Resolved
i. That the information be noted.
Planning and Development Committee noted this item on Wednesday 4 September 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
i. That the information be noted.
1. To advise the Committee of the progress of enforcement action previously authorised by the Committee.
2. The properties, which are the subject of enforcement action and their current status, are set out in Appendix 2.
3. It is recommended that the Committee note the report. Contact: Elaine Rudman Ext: 4589
APPENDIX 1
Nil.
2. RISK MANAGEMENT IMPLICATIONS
Nil.
3. HUMAN RESOURCES IMPLICATIONS
Nil.
4. EQUALITY AND DIVERSITY IMPLICATIONS
Nil
5. CRIME AND DISORDER IMPLICATIONS
Nil.
6. SUSTAINABILITY IMPLICATIONS
Nil.
7. HUMAN RIGHTS IMPLICATIONS
The Human Rights Act states a person is entitled to the peaceful enjoyment of his possessions. However, this does not impair the right of the state to enforce such laws, as it deems necessary to control the use of property and land in accordance with the general interest.
8. WARD IMPLICATIONS
Birtley, Bridges, Blaydon, Pelaw & Heworth, Chowdene, Crawcrook & Greenside, Ryton, Crookhill and Stella, Chopwell and Rowlands Gill, Wardley & Leam Lane, Windy Nook And Whitehills, Winlaton and High Spen, Whickham North, Whickham South and Sunniside, Lobley Hill and Bensham. Lamesley, Dunston Hill and Whickham East and Low Fell.
9. BACKGROUND INFORMATION
Nil. APPENDIX 2 Item Site Ward Alleged Breach of Planning Date Approval Date Served Date Notice End of Case History Current Update Number Control given for comes into Compliance Enforcement Force Period Action 1. Blaydon Quarry Crawcrook Breach of Planning 22nd May 2019 24th May 28th June 2019 28th Blaydon Quarry is in breach of several 21.08.2024 -Soil samples were Lead Road, and Conditions 2019 December planning conditions. taken for analysis on Gateshead Greenside Condition 23 and Condition 2019 – 23.7.2024. Once the results of 24 Condition 23 A Notice has been served in relation to the samples are available, condition 23 to require installation of a they will be sent to the 28 October drainage system. The Council has Council with the relevant 2019 – designed an acceptable scheme to be discharge of condition Condition 24 installed in the interests of surface water application. drainage and to enable the safe and Richard Todd is looking to successful restoration of the site. arrange a liaison group meeting w/c 2nd September A site visit was undertaken on the 4th June although this will have to be 2019, where drainage works had rescheduled as unsuitable for commenced. Officers are working closely some key attendees. with the Operator of the quarry to ensure Invitations will be sent once compliance. the date has been confirmed. A discharge of condition A discharge of condition application has application has been received been submitted in relation to condition 23 for noise and vibration for the Council to assess. conditions (12 and 13) and have been discharged. An appeal has been submitted in relation Draft landscaping information to the enforcement notice. is in the process of being prepared. A Notice has been served in relation to condition 24 to require installation of the previously approved drainage system on the southern boundary, in the interests of surface water drainage and to enable the safe and successful restoration of the site.
A discharge of condition application has been submitted in relation to condition 24 for the Council to assess.
An appeal has been submitted in relation to the enforcement notice.
Wardell Armstrong on behalf of the Operator has withdrawn the Enforcement Appeal.
February 2023 - Development management have engaged a minerals and landfill specialist consultant to consider the current planning status of this development and determine an appropriate course of action should further enforcement activity be required.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Enforcement ActionReport | 158 KB | DownloadRead as text |
Follow Planning and Development Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 9 Sep 2026 | Planning Applicationsi) That the full planning applications and outline applications specified in the appendix to these minutes be granted... | Refused | Open |
| 9 Sep 2026 | No.1 - Alexandra Guest House, 377 Alexandra Road, Gateshead, NE8 4HYThat permission be GRANTED, subject to the following conditions and the addition of an Operational and Management Pla... | Approved | Open |
| 9 Sep 2026 | No.2 - St Cuthberts Clearance Area Land Between Askew RoadThat planning permission is GRANTED subject to the following conditions and that the Service Director of Climate Chan... | Approved | Open |
| 9 Sep 2026 | No.3 - Discover Leisure PLC,Portobello Road, Birtley, DH3 2SNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... | Approved | Open |
| 9 Sep 2026 | No.4 - 16 Langdale Road, Gateshead, NE9 5RNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.