RESOLVED - ( i ) That the proposed programme for integrated transport and maintenance schemes for 2021/22 as set out in appendices D and E be approved and it be noted that there may be a need to review these as the year progresses in line with available resources. (ii) That the Service Director, Highways and Waste be authorised to award the relevant works under the terms of the Highways, Drainage and Street Lighting Maintenance Contract. (iii) That the Service Director, Planning Policy, Climate Change and Strategic Transport be authorised to make changes to the approved programme following consultation with the Cabinet Member for Environment and Transport, as and when the need arises. The above decisions have been made to enable the design and implementation of transport schemes in support of the North East Transport Plan and the Council’s policy objectives.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report is an update on the Local Transport Plan Capital Programme. It provides a summary of the progress that has been made in the 2020/21 financial year, as well as confirming programmes for integrated transport and maintenance schemes scheduled for 2021/22.
Background
2. LTP funding is allocated by government and provides a source of funding for integrated transport schemes and maintenance of highways and structures. It is supplemented wherever possible by prudential borrowing, or external sources such as developer contributions and bids for government funding.
3. Integrated transport improvements cover a range of works including bus priority, new and improved cycleways, better and safer environments for pedestrians, traffic calming and road safety improvements. Maintenance funding covers road maintenance works as well as maintenance of structures relating to the highway such as bridges.
4. Indicative programmes for the current financial year were approved by Cabinet in January 2021. Although the financial year 2020/21 was the final year of the LTP3 funding allocations, this has now been extended into 2021/22.
5. In 2021/22, a similar amount of integrated transport funding has been received from Government (£1197k this year compared to £1199k last year). For maintenance funding the position is more complicated, with funding often coming through a number of different channels. For 2021/22, needs and incentive maintenance funding will be received along with an allocation of Pothole funding. It is proposed that the reduction in Gateshead’s allocation of needs funding from Government is made up using funding from the Pothole Fund, in order to avoid a cut to the planned maintenance programme for 2021/22.
6. Implementation of the programme in 2020/21 was made much more difficult as a result of the Covid-19 outbreak. Most construction work stopped for two months from March 2020, while since that time some resources have had to be diverted to work on the social distancing schemes in local centres, as well as the walking and cycling schemes in Gateshead town centre. This has resulted in significant spend being redirected to the social distancing schemes, with several other schemes in the 2020/21 programme then being put back into the 2021/22 financial year for completion.
7. The indicative programme for 2021/22 included a number of schemes to be funded via the Government’s Transforming Cities Fund. These proposals are under development with a view to seeking approval from the North East Joint Transport Committee to secure the funding later this year. The timing of any such approvals will influence the level of spend it is possible to achieve in this financial year.
Proposal
8. The transport capital programme is managed flexibly and includes an element of overprogramming to ensure that the LTP grant and other funding sources are fully utilised. Some changes to the programme have occurred throughout the year, particularly in terms of slippage of schemes. These changes are set out in appendix 1 and in more detail in the appended programmes.
Recommendations
9. It is recommended that Cabinet:
(i) Approves the proposed programme for 2021/22 as set out in appendices D and E, noting that there may be a need to review these as the year progresses in line with available resources. (ii) Authorises the Service Director, Highways and Waste, to award the relevant works under the terms of the Highways, Drainage and Street Lighting Maintenance Contract. (iii) Authorises the Service Director, Planning Policy, Climate Change and Strategic Transport to make changes to the approved programme following consultation with the Cabinet Member for Environment and Transport, as and when the need arises. For the following reason:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.