RESOLVED - That the Council be recommended to: ( i ) Approve all variations to the 2020/21 Capital Programme as detailed in Appendix 2 to the report as the revised programme. (ii) Approve the financing of the revised programme. (iii) Notes that Cabinet confirms that the capital expenditure and capital financing requirement indicators have been revised in line with the revised budget and that none of the approved Prudential Indicators set for 2020/21 have been breached. The above decisions have been made for the following reasons: (A) To ensure the optimum use of the Council’s capital resources in 2020/21. (B) To accommodate changes to the Council’s in-year capital expenditure plans. (C) To ensure performance has been assessed against the approved Prudential Limits.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report sets out the latest position on the 2020/21 capital programme and Prudential Indicators at the end of the third quarter to 31 December 2020. The report assesses reasons for the variances from the approved programme and details the proposed financing of the capital programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the capital programme and the monitoring of performance against the statutory Prudential Indicators.
Background
2. The original budget for the capital programme for 2020/21, as agreed by Council on 25 February 2020, totalled £110.475m, which was reduced to £96.792m at the first quarter review and £94.452m at the second quarter to accommodate re-profiling into future years and reductions linked to Covid. The third quarter review of progress has resulted in a revised estimate for total capital expenditure of £77.411m.
3. The proposed reduction of the capital programme at the third quarter comprises of the following movements: £m Re-profiling of capital expenditure to future years (20.303) Increased borrowing/external funding/contributions 3.885 Reduction of planned expenditure (0.217) Level of Investment Reviewed (0.406) Total Variance (17.041)
4. Primarily due to the impact of COVID-19 and the need to reassess costs and risks and deal with delays to programme planned investment has been re-profiled from 2020/21 to future years on a number of schemes, amounting to £20.303m reductions in 2020/21, this includes:
£5.275m Clasper House Building Development – Progress has now halted on this as more discussions are needed to determine the financial viability of the development. £3.594m – Urban Core – Exemplar Neighbourhood – Poor ground conditions have significantly impacted viability; work is ongoing with GRP to address these issues with a view to start on site in 2021/22. £2.557m – Local Transport Plan – Planned Maintenance – The planned programme has slipped due to Covid restrictions on a number of schemes and resources focussed on introducing Covid safe measures. £1.681m Decent Homes Investment Programme – A number of schemes have been pushed back into 2021/22 due to Covid restrictions. £0.808m – River View Intermediate Care Facility – The impact of Covid has put back the procurement of this facility until early 2021/22. 1 of 5 £0.690m - Gateshead Solar PV – This will slip into 2021/22 due to the timeline on Freight Depot slipping. £0.639m – Local Transport Plan – Integrated Transport – The progress on planned schemes has been affected by the impact of Covid restrictions on working conditions and staffing resources. £0.550m – Salix Energy Efficiency Works – Progress on this has been impacted by the Asset Review. £0.509m – Speculative Office Build 2 – Baltic Quarter – Investment has been paused on this scheme while due diligence is carried out to assess the demand for office space post COVID-19. £0.500m West Askew Road Junction Improvements – No progress has been made on this due to utility works, it is anticipated works will begin in 2021/22. £0.500m – Baltic Quarter Enabling Infrastructure – Ground clearance will take place after the New Year, but the main scheme has been delayed to allow for works to begin on the Multi Storey Car Park.
5. A total of £3.885m increased capital investment primarily relates to the following schemes:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.