Baltic Quarter - Site Investigation works

Agreed Executive 1 paper

Cabinet agreed this item on Tuesday 22 January 2019. Below is the council's own wording, with the papers it was decided on.

ItemC123

Resolved

RESOLVED - ( i ) That the obtaining of a tender using the Scape Framework from Perfect Circle JV Ltd to provide Phase 2 Site Investigations at Baltic Quarter be endorsed. (ii) That the Acting Strategic Director, Communities and Environment be authorised to accept the final contract price, at a cost not exceeding £150,000, following consultation with the Strategic Director, Corporate Resources and subject to agreeing the form of Contract for the Works with Perfect Circle JV Ltd by the Strategic Director, Corporate Services and Governance (in accordance with the Constitution), The above decisions have been made for the following reasons: (A) To ensure that supporting infrastructure for Gateshead Quays is brought forward in a timely manner. (B) To ensure supporting infrastructure and access requirements to facilitate the wider development of Baltic Quarter are provided.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. To seek approval for the Council to enter into a contract with Perfect Circle JV Limited under the Scape Framework to provide Phase 2 Site Investigations at Baltic Quarter.

Background

2. In October 2018, the Council entered into a Delivery Agreement (Contract) with Perfect Circle JV Ltd under the Scape National Built Environment Consultancy Services Framework to provide Phase 1 Desk Top Site Investigation report for the whole of Baltic Quarter in Council ownership, at a cost of £22,053. This was to facilitate taking the land at Baltic Quarter out to the market in early 2019, by providing supporting information to potential developers regarding ground conditions and potential contamination issues at the site.

3. To facilitate the development of Gateshead Quays, supporting key strategic infrastructure is required to be brought forward on Baltic Quarter, due to its proximity to the Quays site. It is intended to progress the next stage of site investigations – Phase 2 Intrusive studies in areas on Baltic Quarter where this infrastructure is proposed to be located.

4. As Perfect Circle JV Ltd were engaged in the Phase 1 site investigations and have the previous knowledge and experience in respect to the site, costs have been obtained from Perfect Circle JV Ltd for the provision of the Phase 2 works which is in the region of £140,000. The final costs are currently being clarified with Perfect Circle JV Ltd.

Proposal

5. That the Council enter into an additional Contract via the Scape Framework with Perfect Circle JV Ltd to provide Phase 2 Site Investigations at Baltic Quarter at a cost not exceeding £150,000.

6. The Phase 2 investigation is for areas on Baltic Quarter that would house key strategic infrastructure requirements essential to support the Gateshead Quays development including a proposed new Multi Storey Car Park (MSCP) and a new North / South road to allow access/egress to the Felling by-pass. The results of the investigations will help inform detailed design for both. On completion the MSCP and the road will also facilitate the wider development of the Baltic Quarter site. These schemes will be the subject of a further report to Cabinet.

1 of 4 Recommendations

7. It is recommended that Cabinet;

(i) Retrospectively approves the obtaining of a tender using the Scape Framework from Perfect Circle JV Ltd to provide Phase 2 Site Investigations at Baltic Quarter; and

(ii) Authorises the acceptance of the final contract price at a cost not exceeding £150,000 by the Acting Strategic Director, Communities and Environment following consultation with the Strategic Director, Corporate Resources and subject to agreeing the form of Contract for the Works with Perfect Circle JV Ltd by the Strategic Director, Corporate Services and Governance (in accordance with the Constitution),

For the following reasons:

(i) To ensure that supporting infrastructure for Gateshead Quays is brought forward in a timely manner.

(ii) To ensure supporting infrastructure and access requirements to facilitate the wider development of Baltic Quarter are provided.

CONTACT: Sophie Johnson ext:3353

2 of 4 APPENDIX 1

Policy Context

1. The proposed site investigations will support the development of key development sites which is consistent with the overall vision for Gateshead as set out in Making Gateshead a Place Where Everyone Thrives.

2. The proposal will also accord with the provisions of the Corporate Asset Strategy and Management Plan 2015-2020. In particular, the use of assets to deliver economic growth.

3. With over one million visitors each year, Gateshead Quays is one of the UK's most iconic waterfront locations. The area has seen huge transformation over the last 15 years and is now a thriving cultural destination, home to many world-class attractions.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Baltic Quarter: Site Investigation worksReport 77 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 22 attended
CO
Craig OakesCouncil Staff, expected
AT
Andrew TateCouncil Staff, expected
IB
Iain BurnsCouncil Staff, expected
DW
Deborah WiseCouncil Staff, expected
ER
Emma ReynardCouncil Staff, expected
MG
Councillor Martin GannonChair, present
CD
Councillor Catherine DonovanVice-Chair, present
JA
Councillor John AdamsCommittee Member, present
MB
Councillor Malcolm BrainCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MF
Councillor Mary FoyCommittee Member, present
LG
Councillor Linda GreenCommittee Member, present

All 22 on the meeting page

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies