Gateshead Metropolitan Borough Council
Cabinet, Tuesday 17 March 2026 at 10.00am

Mayoral Development Zone - Gateshead Quays

Approved Executive 2 papers

AI summaryGateshead Cabinet backs business case for up to £24 million from North East Combined Authority to deliver Gateshead Quays infrastructure, including a new Performance Square and a green Linear Park.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelegated authority to accept grant and agree terms
MoneyUp to £24 million requestedFrom North East Combined Authority
What happens nextSubmit Business Case to NE CAAccept grant and funding conditions
Who it affectsBridges Ward residents and visitorsWider Gateshead economy and visitors

What was decided

Cabinet approved submission of a Business Case to the North East Combined Authority for up to £24 million for Gateshead Quays Infrastructure Delivery.

Authority was delegated to the Strategic Director of Economy, Innovation and Growth, in consultation with the Strategic Director, Resources and Digital, and the Chief Legal Officer, to accept any resulting grant and agree associated funding conditions.

Why

To bring forward the regeneration of Gateshead Quays.

To reaffirm the Council's commitment to investing in the local economy to provide sustainable opportunities for employment, innovation and growth.

A Strategic Outline Case was completed in October 2025 and a Pre-Market Engagement exercise concluded in January 2026, supporting a market led Arena as the preferred option alongside further derisking of the site. Report P6

What happens next

Submit the Business Case to the North East Combined Authority for up to £24 million of infrastructure funding.

On award, accept the grant and agree funding conditions under delegated authority.

Use the investment for infrastructure delivery, a new Performance Square and green Linear Park, a procurement process to appoint an operator, and design work to prepare for Arena delivery. Report P2

The money

  • up to £24 million Requested from North East Combined Authority for Gateshead Quays Infrastructure Delivery

Options considered

  • Chosen: Submit Business Case to NE Combined Authority for up to £24 million and accept resulting grant under delegated authority. To bring forward regeneration of Gateshead Quays and invest in the local economy

Implications

  • Equalities: The Integrated Impact Assessment rates most protected characteristic and inclusion group impacts as long lasting or extensive positive, with new open space designed to be as inclusive as possible. Report P8, P9, P10
  • Equalities: The site has substantial gradients and the Linear Park will be stepped, which may cause accessibility issues for some; design will seek to overcome these within statutory obligations. Report P9
  • Climate: Developments will use the Council's District Energy Centre, a low carbon heat and power centre, and the Linear Park will use sustainable urban drainage systems. Report P14, P20
  • Environment and climate: Air quality, noise and waste impacts are rated as short term or limited negative during construction, mitigated through a Construction and Environmental Management Plan overseen by the Local Planning Authority. Report P14
  • Other: A long lasting or extensive positive impact is expected on built environment, transport, crime levels and community safety, physical and mental health, and biodiversity. Report P8, P12, P13, P14, P19

Who and where

  • Residents, businesses and visitors in Bridges Ward and the wider Gateshead area Report P3, P4, P18
  • Construction and hospitality sector workers through new job opportunities Report P12, P17
  • North East Combined Authority as funding partner Report P6
  • Ask:Patrizia as development partner Report P6

Timeline

  • 2025-10: Strategic Outline Case completed by North East Combined Authority Report P6
  • 2026-01: Pre-Market Engagement exercise concluded Report P6
  • Delivery: Project stage is delivery Report P5

Plain English for the jargon

  • Strategic Outline Case (SOC): An early stage business case document setting out the strategic need, market demand and financial requirements for a proposed project.
  • Pre-Market Engagement (PME): An exercise to test market interest and capacity before a formal procurement process is run.
  • Mayoral Development Zone: A designated area prioritised for regeneration and investment, in this case covering Gateshead Quays.
  • District Energy Centre (DEC): A local low carbon facility that generates and supplies both heat and power to nearby buildings.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC170

Resolved

i) Cabinet approved the submission of a Business Case to the North East Combined Authority for up to £24 million for Gateshead Quays Infrastructure Delivery. ii) Cabinet delegated authority to the Strategic Director of Economy, Innovation and Growth, in consultation with the Strategic Director, Resources and Digital, and the Chief Legal Officer, to accept any resulting grant and agree associated funding conditions. The above decision was made for the following reasons: a) To bring forward the regeneration of Gateshead Quays. b) To reaffirm the Council’s commitment to investing in the local economy to provide sustainable opportunities for employment, innovation and growth.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Integrated Impact Assessment

Details of the Activity Title of the activity: Gateshead Quays Description of the activity: 3) This investment will be utilised for a) Infrastructure Delivery, readying the Gateshead Quays site, b) New Performance Square, and a green Linear Park from riverside to Baltic Quarter, c) A procurement process to appoint an operator, and d) Funding for design work to prepare for Arena delivery. Group: Economy, Innovation and Growth

Does the activity impact all of Gateshead or a specific ward? Specific ward in Gateshead

Which specific ward(s) in Gateshead does the activity impact? (if applicable) Bridges Ward

What stage is the activity/project at? Delivery

Data and Intelligence What data and intelligence has been used and how has this informed the activity? The Council identified Gateshead Quays as a regeneration priority several years ago and the site is allocated with the Local Plan. The Council is working closely with North East Combined Authority to review the development opportunities and delivery options within a challenging economic environment. North East CA financed a Strategic Outline Case (SOC), which was completed in October 2025, establishing the regional requirement, market demand and financial requirements for the potential development and delivery of an International Conference Centre, Arena and associated infrastructure. North East CA and Gateshead Council agreed with the recommendation of that work, that a ‘market led Arena’ should be pursued as the preferred option, in parallel with further derisking of the Gateshead Quays site. North East CA and the Council agreed that a new Business Case must be developed to enable the acceleration of infrastructure delivery on the Gateshead Quays. North East CA and the Council then worked in partnership with the Developer, Ask:Patrizia (AP) to explore market interest in bringing forward a Market Led Arena scheme. The partners jointly developed a Pre-Market Engagement (PME) exercise which concluded in January 2026.

Summary of consultation/data/research undertaken to inform the assessment: Strategic Outline Case Pre Market Engagement exercise How will you monitor the impacts and mitigating actions on an ongoing basis? Impacts and mitigation actions will be monitored through regular project reporting and escalated through established governance where needed

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Mayoral Development Zone: Gateshead Quays BReport 183 KB DownloadRead as text
PDF
Mayoral Development Zone: Gateshead QuaysReport 262 KB Download

At this meeting

Whole meeting

Who was there

10 of 14 attended
MG
Councillor Martin GannonChair, present
GH
Councillor Gary HaleyVice-Chair, present
CD
Councillor Catherine DonovanCommittee Member, present
JA
Councillor John AdamsCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MH
Councillor Maria HallCommittee Member, present
LK
Councillor Leigh KirtonCommittee Member, present
JM
Councillor John McElroyCommittee Member, present
BO
Councillor Bernadette OliphantCommittee Member, present
MM
Melvyn Mallam-ChurchillSecretary, in attendance
DC
Darren CollinsOfficer, in attendance

All 14 on the meeting page

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open