Gateshead International Stadium – Options Appraisal

Approved Executive 1 paper

Cabinet approved this item on Tuesday 20 June 2023. Below is the council's own wording, with the papers it was decided on.

ItemC18

Resolved

RESOLVED - (i) That the commencement of a 90 day consultation process, with effect from 1 July 2023, on the use of the site in the immediate future, in particular to repurpose GIS so that its primary use is for the purposes of education and sport be approved. (ii) That the Council collaborating with Gateshead College to negotiate and then deliver a new operating model for GIS be approved. (iii) That further market investigation into a longer-term solution to put GIS (excluding sports pitches) to the open market to complement and enhance the education and sport offer be approved. (iv) That a further report be submitted to Cabinet in November 2023 following the consultation process and open market exercise. The above decisions have been made for the following reasons: (A) To enable the development of a proposal which achieves the cost neutral objective to the Council. (B) To ensure that any future recommendations for the use of the GIS are made after seeking appropriate information about their potential impact upon the facility users, community groups and those users who are protected under the Equality Act.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. This report seeks Cabinet approval to progress the Options Appraisal for Gateshead International Stadium (GIS) by taking forward the proposal recommended in paragraph 7-9 below.

Background

2. On the 25th of October 2022, Cabinet (minute number C60) approved:

a. That consideration of the future operating model for the Gateshead International Stadium should be undertaken separately to that of the Council’s wider leisure centre offer, and that it should take the form of a detailed options review followed by a report to Cabinet identifying potential options for the future use of the site and making recommendations for further action.

b. To approve the commencement of a procurement process to identify and contract with a service provider partner to manage the council’s leisure centres and swimming pools under a services contract.

c. To commence a comprehensive public and employee consultation process to both understand the impact of any leisure centre closures and influence the final evaluation of which of them should remain open, and then to receive a report setting out proposals for a reduction in the overall size of the Council’s leisure centres offer.

3. Subsequently, on the 24th of January 2023, Cabinet approved (minute number C97):

a. the commencement of the Options Review on GIS, and b. to receive the further report in July 2023.

4. This report provides an update of the progress made to date and sets out a proposal to progress the Options Appraisal.

Scope, Vision, and Objectives

5. The scope of this report is focused on the future service delivery options for GIS. Whilst GIS is managed within the organisational structure of Leisure Services, it has a wider and significantly different offer to the other facilities in the Leisure Services portfolio. Specifically, as it was built for international athletics events, it provides its key tenants with facilities that both accommodate spectators and enable their own professional sports and educational offers. This is the GIS’s unique selling point (USP). These facilities supplement but are separate from GIS’s own leisure centre health and fitness provision. Options Appraisal – Work and findings to date

6. The council has appointed FMG Consulting to provide specialist support in the process and consider/assess the financial ability of achieving the desired outcome of net zero budget (no financial subsidy from Gateshead Council). To date, the analysis has identified seven factors which will impact on the options for future use and financial sustainability of the site:

a. The site has a broad range of users including, athletics, health and fitness, sports clubs, education, professional sport and charitable organisations. A list of users is included in Appendix 1. Further deep dive work is required to support the development of a fully informed integrated assessment to understand the potential impact of the various options upon facility users, community groups and, as a statutory requirement, those protected under the Equalities Act.

b. The site contains significant amounts of contained sub-surface contamination from its industrial past. The containment infrastructure is currently managed by the Council and will require continuing monitoring and management to remain effective and to enable the Council to meet its statutory obligations as the local regulator of soil contamination.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Gateshead International Stadium: Options AppraisalReport 142 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 26 attended
GC
Gaylor CarleCouncil Staff, expected
LB
Linda BartramCouncil Staff, expected
AD
Alison DunnCouncil Staff, expected
SC
Sarah CoxonOfficer, expected
NP
Neil PorteousOfficer, expected
CO
Craig OakesCouncil Staff, expected
AT
Andrew TateCouncil Staff, expected
IB
Iain BurnsCouncil Staff, expected
DW
Deborah WiseCouncil Staff, expected
ER
Emma ReynardCouncil Staff, expected
MG
Councillor Martin GannonChair, present
CD
Councillor Catherine DonovanVice-Chair, apologies

All 26 on the meeting page

On this subject at Gateshead

Search all
  1. Gateshead International Stadium – Options AppraisalThis decision
  2. Gateshead International Stadium - Options Appraisal UpdateApproved
  3. Gateshead International Stadium - Options AppraisalApproved
  4. Gateshead International Stadium - Investment to host International AthleticsApproved
  5. Gateshead International Stadium Safety CertificateApproved
  6. Gateshead International Stadium Safety CertificateApproved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies