Enforcement Action

Noted Planning 1 paper

AI summaryGateshead Planning Committee noted a progress update on 13 live planning enforcement cases across the borough, with no new decisions taken and no money committed.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedNo new enforcement decisions taken
MoneyNilNo financial implications identified
What happens nextCases continue to progressMonitoring, appeals and prosecutions ongoing
Who it affects13 enforcement sitesAcross most Gateshead wards

What was decided

The committee noted the progress report on previously authorised planning enforcement action. Report P1, P3

Why

The report was submitted to update the committee on the status of enforcement cases that the committee had previously authorised. Report P1, P2

All standard impact assessments (finance, risk, HR, equalities, crime and disorder, sustainability) were identified as having no implications. Report P5, P7, P9, P11, P13, P15

What happens next

A jury trial is listed for 26th April 2027 at Newcastle Crown Court for the operators of Jack and Jo's Ryton who face either-way charges for failing to comply with an enforcement notice on the unauthorised café building. Report P84

A further Case Management Hearing is set for 5 November 2025 at Newcastle Crown Court, joining the cases of the three named individuals. Report P87

The Council's demolition contractor remains on standby for the Kwik Save, High Street site, with a 3-week mobilisation window. Report P67

Options considered

  • Chosen: Note the report as recommended. Standard procedure for progress updates on previously authorised enforcement action Report P3

Implications

  • Legal: Two separate prosecutions are in progress against the operators of Jack and Jo's Ryton, with a jury trial date set for 26th April 2027. Report P83, P84, P87
  • Legal: The site owner of the Former MGM Engineering Factory was successfully prosecuted on 23.9.25 for non-compliance with a Community Protection Notice; case file has been submitted to legal for further prosecution. Report P111, P118
  • Legal: The Human Rights Act does not prevent the Council from enforcing laws that control the use of land in the general interest. Report P17
  • Risk: Risk management implications: Nil. Report P7
  • Equalities: Equality and diversity implications: Nil. Report P11
  • Staffing: Human resources implications: Nil. Report P9
  • Other: Crime and disorder implications: Nil as stated in the report, though cases such as Kwik Save and the Former MGM Factory involve ongoing arson, fly tipping and anti-social behaviour. Report P13, P55, P111

Who and where

  • Operators of the unauthorised café at Jack and Jo's Ryton, facing prosecution for non-compliance with an upheld enforcement notice Report P78, P84
  • Owner of the Former MGM Engineering Factory site, prosecuted and subject to ongoing fly tipping and arson issues Report P111, P116, P118
  • Owner of the Kwik Save site on High Street, Felling, with the Council's demolition contractor on standby Report P67, P70
  • Owner and occupier of Daveys Low Fell, currently considering relocation after appeal dismissed Report P101, P110
  • Landowners of the two Earls Drive sites (road planings and over-height fence), where ownership may have changed Report P138, P149
  • Owner of 9 Claypath, Gateshead, where a first floor door has been removed but a balcony remains Report P150
  • Operator of Blaydon Quarry, working with the Council to discharge outstanding planning conditions Report P49, P52

Timeline

  • 19 September 2025: Compliance deadline for the enforcement notice at 9 Claypath, Gateshead Report P150, P151
  • 23.9.25: Site owner of the Former MGM Engineering Factory prosecuted for non-compliance with a Community Protection Notice Report P111
  • 23 October 2025: Compliance deadline for the enforcement notice at The Borough Arms, 82 Bensham Road Report P154
  • 5 November 2025: Further Case Management Hearing at Newcastle Crown Court joining the cases of the three individuals Report P87
  • 12 November 2025: Deadline for appeal against the enforcement notice at 157 Bewick Road Report P157
  • 15 February 2026: Compliance deadline for the s215 Notices at 85-99 Woodbine Street Report P158
  • 12 March 2026: Compliance deadline for the enforcement notice at 157 Bewick Road Report P157
  • 26th April 2027: Jury trial at Newcastle Crown Court for the operators of Jack and Jo's Ryton Report P84

Plain English for the jargon

  • Section 215 Notice: A notice served under the Town and Country Planning Act 1990 requiring the owner to address land whose condition harms local amenity.
  • Community Protection Notice (CPN): A notice requiring a person to stop causing ongoing nuisance or harm to community life, served where behaviour persistently affects the community's quality of life.
  • Discharge of condition application: A formal request to the council to confirm that a planning condition attached to a permission has been complied with.
  • TPO: Tree Preservation Order, which protects specific trees from being cut down, topped or damaged without permission.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPD50

Resolved

i. That the information be noted.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Planning and Development Committee

Purpose of the report

1. To advise the Committee of the progress of enforcement action previously authorised by the Committee.

Background

2. The properties, which are the subject of enforcement action and their current status, are set out in Appendix 2.

Recommendation

3. It is recommended that the Committee note the report.

Contact: Elaine Rudman Ext: 3911 APPENDIX 1

Financial implications

Nil.

2. RISK MANAGEMENT IMPLICATIONS

Nil.

3. HUMAN RESOURCES IMPLICATIONS

Nil.

4. EQUALITY AND DIVERSITY IMPLICATIONS

Nil

5. CRIME AND DISORDER IMPLICATIONS

Nil.

6. SUSTAINABILITY IMPLICATIONS

Nil.

7. HUMAN RIGHTS IMPLICATIONS

The Human Rights Act states a person is entitled to the peaceful enjoyment of his possessions. However, this does not impair the right of the state to enforce such laws, as it deems necessary to control the use of property and land in accordance with the general interest.

8. WARD IMPLICATIONS

Birtley, Blaydon, Bridges, Chopwell and Rowlands Gill, Chowdene, Crawcrook & Greenside, Deckham, Dunston and Teams, Dunston Hill and Whickham East, Felling, High Fell, Lamesley, Lobley Hill and Bensham, Low Fell, Pelaw & Heworth, Ryton, Crookhill and Stella, Saltwell, Wardley & Leam Lane, Whickham North, Whickham South and Sunniside, Windy Nook and Whitehills, Winlaton and High Spen.

9. BACKGROUND INFORMATION

Nil. APPENDIX 2 Item Site Ward Alleged Breach of Planning Date Approval Date Served Date Notice End of Case History Current Update Number Control given for comes into Compliance Enforcement Force Period Action 1. Blaydon Quarry Crawcrook Breach of Planning 22nd May 2019 24th May 28th June 2019 28th Blaydon Quarry is in breach of several 22.10.2025 – Application has Lead Road, and Conditions 2019 December planning conditions. been received to discharge Gateshead Greenside Condition 23 and Condition 2019 – the landscaping condition. 24 Condition 23 A Notice has been served in relation to This is currently under condition 23 to require installation of a consideration. 28 October drainage system. The Council has The next liaison group 2019 – designed an acceptable scheme to be meeting is in the process of Condition 24 installed in the interests of surface water being arranged for 11th drainage and to enable the safe and November. Invites will be sent successful restoration of the site. in due course.

A site visit was undertaken on the 4th June 2019, where drainage works had commenced. Officers are working closely with the Operator of the quarry to ensure compliance.

A discharge of condition application has been submitted in relation to condition 23 for the Council to assess.

An appeal has been submitted in relation to the enforcement notice.

A Notice has been served in relation to condition 24 to require installation of the previously approved drainage system on the southern boundary, in the interests of surface water drainage and to enable the safe and successful restoration of the site.

A discharge of condition application has been submitted in relation to condition 24 for the Council to assess.

An appeal has been submitted in relation to the enforcement notice.

Wardell Armstrong on behalf of the Operator has withdrawn the Enforcement Appeal.

February 2023 - Development management have engaged a minerals and landfill specialist consultant to consider the current planning status of this development and determine an appropriate course of action should further Item Site Ward Alleged Breach of Planning Date Approval Date Served Date Notice End of Case History Current Update Number Control given for comes into Compliance Enforcement Force Period Action enforcement activity be required.

04.05.2023 – Site meeting took place with with owner, Environment Agency, Planning, Enforcement and consultant on 03.05.23.

Agreed on action that is required by owner to ensure compliance and required timescales.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enforcement ActionReport 206 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

13 of 21 attended
JT
Councillor Judith TurnerChair, present
KW
Councillor Keith WoodVice-Chair, present
VA
Councillor Vicky AndersonCommittee Member, present
DB
Councillor Dot BurnettCommittee Member, present
LC
Councillor Lynne CaffreyCommittee Member, apologies
SD
Councillor Sonya DickieCommittee Member, apologies
PE
Councillor Paul ElliottCommittee Member, present
AG
Councillor Alex GeddesCommittee Member, present
TG
Councillor Tom GrahamCommittee Member, apologies
HK
Councillor Hugh KellyCommittee Member, present
KM
Councillor Kathleen McCartneyCommittee Member, present
EM
Councillor Eileen McMasterCommittee Member, apologies

All 21 on the meeting page

On this subject at Gateshead

Search all
  1. Enforcement ActionThis decision
  2. Enforcement ActionNoted
  3. Enforcement ActionNoted
  4. Enforcement ActionNoted
  5. Enforcement ActionNoted
  6. Enforcement ActionNoted

More from Gateshead Planning and Development Committee

All decisions
MeetingDecisionOutcome
9 Sep 2026 Planning Applicationsi) That the full planning applications and outline applications specified in the appendix to these minutes be granted... Refused Open
9 Sep 2026 No.1 - Alexandra Guest House, 377 Alexandra Road, Gateshead, NE8 4HYThat permission be GRANTED, subject to the following conditions and the addition of an Operational and Management Pla... Approved Open
9 Sep 2026 No.2 - St Cuthberts Clearance Area Land Between Askew RoadThat planning permission is GRANTED subject to the following conditions and that the Service Director of Climate Chan... Approved Open
9 Sep 2026 No.3 - Discover Leisure PLC,Portobello Road, Birtley, DH3 2SNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open
9 Sep 2026 No.4 - 16 Langdale Road, Gateshead, NE9 5RNThat permission be GRANTED subject to the following condition(s) and that the Service Director of Climate Change, Com... Approved Open