RESOLVED - (i) That the outcome of the stakeholder consultation process as set out in appendix 1, paragraph 12 and appendix 2 to the report be approved. (ii) That the negotiations currently underway with Gateshead College be noted. (iii) That ongoing further market investigation into a longer-term solution to put GIS (excluding sports pitches) to the open market to complement and enhance the education and sport offer be noted. (iv) That the inclusion of GIS within the agreed procurement process for the operation of the Council’s Leisure Centres be approved. (v) That a further report be submitted to Cabinet in June 2024. The above decisions have been made for the following reasons: (A) To enable the development of a proposal which achieves the cost neutral objective to the Council. (B) To ensure that any future recommendations for the use of the GIS are made following a thorough options appraisal process to identify an approach, which achieves a net zero budget, whilst considering the impact this may have upon the facility users, community groups and those users who are protected under the Equality Act.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report provides an update on the progress made in the options appraisal for the Gateshead International Stadium (GIS) and seeks Cabinet approval to progress further by taking the measures that are recommended in paragraph 9.
Background
2. On the 24 January 2023, Cabinet approved (minute number C97):
i. the commencement of the Options Review on GIS, and ii. to receive the further report (Paragraph 1.2 above) in July 2023
3. Subsequently, on 20 June 2023, Cabinet approved (minute number C18):
i. the commencement of a consultation process on the following proposals for the use of the site in the immediate future: a. Repurpose GIS so that its primary use is for the purposes of education and sport b. Collaborate with Gateshead College to negotiate and then deliver a new operating model for GIS; ii. further market investigation into a longer-term solution to put GIS (excluding sports pitches) to the open market to complement and enhance the education and sport offer; and iii. to receive a further report in November 2023.
4. This report provides an account of the progress made in the options appraisal since June 2023 and makes recommendations for undertaking the additional steps that are considered necessary to complete the appraisal process.
Scope, Vision, and Objectives
5. The scope of this report is focused on the future service delivery options for the GIS. Cabinet should note that whilst the GIS is managed within the organisational structure of Leisure Services, it has a wider and significantly different offer to the other facilities in the Leisure Services portfolio. Specifically, as it was built for international athletics events, it provides its key tenants with facilities that both accommodate spectators and enable their own professional sports and educational offers.
The vision and the objective are to find an option (or several connected options) for the future use of the GIS for education and sport and which at the same time reduces its financial dependence on the Council to achieve net zero site costs. Options Appraisal – ongoing work and updates
6. Following Cabinet approval in June 2023, there has been progress across several workstreams:
i. A stakeholder engagement process has been undertaken starting on 5th July 2023 and closing on 2nd October 2023. The main purpose of that engagement was to understand how stakeholders currently use GIS and what they value about GIS, whether they agreed with the future purpose of the site, and any suggestions on future sustainability of GIS. An overview of the responses received and key themes is at appendix 1 paragraph 12, and the full stakeholder engagement report is at appendix 2. ii. Proposals for consideration by Gateshead College on a future operating model for GIS are being progressed by the Council and will be discussed with and considered by the College in due course. These discussions are commercially confidential and will be reported to Cabinet at a later date.
iii. Work is underway to progress the market investigation into a longer-term solution to put GIS (excluding sports pitches) to the open market to complement and enhance the education and sport offer. This task is being led by FMG Consulting with the support of Savills.
7. Given the complexities of the options appraisal and the need to thoroughly explore all possible options, achieving net zero budget by 1st April 2024 may be unachievable. However, through consultation and negotiation, it may be possible to significantly reduce the operating budget and retain the current management arrangements. There may also be an opportunity to leverage rental income from the site to help support the operating costs.
Proposal
8. This report proposes that the Council should:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.