RESOLVED - That Council be recommended to: (i) note the Gateshead Quays Development Framework Consultation Feedback Report, as set out in Appendix 4 of the report; (ii) make the Consultation Feedback Report available along with the amended Development Framework for over 30 days on the Council’s website and in the Civic Centre reception; (iii) approve the , set out in Appendix 2 to the report, subject to any minor modifications arising from the consultation on the Feedback Report and amended Framework; (iv) delegate authority to the Strategic Director, Economy, Innovation and Growth, following consultation with the Cabinet member for Transport and Environment, to make any minor changes necessary to the Gateshead Quays Development framework in light of any further representations received during the consultation; and (v) delegate authority to the Strategic Director, Economy, Innovation and Growth, following consultation with the Cabinet member for Transport and Environment, to approve the Adoption Statement and publish the final Gateshead Quays Development Framework. The above decisions have been made for the following reasons: (A) To ensure a comprehensive and coordinated approach to site development and infrastructure provision to facilitate and accommodate the growth proposed in the CSUCP. (B) To meet statutory obligations and ensure full public engagement and afford weight to the Framework as a material planning consideration.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. The purpose of the report is for Cabinet to recommend to Council that it notes the Gateshead Quays Development Framework Consultation Feedback Report, approves the Gateshead Quays Development Framework and delegates any minor modifications as a result of consultation on the Feedback Report and amended Framework to the Strategic Director, Economy, Innovation and Growth, following consultation with the Cabinet member for Transport and Environment, and publish the final Framework.
Background
2. Gateshead Council adopted the Core Strategy and Urban Core Plan (CSUCP) in March 2015. The CSUCP identifies the Urban Core as the priority location for development which will maintain and enhance its vibrancy. Key to this spatial strategy is the allocation of key sites within the Urban Core for growth, including this framework area, the wider Gateshead Quays (Policy QB2). Policy CS2, requires that all sites within the wider Gateshead Quays are brought forward in accordance with an approved development framework or masterplan to ensure a comprehensive and coordinated approach.
3. This Development Framework therefore sets out a comprehensive and coordinated approach to the development of the wider Gateshead Quays and infrastructure provision in accordance with policy. It has been led in partnership by Gateshead Council and, Ask and Patrizia the appointed developers for Gateshead Quays. There have been specialist inputs from Gateshead Council and the Gateshead Quays design team consisting of; Lichfields, masterplanners Planit-IE, architects HoK, transport consultants Vectos and environmental consultants Arup.
4. The Framework is prepared for the entirety of the wider Gateshead Quays as identified by Policy QB2 in the CSUCP, in the context of informing emerging proposals by Ask Patrizia and Gateshead Council for the development of an arena and conferencing facility on the site located between the Sage Gateshead and BALTIC Centre for Contemporary Art. This Framework considers the possibility of accommodating large, ‘landmark’ buildings within this site as well as ensuring the architectural detailing is of a high quality to complement that of the Sage Gateshead and BALTIC.
5. The Framework corresponds with the timeframe of the CSUCP. As such, this document provides realistic considerations for development up to 2030 within the wider Gateshead Quays development framework area. 6. The development Framework sets out the purpose of the document; introducing the area; the existing context; the development opportunities - identifying three main development Plots, A the arena and conference centre, B land between the Baltic and the Tyne Bridge and C Hillgate Quay. The Framework then sets out a strategy and plan, the environmental considerations that will need to be considered bringing this site forward, development delivery including infrastructure provision.
7. In accordance with the adopted Statement of Community Involvement (SCI), consultation on the development Framework followed the procedures set out in Sections 12-22 of Town and Country Planning (Local Planning) (England) Regulations 2012. Consultation commenced on the 9 September concluding on the 8 October
8. Consultation was undertaken through:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.