Planning and Development Committee refused this item on Wednesday 31 August 2022. Below is the council's own wording, with the papers it was decided on.
i ) That the full planning applications and outline applications specified in the appendix to these minutes be granted, refused or referred to the Department for Communities and Local Government or deferred as indicated subject to the conditions, if any, as specified therein and to any other appropriate conditions of a routine or standard nature. ii) That the applications granted in accordance with delegated powers be noted.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
DC/19/00821/FUL [name removed] Dunston Hill Community Primary School Dunston Bank Gateshead
Proposal:
Demolition of existing school buildings followed by full redevelopment of the site to provide 35 dwellings, with associated parking and vehicle access onto Dunston Bank (amended plans received 21.04.2021, 06.05.2022, 08.06.2022, 28.07.2022 and 16.08.2022 and description amended to reflect increase in proposed amount of redevelopment and dwellings 12.05.2021 and 10.05.2022) (additional information received 04.08.2021, 13.05.2022, 28.07.2022, 05.08.2022 and 09.08.2022).
Declarations of Interest:
Name Nature of Interest
List of speakers and details of any additional information submitted:
[name removed] spoke in objection to the application.
[name removed] (agent) spoke in favour of the application.
Reason for Minor Update
Clarification of earliest decision date and condition(s) amended
Paragraphs 3.12 and 7.0 of the Officer Report refer to the publicity period ending on 8 September 2022, however, this date is 15 September 2022. No further representations have been received since the Officer Report was published.
The description of existing accesses in paragraph 1.4 of the Officer Report should note that in total there is one main vehicular access point on Dunston Bank and two secondary vehicle access points, one on Ellison Road and one on the corner of Dunston Bank. There are also two pedestrian accesses on Dunston Bank and two on Ellison Road.
Condition wording is also recommended to be amended as follows:
32 No dwelling hereby approved shall be occupied until final details of secure and weatherproof cycle parking have been submitted to and approved in writing by the Local Planning Authority.
The details shall include an anchor point within the shed and a locking mechanism for the shed. The shed construction and all equipment should meet Secured By Design criteria.
Reason To ensure appropriate provision for cycle parking in accordance with the NPPF and policies CS13 and MSGP15 of the Local Plan.
42 No dwelling hereby approved shall be occupied until the following details (relating to off-site highways matters) have been submitted to and approved in writing by the Local Planning Authority:
a) Making good of all redundant footway crossings on the site frontage along both Ellison Street and Dunston Bank. b) Dropped kerb arrangement for cyclists on Ellison Road c) Works associated with new accesses (vehicle and pedestrian). d) Relocation of the bus shelter on Dunston Bank. e) An independent Road Safety Audit. f) The removal of infrastructure associated with the previous school use on the site (ie guard rail, zig zag marking, signage - the guard rail removal being subject to a safety assessment) g) Final details of amendments to roadmarkings and relevant legal orders. h) Amendments to streetlighting following consultation with the Council’s Adoption Engineer and Street Lighting team. i) Final details of amendments to or additional external highway drainage as a result of off-site highway works j) Final details of signage, further to the detailed highways design, as a minimum in relation to cyclists joining carriageway at Ellison Road, short section of the shared use path, and the 20mph zone.
Reason In the interests of highway safety, in accordance with the NPPF and policies CS13 and MSGP15 of the Local Plan.
44 Notwithstanding the approved plans, following demolition, no further development shall commence until final details of footpath gradients and sections of footpaths 1 and 2 as shown on plan ‘003-01 -G- External Works’, which shall include landings at regular intervals and the length of each landing being equal to at least the width of the footpath, has been submitted to and approved in writing by the Local Planning Authority.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.