Resolved
RESOLVED that i. the Treasury Management Performance to 30 September 2025, prior to submission to Cabinet on 18 November 2025 be noted.
AI summaryGateshead Council Audit and Standards Committee noted mid-year treasury performance to 30 September 2025, showing a projected revenue budget underspend of £0.087m, before Cabinet review on 18 November 2025.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED that i. the Treasury Management Performance to 30 September 2025, prior to submission to Cabinet on 18 November 2025 be noted.
2. The mid-year performance of the Treasury Management Service is reported in line with CIPFA’s Code of Practice on Treasury Management and the Council’s Treasury Policy Statement and Treasury Strategy 2025/26 to 2029/30 which was approved by Council on 20 March 2025.
3. The Council operates a balanced approach, and this broadly means that cash raised during the year will meet its cash expenditure. Part of the treasury management operations ensure this cash flow is adequately planned, with surplus monies being invested in low-risk counterparties, providing security and adequate liquidity initially before considering optimising investment return.
4. The second main function of the Treasury Management Service is the funding of the Council’s capital plans. These capital plans provide a guide to the borrowing need of the Council, essentially the longer-term cash flow planning to ensure the Council can meet its capital spending operations.
5. Accordingly, treasury management is defined as:
“The management of the Council’s borrowing, investments and cash flows, its banking, money market and capital market transactions; the effective control of the risks associated with those activities; and the pursuit of optimum performance consistent with those risks.”
6. The primary objective of the investment strategy is to safeguard the Council’s assets with a secondary objective of obtaining an optimum rate of return on investments and minimising the costs of borrowing.
Treasury Management Strategy Statement
7. The Treasury Management Strategy Statement (TMSS) 2025/26 to 2029/30 was approved by Council on 20 March 2025. There are no policy changes to the TMSS; the details in this report update the position in the light of the updated economic position and budgetary changes already approved. Investment Performance
8. The latest projection of gross investment income for 2025/26 based on interest earned to date and expected interest to 31 March 2026 is £2.273m, compared to an original estimate of £3.926m.
9. The gross investment interest is then adjusted to include other financial transactions with interest payable to or receivable from external parties:
Budget Projected Variance Outturn £m £m £m Gross Investment Interest (3.926) (2.273) 1.653
Interest paid/(received) on revenue balances 0.660 0.660 0 Interest due on loan balances from third parties (1.314) (1.448) (0.134) Temporary Loans & Internal/Trust Funds 0.003 0.003 0 Interest Receivable from Newcastle Airport (0.878) (0.878) 0
General Fund Total (5.455) (3.936) 1.519
This gives a projected 2025/26 net interest to the General Fund of £3.936m compared to the budget of £5.455m, a projected deficit of £1.519m. This is mainly due to the treasury management strategy of delaying borrowing until interest rates reduce which means that investment balances are lower than estimated.
The Economy
10. Interest rates have been on a downward curve from August 2024. The Bank of England’s Monetary Policy Committee (MPC) have agreed the following bank base rates in 2025/26:
Date Base Rate 01 April 2025 4.50% 08 May 2025 4.25% 07 August 2025 4.00%
Four further MPC meetings are scheduled in financial year 2025/26 and it is projected that the base rate will fall in the second half of the current financial year to around 3.75%.
Rate of Return
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Treasury Management Performance 2025/26: Mid year resultReport | 190 KB | DownloadRead as text |
Follow Audit and Standards Committee at Gateshead and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 14 Jul 2026 | Treasury Management Annual Report 2025/26RESOLVED that the Treasury Annual Report be submitted to Cabinet. | Decided | Open |
| 14 Jul 2026 | Treasury Management Quarter 1 ReportRESOLVED that the Treasury Management Performance at the 2026/27 First Quarter Review be noted. | Noted | Open |
| 14 Jul 2026 | Annual Report To CabinetRESOLVED that the report and the work undertaken by the Audit and Standards Committee during the period 01 July 2025 ... | Noted | Open |
| 14 Jul 2026 | Corporate Risk Management 2026/27 Quarter 1 UpdateRESOLVED that the report be noted, and the Council's risk management be considered effective. | Noted | Open |
| 14 Jul 2026 | Exclusion of the Press and PublicRESOLVED that the press and public be excluded from the meeting during consideration of Item 9 in accordance with Par... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.