RESOLVED - ( i ) That the revised programme for 2017/18 as set out in appendices 3-5 of the report, noting that there may be a need to further review scheme priorities during the remainder of the financial year in line with the available resources, be approved. (ii) That the Service Director, Development, Transport and Public Protection be authorised to award the relevant works to the Service Director, Construction Services under the terms of the Highways, Drainage & Street Lighting Maintenance Contract. (iii) That the Service Director, Development, Transport and Public Protection be authorised to make changes to the approved indicative programme, following consultation with the Cabinet Member for Environment and Transport as and when the need arises. (iv) That the highways planned maintenance programme for 2018/19 be approved to allow forward planning of these works. The above decisions have been made to enable the design and implementation of transport schemes in support of the Tyne and Wear Local Transport Plan and the Council’s policy objectives.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. The report provides an update on progress with the Council’s programme of investment in the local transport network, including funding received through the Local Transport Plan (LTP) process. It includes a review of the 2017/18 programme which was approved by Cabinet in April of this year along with the in-year changes that have taken place. An outline of the 2018/19 roads maintenance programme is also set out for approval to allow for forward planning of these works.
Background
2. The LTP provides an important source of capital funding for local transport improvements. This includes both structural maintenance of highways and structures and integrated transport improvements. The latter covers a range of works including bus priority, new and improved cycleways, better facilities for pedestrians and disabled people, safer routes to school, traffic calming and road safety improvements. This funding is supplemented wherever possible by prudential borrowing or external sources such as developer contributions and other capital grants.
3. The financial year 2017/18 is the seventh year of LTP3, which is the third Local Transport Plan for Tyne and Wear and covers the period from 2011 to 2021. The main priorities of LTP3 are; to maintain and develop the transport network; support the growth of the economy of Tyne and Wear; reduce transport carbon emissions; and contribute to making communities in Tyne and Wear healthier and safer.
4. Investment in the Council’s highways infrastructure is identified and prioritised in accordance with the principles outlined within the Council’s agreed Highways Asset Management Plan, which helps to deliver the LTP priorities.
Proposal
5. A number of in year changes to the 2017/18 programme (approved by Cabinet in April 2017) have been necessary in the first half of the financial year. The most significant changes relate to the successful bids for funding from Central Government via the Highways Maintenance Challenge Fund and the National Productivity Investment Fund, which has necessitated the re- allocation of resources. Other changes have occurred due to variations in cost 1 of 26 estimates following detailed design, revised priorities and unforeseen circumstances during construction. The programme is managed in a flexible manner and often includes an element of over-programming to ensure that additional schemes can be accelerated where new issues are encountered.
6. Gateshead is set to receive £1.233m of the Tyne and Wear LTP allocation for integrated transport in 2017/18.
7. The LTP maintenance allocation for Gateshead for 2017/18 is £2.646m which is based on the Council achieving band 2 status through the DfT’s new performance based approach.
8. The performance based approach considers the Council’s approach towards asset management, resilience, customer input and consultation, benchmarking and efficiency and operational delivery, with the aim of ensuring that the highway infrastructure asset is managed effectively. Band 2 status means that the Council can demonstrate that outputs are being produced that support the implementation of key areas that will lead towards improvement.
9. The outcome of the Challenge Fund bid was announced in August following delays caused by the General Election in June. The Council has been awarded £5.000m of funding towards a scheme to repair and improve the Heworth roundabout, which will involve maintenance of the supporting structures, the removal of the roundabout and installation of a new fully signalised junction. Given the delay in the announcement from Central Government and other difficulties in progressing the scheme it is likely that works will commence in 2017/18 and carry over into the 2018/19 financial year.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.