Corporate Risk Management 2020/21 - Quarter 3 Update

Noted Finance 1 paper

Audit and Standards Committee noted this item on Monday 25 January 2021. Below is the council's own wording, with the papers it was decided on.

ItemASC299

Resolved

RESOLVED - i ) That the information be noted ii) The Committee endorsed the effectiveness of the Council’s risk management arrangements
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Audit and Standards Committee

Purpose of the report

1. This report updates the Committee on Corporate Risk Management during the period 1 October 2020 to 31 December 2020.

Background

2. Quarterly reporting to those with the responsibility for the oversight of risk management issues complies with the principles of good corporate governance. It is also embodied in the Corporate Risk Management Policy. This was last approved by Council on 21 May 2013 and is kept under review. Whilst it has been amended to reflect changes in Senior Officer titles since that time, it remains relevant and fit for purpose.

3. The report covers progress against the Corporate Risk Management Developmental Objectives for 2020/21 as cited in the Corporate Risk Management Annual Report 2019/20, and any other risk management issues emerging within the quarter under consideration.

Strategic Risk Management

4. In November 2018, Cabinet and Council approved a revised Strategic Risk Register which had been presented to Audit and Standards Committee on 1 October 2018. The Corporate Management Team has continued to ensure strategic risks are responded to in accordance with the Risk Management Policy, with risks and controls being recorded for inclusion within the Strategic Risk Register. As part of the iterative nature of the Register, risk owners are asked to provide updates as part of the quarterly reviews, which are then reported to Committee as part of the quarterly reporting.

5. There have been no changes to the Strategic Risk Register in the third quarter 2020/21. The Strategic Risk Register is attached for information at Appendix 1.

Operational Risk Management

6. Operational risks identified within the Council are recorded on the operational risk register. Work is ongoing to ensure operational risk management activity within services continues to align with service objectives, including those risks specific to operational objectives as a consequence of the Council’s response to the COVID pandemic and EU transition. 7. Service Risk Coordinators, whose role it is to support and champion risk management activity within their Services, are working with the Corporate Risk Officer to support risk owners with evaluating existing operational risk assessments. The focus of this work is on ensuring the assessments contain the required information to inform the management response.

Business Continuity Management

8. In accordance with the Council’s Risk Management and Business Continuity Policies, all services are required to continuously assess the risk of their activities being disrupted and to develop cost effective business continuity plans.

9. All Business Impact Assessments were reviewed by Services in March 2020 and again in November 2020. This was to identify threats to critical activities and potential increased demand on Council Services following a second wave of infections, along with other potential pressures such as exit from the EU and seasonal events like flu and adverse weather.

10. Business Continuity Plans were also revised accordingly to mitigate, as far as possible, any threats to the delivery of key activities with a focus on activity that could not be interrupted for more than 48 hours without critical impact. This exercise was also used to assess which activities might require additional support to strengthen resilience and estimated the officer numbers and skills that might be needed.

11. Where these could not be provided by redeployment from within the Service or Group, redeployment of officers would be sought from Services that had either been stood down due to the pandemic or could be reduced in the short term without significant impact.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Management 2020/21: Quarter 3 UpdateReport 229 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 26 attended
GM
Ged MortonCouncil Staff, expected
AD
Alison DunnCouncil Staff, expected
SC
Sarah CoxonOfficer, expected
NP
Neil PorteousOfficer, expected
LG
Councillor Linda GreenCommittee Member, present
JM
Councillor John McClureyCommittee Member, present
JM
Councillor John McElroyCommittee Member, present
TA
Mr Tony Atkinson (Independent Person)Committee Member, expected
SB
Mr Stuart Bell (Independent Member)Committee Member, present
GC
Mr George Clark (Independent Member)Committee Member, apologies
BJ
Mr Brinley Jones (Independent Member)Committee Member, absent
CO
Craig OakesOfficer, expected

All 26 on the meeting page

On this subject at Gateshead

Search all
  1. Corporate Risk Management 2020/21 - Quarter 3 UpdateThis decision
  2. Corporate Risk Management 2026/27 Quarter 1 UpdateNoted
  3. Corporate Risk Management Annual Report 2025/26Noted
  4. Corporate Risk Management 2025/26 - Quarter 4 UpdateDecided
  5. Corporate Risk Management 2025/26 Quarter 3 UpdateNoted
  6. Corporate Risk Management Annual Report 2024/25Noted

More from Gateshead Audit and Standards Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Treasury Management Annual Report 2025/26RESOLVED that the Treasury Annual Report be submitted to Cabinet. Decided Open
14 Jul 2026 Treasury Management Quarter 1 ReportRESOLVED that the Treasury Management Performance at the 2026/27 First Quarter Review be noted. Noted Open
14 Jul 2026 Annual Report To CabinetRESOLVED that the report and the work undertaken by the Audit and Standards Committee during the period 01 July 2025 ... Noted Open
14 Jul 2026 Corporate Risk Management 2026/27 Quarter 1 UpdateRESOLVED that the report be noted, and the Council's risk management be considered effective. Noted Open
14 Jul 2026 Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of Item 9 in accordance with Par... Decided Open