RESOLVED - ( i ) That the proposed Salix programme of works as identified in appendix 2 to the report and the award of contracts for these works to the Gateshead Housing Company be approved. (ii) That the Acting Strategic Director, Communities and Environment be authorised to agree the final terms and costs of contracts with the Gateshead Housing Company within the agreed overall budget limit . The above decisions have been made for the following reasons: (A) To meet the Council’s targets for the reduction in energy, carbon emissions and costs through energy efficiency improvements. (B) To improve the internal environment in the Council’s buildings.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. To seek approval to the proposed programme of works to various existing Council premises to enable energy efficiency savings
2. To approve contract award for works to the Gateshead Housing Company (TGHC)
Background
3. The Council continues to reduce its energy consumption, energy costs and carbon dioxide emissions, to meet agreed corporate indicators and targets.
4. As of March 2018, the Council had reduced carbon emissions by 40% compared to the baseline year of 2007/8. The Council aims to achieve 50% reduction by March 2020.
5. Since 2009, an annual programme of energy efficiency works has contributed to reducing energy and carbon emissions. The programme includes surveys of appropriate Council properties, viability calculations, design schemes and construction works. The works are included within the Councils’ Capital Programme and financed through either prudential borrowing or Salix grant funding. Salix Finance is a government back funding body, that provides grants and loans to support public sector energy efficiency schemes.
6. A budget of £250k was included for both 2018/19 and 2019/20 Capital Programme for Salix finance compliant projects but due to the success of projects to date and to enable additional works to be completed to benefit the Council this has been matched with grant funding from Salix Finance of £250k in 2018/19 and a further £250k in 2019/20, to create a budget of £500k per annum for these years.
Proposal
7. To achieve prioritised budget spend in 2018/19 and 2019/20 it is proposed to approve the award of contracts for the works programme to the Gateshead Housing Company.
8. It is also requested that Cabinet approve delegated powers to the Strategic Director, Communities and Environment, to negotiate the detailed terms and cost of works up to a total value of £1.0m for works to be delivered in 2018/19 and 2019/20. 9. Schemes listed in the Appendix 2 have been identified and prioritised with each Service within the available budget.
Recommendations
The Cabinet is recommended to:
(i) Agree the proposed Salix programme of works as identified in Appendix 2, and approve the award of contracts for these works to the Gateshead Housing Company; and
(ii) Authorise the Acting Strategic Director, Communities and Environment to agree the final terms and costs of contracts with the Gateshead Housing Company within the agreed overall budget limit.
For the following reasons:
(i) In order to meet the Council’s targets for the reduction in energy, carbon emissions and costs through energy efficiency improvements.
(ii) In order to improve the internal environment in the Council’s buildings.
CONTACT: Jim Gillon Ext. 3923 APPENDIX 1 Policy Context
1. On a local level, the proposals will contribute to the delivery of many targets within the Thrive Agenda “Making Gateshead a Place Where Everyone Thrives”, Vision 2030, the Council’s Climate Change Strategy and other Council strategies and commitments, specifically:
Support our communities to support themselves and each other Invest in our economy to provide sustainable opportunities for employment, innovation and growth across the borough Reducing energy consumption and carbon emissions of homes and public buildings in the borough. Reducing carbon emissions of homes and public buildings. Sustainable Gateshead - Improving how we use energy and resources as well as working towards a sound economic future.
2. The proposal also generates savings to the Council’s revenue budgets, contributing to closing the budget gap, and so supporting the Thrive Agenda by increasing resources available to invest in public services where they are most needed.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.