i ) That the full planning applications and outline applications specified in the appendix to these minutes be granted, refused or referred to the Department for Communities and Local Government or deferred as indicated subject to the conditions, if any, as specified therein and to any other appropriate conditions of a routine or standard nature. ii) That the applications granted in accordance with delegated powers be noted.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
Appendix Date of Committee: Wednesday 6th September 2023
Application Number and Address: Applicant:
DC/23/00138/FUL [name removed] 1 Long Bank Birtley DH3 1PX
Proposal:
Erection of detached house with integral garage and four bedrooms (amended 30/05/23).
Declarations of Interest:
Name Nature of Interest
None None
List of speakers and details of any additional information submitted:
Councillor Sheila Gallagher spoke as a ward councillor against the application. [name removed] spoke as Agent in favour of the application.
GRANT permission subject to the following condition(s) and that the Service Director of Climate Change, Compliance, Planning and Transport be authorised to add, vary and amend the planning conditions as necessary:
1 Unless otherwise required by condition, the development shall be carried out in complete accordance with the approved plan(s) as detailed below:
357 LP Location Plan 357 SV Street View 357 HD Highways details 357 PSPc Proposed Site Plan 357 05 Proposed Plans 357 06 Proposed Elevations DTP/3707923/ATR001 Proposed site layout swept path analysis large car Cycle Store Plans Received 14 August 2023
Any material change to the approved plans will require a formal planning application to vary this condition and any non-material change to the plans will require the submission of details and the agreement in writing by the Local Planning Authority prior to any non-material change being made. 2 The development to which this permission relates must be commenced not later than 3 years from the date of this permission.
3 Prior to the commencement of the development hereby approved details of all materials and external finishes shall be submitted to and approved in writing by the Local Planning Authority.
4 The materials and external finishes approved under condition 3 shall be implemented in full accordance with the approved details
5 The dwelling hereby approved shall not be occupied until final details of the appearance and siting of boundary treatments have been submitted to and approved in writing by the Local Planning Authority.
6 The boundary treatment details approved under condition 5 shall be implemented in accordance with the approved details before the dwelling hereby approved is occupied and retained as such for the lifetime of the development.
7 Notwithstanding the provisions of the Town and Country Planning (General Permitted Development) (England) Order 2015 (or any Order revoking, re-enacting, substituting, amending, extending, consolidating replacing or modifying that Order), no enlargements, additions, incidental buildings, within Part 1, Classes A, B and E of Schedule 1 shall be erected/installed on the land, except in the event that a further planning permission is expressly granted for that development.
8 Unless otherwise approved in writing by the Local Planning Authority, all external works and ancillary operations in connection with the construction of the development, including deliveries to the site, shall be carried out only between 0800 hours and 1800 hours on Mondays to Saturdays and at no time on Sundays, Bank Holidays or Public Holidays.
9 No development hereby approved shall take place until a Construction Management Plan (CMP) has been submitted to and approved in writing by the Local Planning Authority. The Plan shall provide for:
(a) Hours of site operation
(b) The parking of vehicles of site operatives and visitors
(c) Storage of plant and materials used in constructing the development
(d) Wheel washing facilities (e) Measures to control the emission of dust and dirt during construction
(f) Measures to control noise and vibration during construction
(g) A waste management plan for recycling/disposing of waste resulting from construction works.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.