CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Gateshead Metropolitan Borough Council
Cabinet, Tuesday 19 March 2019 at 10.00am

Heat Tariffs for Gateshead HEIGHTs Project

Approved Executive 1 paper

Cabinet approved this item on Tuesday 19 March 2019. Below is the council's own wording, with the papers it was decided on.

ItemC151

Resolved

RESOLVED - That the heat tariffs set out below be approved: · Regent Court – 4.405 p/kWh (an 11% reduction) · Barford, Stretford, Ripley, Willerby, Acomb and Bedale Courts – 7.595 p/kWh (a 5% reduction) The above decision has been made for the following reasons: (A) To comply with heat supply agreements in place with customers. (B) To ensure the HEIGHTs scheme recovers its operating and construction costs over its lifetime.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. To update Cabinet on the completion of the Gateshead HEIGHTs project and to approve the heat tariffs chargeable to residents of the Gateshead HEIGHTs project for 2019/20.

Background

2. The Gateshead HEIGHTs (High Rise Energy Infrastructure for Gateshead Housing Tenants) project has installed new district heat and/or power systems to 7 High Rise Housing blocks in the Town Centre and Harlow Green.

3. Under heat supply agreements with residents, the Council is required to revise heat tariffs annually from 1st April, in line with energy price inflation.

Proposal

4. The heat tariffs for customers within the HEIGHTs project for 1 April 2019 to 31 March 2020 are due to decrease, and have been set as follows:

 Regent Court – 4.405 p/kWh (an 11% reduction)  Barford, Stretford, Ripley, Willerby, Acomb and Bedale Courts – 7.595 p/kWh (a 5% reduction)  No standing charges are proposed and all tariffs are inclusive of VAT

Recommendations

5. It is recommended that the heat tariffs set out in paragraph 4 above be approved.

For the following reasons:

(i) To comply with heat supply agreements in place with customers (ii) To ensure the HEIGHTs scheme recovers its operating and construction costs over its lifetime

CONTACT: Jim Gillon Extension: 3923

1 of 10 APPENDIX 1

Policy Context

1. On a local level, the proposals will contribute to the delivery of many targets within Vision 2030, strategic interventions within the Council’s Thrive Agenda, the Council’s Climate Change Strategy and other Council strategies and commitments, specifically:

 Helping to alleviate fuel poverty for residents, by providing lower cost heat;  Reducing energy consumption and carbon emissions of homes and public buildings in the borough;  Reducing carbon emissions of homes.

Background to Gateshead HEIGHTs

2. The Gateshead HEIGHTs project has installed low-carbon heat and power generation plant in 7 high rise blocks in Gateshead, to reduce carbon emissions of those homes, and reduce energy costs for residents, as follows:

 Regent Court – heat only supplied direct to tenants from town centre district energy scheme.  Ripley, Willerby, Acomb, Bedale, Angel courts – heat only, supplied from Ground Source Heat pumps.  Stretford, Barford – heat and power supplied direct to tenants, from combined heat and power generation plant.

3. The project was funded by the Council’s Housing Revenue Account, using £4.5m grant from the European Regional Development Fund.

4. As a result of the Council’s objectives for the project, and the terms of the funding:

 EU funding rules mean the scheme cannot make a profit.  The Council wants to reduce tenants and leaseholders energy costs by at least 10%  The Council needs to fully recover its investment in the scheme, over the lifetime of the scheme

5. New heating systems were installed, with heat supply to residents commencing from May 2018 and completing in December 2018. A total of 620 homes now receive heat under the Gateshead HEIGHTs scheme.

Updated scheme costs

6. The HEIGHTs project was funded from a number of sources: a. Housing Revenue Account for fabric improvement works b. External grant funding c. Contribution from Right to Buy receipts.

2 of 10 7. Appendix 2a shows the final capital cost of the HEIGHTs project, which includes both the heating works, and fabric improvement works (roof replacement, window installation and façade replacement).

8. Scheme construction costs increased from the budgeted £19.6m to £22.4m, due to a number of factors:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Heat Tariffs for Gateshead HEIGHTs ProjectReport 145 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 21 attended
CO
Craig OakesCouncil Staff, expected
AT
Andrew TateCouncil Staff, expected
IB
Iain BurnsCouncil Staff, expected
DW
Deborah WiseCouncil Staff, expected
ER
Emma ReynardCouncil Staff, expected
MG
Councillor Martin GannonChair, present
CD
Councillor Catherine DonovanVice-Chair, present
JA
Councillor John AdamsCommittee Member, present
MB
Councillor Malcolm BrainCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MF
Councillor Mary FoyCommittee Member, present
LG
Councillor Linda GreenCommittee Member, present

All 21 on the meeting page

On this subject at Gateshead

Search all
  1. Heat Tariffs for Gateshead HEIGHTs ProjectThis decision
  2. Heat Tariffs for Gateshead HEIGHTs schemeApproved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies