RESOLVED - That the power tariffs for 2019/20 of 14.86 p/kWh, with a standing charge of 18.61 p/day inclusive of VAT, for residents of the Gateshead HEIGHTs project be approved. The above decisions have been made for the following reasons: (A) To ensure cost savings are delivered to residents of the HEIGHTs scheme. (B) To ensure the HEIGHTs scheme recovers its operating and construction costs over its lifetime.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. To approve the electricity tariffs chargeable to residents of the Gateshead HEIGHTs project
Background
2. The Gateshead HEIGHTs (High Rise Energy Infrastructure for Gateshead Housing Tenants) project has installed new district heat and/or power systems to 7 High Rise Housing blocks in the Town Centre and Harlow Green.
3. Power supply to customers in Barford and Stretford Courts is due to commence early in 2019, and the starting power tariff needs to be approved.
Proposal
4. The power tariffs for Barford and Stretford Courts to 31 March 2020 have been set as follows:
The Council aims to provide the lowest tariff on the market for customers. Power tariff for 2019/20 is proposed at 14.86 p/kWh, with a standing charge of 18.61 p/day. All tariffs are inclusive of VAT
Recommendations
5. It is recommended that approval is given to agree the power tariffs for 2019/20 of 14.86 p/kWh, with a standing charge of 18.61 p/day inclusive of VAT.
For the following reasons:
(i) To ensure cost savings are delivered to residents of the HEIGHTs scheme. (ii) To ensure the HEIGHTs scheme recovers its operating and construction costs over its lifetime.
Contact: Anthony Alder Extension: 3402
1 of 6 APPENDIX 1
Policy Context
1. On a local level, the proposals will contribute to the delivery of many targets within Vision 2030, strategic interventions within “Making Gateshead a Place where Everyone Thrives”, the Council’s Climate Change Strategy and other Council strategies and commitments, specifically:
Helping to alleviate fuel poverty for residents, by providing lower cost heat; Reducing energy consumption and carbon emissions of homes and public buildings in the borough. Reducing carbon emissions of homes and public buildings.
2. The proposal will also accord with the provisions of the Corporate Asset Strategy and Management Plan 2015 – 2020. In particular; ensuing that the Council’s properties are fit for purpose and the continuous improvement of the sustainability of the Council’s assets;
Background to Gateshead HEIGHTs
3. The Gateshead HEIGHTs project has installed low-carbon heat and power generation plant in seven high rise blocks in Gateshead, to reduce carbon emissions of those homes, and reduce energy costs for residents, as follows:
Regent Court – heat only supplied direct to tenants from town centre district energy scheme. Ripley, Willerby, Acomb, Bedale, Angel courts – heat only, supplied from Ground Source Heat pumps. Stretford, Barford – heat and power supplied direct to tenants, from combined heat and power generation plant.
4. The project was funded by the Council’s Housing Revenue Account, using £4.5m grant from the European Regional Development Fund.
5. As a result of the Council’s objectives for the project, and the terms of the funding:
EU funding rules mean the scheme cannot make a profit. The Council wants to reduce tenants and leaseholders energy costs by at least 10% The Council needs to fully recover its investment over the lifetime of the scheme
6. In February 2018, heat tariffs were set for the scheme, which estimated that in the first year, would deliver a saving of more than 10% to residents from the new heat supply alone.
7. New heating systems were installed, with heat supply to residents commencing from May 2018 and completing in December 2018. A total of 620 homes now receive heat under the Gateshead HEIGHTs scheme.
2 of 6 8. In addition, from early 2019, the Council will become the electricity supplier to 154 homes within Barford and Stretford Courts, which has the potential to provide further benefits to residents of these blocks. To facilitate this, the Council has contracted with Emrgnt Ltd and Robin Hood Energy, to enable the electricity supply to be managed in line with UK electricity regulations (as approved by Cabinet on 18 December 2018).
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.