Gateshead Metropolitan Borough Council
Cabinet, Tuesday 20 November 2018 at 10.00am

Local Transport Plan: Capital Programme mid-year update

Approved Executive 1 paper

Cabinet approved this item on Tuesday 20 November 2018. Below is the council's own wording, with the papers it was decided on.

ItemC81

Resolved

RESOLVED - ( i ) That the revised programme for 2018/19 as set out in appendices 2-4 of the report be approved and it be noted that there may be a need to review scheme priorities during the course of the financial year in line with the available resources. (ii) That the Service Director, Development, Transport and Public Protection be authorised to award the relevant works to the Service Director, Street Scene under the terms of the Highways, Drainage and Street Lighting Maintenance Contract. (iii) That the Service Director, Development, Transport and Public Protection be authorised to make changes to the approved programme following consultation with the Cabinet Member for Environment and Transport as and when the need arises. (iv) That the use of the SCAPE Civic Engineering and Infrastructure Framework to appoint contractors to undertake specialist major concrete repairs to structures on the A184 at Whitemare Pool be approved. (v) That the indicative Integrated Transport and Maintenance programmes for 2019/20 be approved as a basis for future planning. The above decision has been made to enable the design and implementation of transport schemes in support of the Tyne and Wear Local Transport Plan and the Council’s policy objectives.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. The report provides an update on progress with the Council’s programme of investment in the local transport network, including funding received through the Local Transport Plan (LTP) process. It includes a review of the 2018/19 programme which was approved by Cabinet in April of this year. The 2019/20 Integrated Transport and Roads Maintenance Programmes are included as appendices to allow for forward planning of these works.

Background

2. The LTP provides an important source of capital funding for local transport improvements. This includes both structural maintenance of highways and structures and integrated transport improvements. The latter covers a range of works including bus priority, new and improved cycleways, better facilities for pedestrians and disabled people, safer routes to school, traffic calming and road safety improvements. This funding is supplemented wherever possible by prudential borrowing or external sources such as developer contributions and other capital grants.

3. The financial year 2018/19 is the eighth year of LTP3, which is the third Local Transport Plan for Tyne and Wear and covers the period from 2011 to 2021. The main priorities of LTP3 are; to maintain and develop the transport network; support the growth of the economy of Tyne and Wear; reduce transport carbon emissions; and contribute to making communities in Tyne and Wear healthier and safer.

4. Investment in the Council’s highways infrastructure is identified and prioritised in accordance with the principles outlined within the Council’s agreed Highways Asset Management Plan and helps to deliver the LTP priorities.

Proposal

5. A number of in year changes to the 2018/19 LTP programme (originally approved by Cabinet in April 2018) have been necessary in the first 6 months of this financial year. The programme is managed in a flexible manner and

1 of 27 includes an element of over-programming to ensure that the grant is fully utilised. A forward plan of integrated transport and roads maintenance schemes has also been developed to allow schemes to be brought forward or slip as necessary.

6. Early measures funding of £400k has been confirmed from central government for works to improve the Great North Cycleway on Durham Road between Shipcote Lane and Prince Consort Road. This follows on from previous phases of work along the Great North Cycle Route.

7. Funding secured through the planning system via Section 106 Agreements has been allocated where possible.

8. Specific approval is sought for the use of the SCAPE Civil Engineering and Infrastructure Framework to appoint contractors to undertake specialist major concrete repairs to structures on the A184 at Whitemare Pool. The works cannot be undertaken by the Council’s internal contractors due to the specialist nature. These are being undertaken using Highways Maintenance Challenge Funding associated with the scheme at Heworth.

9. Appendix 1 provides further background to the above together with details of other external funding that has been secured for use in conjunction with the LTP funding.

10. Appendix 2 sets out the revised budgets for 2018/19 and the updated programme with the projected outturns of each scheme are set out at Appendices 3 and 4.

11. Appendices 5 and 6 set out indicative Integrated Transport and Road Maintenance Programmes for 2019/120 and Appendix 6 provides details of the Prudential borrowing, which has been allocated to the Quays sustainable transport improvements.

12. The 2018/19 programme will continue to be monitored and reviewed over the remainder of the financial year with funding re-allocated and budgets revised where necessary.

Recommendations

13. It is recommended that Cabinet:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Transport Plan: Capital Programme mid-year updateReport 259 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 22 attended
CO
Craig OakesCouncil Staff, expected
AT
Andrew TateCouncil Staff, expected
IB
Iain BurnsCouncil Staff, expected
DW
Deborah WiseCouncil Staff, expected
ER
Emma ReynardCouncil Staff, expected
MG
Councillor Martin GannonChair, present
CD
Councillor Catherine DonovanVice-Chair, apologies
JA
Councillor John AdamsCommittee Member, present
MB
Councillor Malcolm BrainCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MF
Councillor Mary FoyCommittee Member, present
LG
Councillor Linda GreenCommittee Member, present

All 22 on the meeting page

On this subject at Gateshead

Search all
  1. Local Transport Plan: Capital Programme mid-year updateThis decision
  2. Local Transport Plan Capital Programme Mid-Year Update (December 2025)Approved
  3. Local Transport Plan Capital Programme Year End ReportApproved
  4. Local Transport Plan: Capital Programme Mid-Year UpdateApproved
  5. Local Transport Plan: Capital Programme Year End ReportApproved
  6. Local Transport Plan: Capital Programme Mid-Year Update (November 2023)Approved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies