Treasury Management – Performance to 30 September 2025
AgreedExecutive1 paper
AI summaryCabinet asks Council to note the half-year Treasury Management report, which projects a net underspend of £0.087m against the 2025/26 budget of £21.142m, with no new borrowing taken so far.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedSix-month Treasury Management performance to 30 September 2025
MoneyNet projected underspend £0.087mAgainst combined budget of £21.142m for 2025/26
What happens nextForward to full CouncilCabinet recommends the report is noted
Who it affectsCouncil finances, HRA tenants, taxpayersGeneral Fund, Housing Revenue Account and borrowing strategy
What was decided
Cabinet agreed to recommend that Council note the Treasury Management Performance to 30 September 2025. Report P10
The recommendation is made to support sound financial management and the long-term financial sustainability of the Council. Report P11
Why
Cabinet must receive half yearly performance reports on the agreed Treasury Management budget identifying any variances. Report P2
The Treasury Management Strategy's primary objective is to safeguard all assets through investment; the report confirms this has been achieved. Report P7
Effective budget monitoring and action planning in 2025/26 is needed to keep spending within approved budgets and protect the Council's sustainable financial position. Report P9
What happens next
Cabinet will forward the recommendation to full Council for the performance to be noted. Report P10
The borrowing strategy will be kept under regular review and revised if needed, with timing of further borrowing driven by cash flow and capital programme needs. Report P67
The Council will continue to monitor the market to identify opportunities to repay borrowing earlier than planned, subject to any discounts received. Report P78
The money
£21.142m Original 2025/26 Treasury Management budget, split £8.927m General Fund and £12.215m HRA Report P4
£21.055m Combined projected outturn for 2025/26 at 30 September 2025 Report P22, P76
£0.254m Projected General Fund overspend (£9.181m against £8.927m) Report P6, P76
£0.341m Projected HRA underspend (£11.874m against £12.215m) Report P6, P76
£3.936m Projected 2025/26 net interest to the General Fund, against a budget of £5.455m Report P53, P54
£1.519m Projected deficit on General Fund net interest against budget Report P53, P54
£24.529m Forecast interest payable combined (General Fund £12.655m and HRA £11.874m), against a budget of £26.135m Report P69
£1.606m Gross saving on interest payable against original estimate Report P69
£2.273m Projected gross investment income for 2025/26, against an original estimate of £3.926m Report P49
£660.182m Total Council and HRA borrowing at 30 September 2025 (within the £836.000m operational limit) Report P65, P83
£836.000m Operational borrowing limit for 2025/26 Report P65, P83
£851.000m Authorised external debt limit for 2025/26 Report P83
Options considered
Chosen: Note the Treasury Management Performance to 30 September 2025. Required to comply with the policy on delegation, review requirements and reporting arrangements in the Treasury Policy Statement and Treasury Strategy. Report P10, P11, P26
Implications
Financial: Combined 2025/26 Treasury Management outturn is projected at £21.055m, an underspend of £0.087m against the £21.142m budget, with a General Fund overspend of £0.254m offset by an HRA underspend of £0.341m. Report P6, P22, P75, P76
Financial: The Council has not taken any new borrowing in the year to date and is delaying external borrowing, which has lowered both borrowing costs and investment income compared with budget. Report P23, P66
Risk: The Treasury Policy and Strategy were prepared with the primary aim of minimising risk to safeguard principal sums; maximising income is secondary. Report P33
Legal: The Council is required by regulation to have regard to the CIPFA Prudential Code under Part 1 of the Local Government Act 2003, and to MHCLG guidance on Local Government Investments under Section 15 of the same Act. Report P15, P18
Staffing: There are no human resources implications arising from this report. Report P30
Equalities: There are no equality and diversity implications arising from this report. Report P35
Climate: There are no climate emergency or sustainability implications arising from this report. Report P40
Who and where
Gateshead Council as a whole, through its General Fund and Housing Revenue Account Report P4, P6
Council tax payers and residents, given the Council's financial sustainability and pressures on partners and local businesses Report P9, P14
HRA tenants, given the £0.341m underspend on HRA borrowing costs Report P6, P76
Counterparties and the PWLB, as the Council delays new borrowing and reshapes its investment portfolio Report P23, P65, P66
Timeline
20 February 2025: Council agreed the original 2025/26 Treasury Management budgets of £21.142m Report P4
20 March 2025: Council agreed the Treasury Policy Statement and Treasury Strategy 2025/26 to 2029/30 Report P3, P20
01 April 2025: Bank of England base rate at start of 2025/26 was 4.50% Report P57
08 May 2025: Bank of England base rate reduced to 4.25% Report P57
07 August 2025: Bank of England base rate reduced to 4.00% Report P57
30 September 2025: Date of the mid-year Treasury Management performance position reported to Cabinet Report P1, P22
4 November 2025: Audit and Standards Committee reviewed the Treasury Management performance for the six months to 30 September 2025 Report P8
18 November 2025: Cabinet considered the mid-year Treasury Management performance report
31 March 2026: End of 2025/26 financial year, by which further base rate reductions are forecast Report P58, P63
Plain English for the jargon
Treasury Management: The management of the Council's cash flows, borrowing and investments to support its services.
HRA: Housing Revenue Account, the ring-fenced account that holds the income and costs of the Council's own housing stock.
General Fund: The main council account for services funded by council tax, government grants and other non-HRA income.
PWLB: Public Works Loans Board, a government body that lends to local authorities for capital projects.
CFR: Capital Financing Requirement, the Council's underlying need to borrow for capital purposes.
CIPFA: Chartered Institute of Public Finance and Accountancy, which publishes the Prudential Code and Treasury Management Code of Practice.
Prudential Code: CIPFA professional code of practice requiring councils to set and monitor affordable borrowing limits.
MHCLG: Ministry of Housing, Communities and Local Government, which issues guidance on local authority investments.
MPC: Bank of England's Monetary Policy Committee, which sets the bank base rate.
Liability Benchmark: CIPFA indicator showing the Council's net borrowing requirement plus a liquidity allowance, used to judge optimum borrowing.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC93
Resolved
i) Cabinet agreed to recommend that Council note the Treasury Management Performance to 30 September 2025. The above decision was made for the following reason: a) To support sound financial management and the long-term financial sustainability of the Council.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. The purpose of this report is to review Treasury Management performance for the six months to 30 September 2025, covering investments and borrowing. This is consistent with approved performance management arrangements.
Background
2. Cabinet will receive half yearly performance reports on the agreed Treasury Management budget identifying any variances. This report sets out the monitoring position at 30 September 2025.
3. On 20 March 2025, Council agreed the Treasury Policy Statement and Treasury Strategy 2025/26 to 2029/30 which provided a framework for the Strategic Director, Resources and Digital to exercise his delegated powers.
4. On 20 February 2025, Council also agreed the original Treasury Management 2025/26 budgets of £21.142m, split £8.927m for General Fund and £12.215m for the Housing Revenue Account (HRA).
Mid Year Update
5. The projected outturn for 2025/26 at 30 September 2025 for the General Fund is £9.181m compared to the budget of £8.927m, an overspend of £0.254m. The HRA projection is £11.874m compared to the budget of £12.215m, an underspend of £0.341m.
6. The primary objective of the Treasury Management Strategy is to safeguard all assets (investments). The proposals in the report confirm this has been achieved.
7. On 4 November 2025, the Audit and Standards Committee reviewed the Treasury Management performance for the six months to 30 September 2025.
8. It is important that effective budget monitoring and action planning is in place to ensure that spending in 2025/26 is contained within approved budgets as this will contribute to a sustainable financial position for the Council. Recommendation
9. It is recommended that (i) Cabinet recommend that Council note the Treasury Management Performance to 30 September 2025.
For the following reason (ii) to support sound financial management and the long-term financial sustainability of the Council.
CONTACT: Terence Appleby ext. 2468 APPENDIX 1
Policy Context
1. The proposals in this report are consistent with Council priorities and in particular they ensure that effective use is made of the Council’s resources to ensure a sustainable financial position and support of the framework for achieving the Council’s strategic approach ‘Making Gateshead a Place Where Everyone Thrives’. The Council recognises there are huge financial pressures on not just Council resources, but those of partners, local businesses and residents. This requires the Council’s decision-making to be policy and priority led and driven.
2. The Prudential Code plays a key role in capital finance in local authorities. Local authorities determine their own programmes for capital investment that are central to the delivery of quality public services. The Prudential Code was developed by CIPFA, the Chartered Institute of Public Finance and Accountancy, as a professional code of practice to support local authorities in taking their decisions. Local authorities are required by regulation to have regard to the Prudential Code when carrying out their duties in England and Wales under Part 1 of the Local Government Act 2003.
3. In December 2021 CIPFA issued a revised Treasury Management Code of Practice and a revised Prudential Code (the Code) which represent best practice. The Council fully complies with the Code and this contributes towards achieving good practice.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.