RESOLVED - (i) That the proposed programme for 2022/23 as set out in Appendices D and E to the report be approved and it be noted that there may be a need to review the programme as the year progresses in line with available resources. (ii) That the Service Director, Highways and Waste be authorised to award the relevant works under the terms of the Highways, Drainage and Street Lighting Maintenance Contract. (iii) That the Service Director, Climate Change, Compliance, Planning and Transport be authorised to make changes to the approved programme, following consultation with the Cabinet Member for Environment and Transport, as and when the need arises. The above decisions have been made to enable the design and implementation of transport schemes in support of the North East Transport Plan and the Council’s policy objectives.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report is an update on the Local Transport Plan (LTP) Capital Programme. It provides a summary of the progress that has been made in the 2021/22 financial year, as well as confirming programmes for integrated transport and maintenance schemes scheduled for 2022/23.
Background
2. LTP funding is allocated by government and provides a source of funding for integrated transport schemes and maintenance of highways and structures. It is supplemented wherever possible by external sources such as developer contributions and bids for government funding, and by prudential borrowing.
3. Integrated transport improvements cover a range of works including bus priority, new and improved cycleways, better and safer environments for pedestrians, traffic calming and road safety improvements. Maintenance funding covers road maintenance works as well as maintenance of structures relating to the highway such as bridges.
4. Indicative programmes for the current financial year were approved by Cabinet in December 2021. Although the financial year 2020/21 was the final year of the LTP3 funding allocations, this was subsequently extended into 2021/22 and again into 2022/23.
5. In 2022/23, a similar amount of integrated transport funding has been received by the region; Gateshead’s share of this is likely to remain similar to last year. For maintenance funding in 2022/23, the same amount of funding will be received as the previous year for the Needs and Pothole allocations. The amount of Incentive funding received may be slightly higher than previous years, but this element is yet to be confirmed. 6. The indicative programme for 2022/23 also includes the construction of a number of schemes to be funded via the Government’s Transforming Cities Fund (TCF). Business case production for four of the proposals is ongoing, while one of the schemes (GA08 Gateshead Quays) has now been approved for grant funding at full business case stage and has commenced. A regionwide TCF scheme to improve the operation of traffic signals along the major bus corridors will also be implemented this year. Implementation of Gateshead’s Active Travel Fund scheme is currently underway.
Proposal
7. The transport capital programme is managed flexibly and includes an element of overprogramming to ensure that the LTP grant and other funding sources are fully utilised. Some changes to the programme have occurred throughout the year, particularly in terms of slippage of schemes. These changes have been set out in Appendix 1 and in more detail in the appended programmes.
Recommendations
8. It is recommended that Cabinet:
(i) approves the proposed programme for 2022/23 as set out in Appendices D and E, noting that there may be a need to review these as the year progresses in line with available resources; (ii) authorises the Service Director, Highways and Waste, to award the relevant works under the terms of the Highways, Drainage and Street Lighting Maintenance Contract; and (ii) authorises the Service Director, Climate Change, Compliance, Planning and Transport to make changes to the approved programme, following consultation with the Cabinet Member for Environment and Transport, as and when the need arises.
For the following reason:
To enable the design and implementation of transport schemes in support of the North East Transport Plan and the Council’s policy objectives.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.