live Well Gateshead’.
The importance of accessing good quality, affordable housing is recognised in all of the Council’s major strategies;
The Core Strategy identifies the need to build 11,000 new homes by 2030.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.