Local Transport Plan: Capital Programme Mid-Year Update (December 2021)

Approved Executive 1 paper

Cabinet approved this item on Tuesday 14 December 2021. Below is the council's own wording, with the papers it was decided on.

ItemC101

Resolved

RESOLVED - (i) That the revised programme for 2021/22 as set out in Appendices A and B to the report be approved, noting that there may be a need to review these as the year progresses in line with available resources. (ii) That the Service Director, Highways and Waste, be authorised to award the relevant works under the terms of the Highways, Drainage and Street Lighting Maintenance Contract. (iii) That the Service Director, Climate Change, Compliance, Planning and Transport be authorised to make changes to the approved programme, following consultation with the Cabinet Member for Environment and Transport, as and when the need arises. (iv) That the indicative integrated transport and maintenance programmes for 2022/23 as set out in Appendices D and E to the report be approved as a basis for future planning. (v) That the expenditure in excess of £250,000 to undertake the principal inspection of Gateshead Viaduct be approved. (vi) That the Service Director, Highways and Waste be authorised to procure the principal inspection of Gateshead Viaduct through the existing procurement frameworks in place. The above decisions have been made to enable the design and implementation of transport schemes in support of the North East Transport Plan and the Council’s policy objectives.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. This report is an update on the Local Transport Plan Capital Programme. It provides a summary of the progress that has been made and any changes to the programme that have occurred at the end of Quarter 2.

2. Approval is requested for the indicative programmes for integrated transport and maintenance schemes scheduled for 2021/22, which are included as appendices to allow for forward planning of these works.

Background

3. LTP funding is allocated by government and provides a source of funding for integrated transport schemes and maintenance of highways and structures. It is supplemented wherever possible by prudential borrowing, or external sources such as developer contributions and bids for government funding.

4. The integrated transport and maintenance programmes were approved by Cabinet in April 2021. Although the financial year 2020/21 was the final year of the LTP3 funding allocations, this has now been extended into 2021/22. Investment in the highways infrastructure is identified and prioritised in accordance with the Council’s Highways Asset Management Plan.

5. Although there has not yet been confirmation from Government, it is expected that funding levels for 2022/23 are likely to be similar for those for 2021/22 for integrated transport. The local detail of this has also yet to be confirmed. For maintenance funding the position is more complicated, with funding often coming through a number of different channels. In the light of this the indicative programmes for 2022/23 are based provisionally on receiving the same allocation as in 2021/22.

6. Implementation of the programme in 2020/21 has been made more difficult as a result of Covid-19. Most construction work stopped for two months from March, while since that time some resources have had to be diverted to work on the social distancing schemes in local centres, as well as the walking and cycling schemes in Gateshead town centre. The main impact of this was felt in the previous financial year, but full implications of this for the current year’s programme remain to be seen.

Proposal

7. The transport capital programme is managed flexibly and includes an element of overprogramming to ensure that the LTP grant and other funding sources are fully utilised. Some changes to the programme have occurred during the first part of the year. These changes have been set out in the report and in the appended programmes.

8. A forward plan of integrated transport and maintenance schemes has been developed to allow for longer term planning and is included as appendices A to E.

Recommendations

9. It is recommended that Cabinet:

(i) Approves the revised programme for 2021/22 as set out in Appendices A and B, noting that there may be a need to review these as the year progresses in line with available resources. (ii) Authorises the Service Director, Highways and Waste, to award the relevant works under the terms of the Highways, Drainage and Street Lighting Maintenance Contract. (iii) Authorises the Service Director, Climate Change, Compliance, Planning and Transport to make changes to the approved programme, following consultation with the Cabinet Member for Environment and Transport, as and when the need arises. (iv) Approves the indicative integrated transport and maintenance programmes for 2022/23 as set out in Appendices D and E as a basis for future planning. (v) Approves the expenditure in excess of £250,000 to undertake the principal inspection of Gateshead Viaduct. (vi) Authorises the Service Director, Highways & Waste, to procure the principal inspection of Gateshead Viaduct through the existing procurement frameworks in place.

For the following reason:

To enable the design and implementation of transport schemes in support of the North East Transport Plan and the Council’s policy objectives.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Local Transport Plan: Capital Programme Mid-Year Update (December 2021)Report 816 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 28 attended
LB
Linda BartramCouncil Staff, present
GM
Ged MortonOfficer, expected
AD
Alison DunnCouncil Staff, expected
SC
Sarah CoxonOfficer, expected
NP
Neil PorteousOfficer, expected
CO
Craig OakesCouncil Staff, expected
AT
Andrew TateCouncil Staff, expected
IB
Iain BurnsCouncil Staff, expected
DW
Deborah WiseCouncil Staff, expected
ER
Emma ReynardCouncil Staff, expected
MG
Councillor Martin GannonChair, present
CD
Councillor Catherine DonovanVice-Chair, present

All 28 on the meeting page

On this subject at Gateshead

Search all
  1. Local Transport Plan: Capital Programme Mid-Year Update (December 2021)This decision
  2. Local Transport Plan Capital Programme Mid-Year Update (December 2025)Approved
  3. Local Transport Plan Capital Programme Year End ReportApproved
  4. Local Transport Plan: Capital Programme Mid-Year UpdateApproved
  5. Local Transport Plan: Capital Programme Year End ReportApproved
  6. Local Transport Plan: Capital Programme Mid-Year Update (November 2023)Approved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies