Local Transport Plan: Capital Programme Mid-Year Update (December 2020)

Approved Executive 1 paper

Cabinet approved this item on Tuesday 19 January 2021. Below is the council's own wording, with the papers it was decided on.

ItemC71

Resolved

RESOLVED - ( i ) That the revised programme for 2020/21 as set out in Appendices A and B to the report be approved and it be noted that there may be a need to review the schemes as the year progresses in line with available resources. (ii) That the Service Director, Highways and Waste be authorised to award the relevant works under the terms of the Highways, Drainage and Street Lighting Maintenance Contract. (iii) That the Service Director, Planning Policy, Climate Change and Strategic Transport be authorised to make changes to the approved programme following consultation with the Cabinet Member for Environment and Transport, as and when the need arises. (iv) That the indicative integrated transport and maintenance programmes for 2021/22 as set out in Appendices D and E to the report be approved as a basis for future planning. (v) That it be noted the Strategic Director, Housing, Environment and Healthy Communities awarded the contract for the Chainbridge Road Overbridge; Concrete Repairs through the Scape Framework Agreement for Civil Engineering and a tender exemption decision was taken by the Service Director, Highways and Waste, to extend this contract to procure the works for Team Street Viaduct; Concrete Repairs. The above decisions have been made t o enable the design and implementation of transport schemes in support of the Tyne and Wear Local Transport Plan and the Council’s policy objectives.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. This report is an update on the Local Transport Plan Capital Programme. It provides a summary of the progress that has been made and any changes to the programme that have occurred as it stands in December 2020, nearing the end of Quarter 3. Indicative programmes for integrated transport and maintenance schemes scheduled for 2021/22 are included as appendices to allow for forward planning of these works.

Background

2. LTP funding is allocated by government and provides a source of funding for integrated transport schemes and maintenance of highways and structures. It is supplemented wherever possible by prudential borrowing, or external sources such as developer contributions and bids for government funding.

3. The integrated transport and maintenance programmes were approved by Cabinet at the beginning of 2020/21. The schemes in the integrated transport programme are aligned to four priorities derived from the Local Transport Plan: economic development and regeneration, climate change, safe and sustainable communities, and scheme development. Investment in the highways infrastructure is identified and prioritised in accordance with the Council’s Highways Asset Management Plan.

4. The financial year 2020/21 is the final year of the LTP3 funding allocations. While the recent Government spending review suggests that funding levels for 2021/22 are likely to be similar for those for 2021 for integrated transport, the local detail of this has yet to be confirmed. For maintenance funding the position is more complicated, with funding often coming through a number of different channels. In the light of this the indicative programmes for 2021/22 are based provisionally on receiving the same allocation as in 2020/21.

5. Implementation of the programme in 2020/21 has been made much more difficult as a result of the Covid-19 outbreak. Most construction work stopped for two months from March, while since that time some resources have had to be diverted to work on the social distancing schemes in local centres, as well as the walking and cycling schemes in Gateshead town centre. The full implications of this have yet to be assessed.

Proposal

6. The transport capital programme is managed flexibly and includes an element of overprogramming to ensure that the LTP grant and other funding sources are fully utilised. Some changes to the programme have occurred during the first part of the year, particularly in terms of slippage of schemes. These changes have been set out in the report and in the appended programmes.

7. A forward plan of integrated transport and maintenance schemes has been developed to allow for longer term planning. The indicative programme for 2021/22 includes some schemes which have slipped from the current financial year due to delays in their development.

Recommendations

8. It is recommended that Cabinet:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Transport Plan: Capital Programme Mid-Year Update (December 2020)Report 821 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 26 attended
AD
Alison DunnCouncil Staff, expected
SC
Sarah CoxonOfficer, expected
NP
Neil PorteousOfficer, expected
CO
Craig OakesCouncil Staff, expected
AT
Andrew TateCouncil Staff, expected
IB
Iain BurnsCouncil Staff, expected
DW
Deborah WiseCouncil Staff, expected
ER
Emma ReynardCouncil Staff, expected
MG
Councillor Martin GannonChair, present
CD
Councillor Catherine DonovanVice-Chair, present
JA
Councillor John AdamsCommittee Member, present
MB
Councillor Malcolm BrainCommittee Member, present

All 26 on the meeting page

On this subject at Gateshead

Search all
  1. Local Transport Plan: Capital Programme Mid-Year Update (December 2020)This decision
  2. Local Transport Plan Capital Programme Mid-Year Update (December 2025)Approved
  3. Local Transport Plan Capital Programme Year End ReportApproved
  4. Local Transport Plan: Capital Programme Mid-Year UpdateApproved
  5. Local Transport Plan: Capital Programme Year End ReportApproved
  6. Local Transport Plan: Capital Programme Mid-Year Update (November 2023)Approved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies