Gateshead Metropolitan Borough Council
Cabinet, Tuesday 18 November 2025 at 10.00am

Capital Programme and Prudential Indicators - Second Quarter Review

Agreed Executive 1 paper

AI summaryCabinet recommends Council approve revised 2025/26 capital programme of £136.624m, down from original £157.232m, with all prudential indicators confirmed within limits.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedVariations and revised financing agreed
Money£136.624mRevised 2025/26 capital programme
What happens nextCouncil to decideFinal approval of variations and financing
Who it affectsBorough-wide capital projectsHRA, transport, schools, housing, regeneration

What was decided

Cabinet agreed to recommend to Council the variations to the 2025/26 Capital Programme. Report P18

Cabinet agreed to recommend to Council the revised financing of the programme. Report P18

Cabinet confirmed to Council that capital expenditure and financing requirements have been revised in line with the amended budget and that no approved Prudential Indicators have been breached. Report P18, P57

Why

To ensure the optimum use of the Council's capital resources in 2025/26. Report P20

To accommodate changes to the Council's in-year capital expenditure plans. Report P20

To ensure performance has been assessed against the approved Prudential Limits. Report P20

What happens next

Recommendations to be considered by full Council. Report P18

Cabinet will continue to receive quarterly reports on the capital programme. Report P36

Performance against prudential indicators to continue to be monitored. Report P15, P57

The money

  • £157.232m Original 2025/26 capital programme budget agreed by Council on 20 February 2025 Report P2, P14, P25
  • £136.624m Q2 revised 2025/26 capital programme Report P2, P13, P14, P26
  • £20.6m Forecast slippage in 2025/26 Report P9
  • £41.1m Net additional spend over revised 5-year programme compared to original £625.3m Report P9
  • (£12.856m) HRA schemes slippage: Communal M&E, Digital Transformation, Energy and Carbon Net Zero, Decent Homes Report P4
  • £1.714m Local Transport Plan Planned Maintenance accelerated Report P5
  • 48,220 General Fund Borrowing Q2 revised (£'000) Report P54
  • 51,060 Capital Grant Funding Q2 revised (£'000) Report P54

Options considered

  • Chosen: Recommend variations to 2025/26 Capital Programme and revised financing to Council. Proposed financing arrangements are the best available to ensure optimum use of capital resources in 2025/26 Report P18, P20, P31

Implications

  • Financial: Revised capital programme of £136.624m for 2025/26, funded through borrowing, capital grants, capital receipts and the Major Repairs Reserve; Strategic Director, Resources and Digital confirms financial implications are as set out in the report. Report P13, P14, P33
  • Risk: Risks are assessed as part of programme monitoring and treasury management; Cabinet will continue to receive quarterly reports to ensure expenditure is managed within available resources. Report P36
  • Equalities: No equality and diversity implications arising from this report. Report P37
  • Other: No human resources, direct property, crime and disorder, health, or human rights implications identified. Report P34, P35, P38, P39, P41
  • Climate: Sustainability implications considered as part of individual capital projects; planned investment expected to result in improvements throughout the Borough. Report P40

Who and where

  • Residents across the borough receiving capital improvements Report P42
  • HRA tenants (housing capital works including Decent Homes, heating, lifts, building safety) Report P4, P48, P49, P50
  • School pupils and families (school condition and basic need works) Report P5, P47
  • Road and transport users (Local Transport Plan, street lighting, traffic signals) Report P4, P5, P47
  • Council taxpayers (borrowing and financing costs) Report P14, P54

Timeline

  • 20 February 2025: Council agreed original 2025/26 capital programme of £157.232m and prudential indicators Report P2, P15, P25, P29
  • 17 July 2025: Council considered Q1 capital programme review Report P45
  • 30 September 2025: End of Q2; position reported in this paper Report P1, P56
  • 18 November 2025: Cabinet agreed to recommend Q2 variations and financing to Council Report P21
  • July 2026: Expected completion of Children's Three Bed Residential Assessment Service (Fell View) Report P4

Plain English for the jargon

  • Prudential Indicators: Limits under CIPFA's Prudential Code that regulate borrowing and investment
  • MTFS: Medium Term Financial Strategy
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC92

Resolved

i) Cabinet agreed to recommend to Council the variations to the 2025/26 Capital Programme. ii) Cabinet agreed to recommend to Council the revised financing of the programme. iii) Cabinet confirmed to Council that capital expenditure and financing requirements have been revised in line with the amended budget and that no approved Prudential Indicators have been breached. The above decision was made for the following reasons: a) To ensure the optimum use of the Council’s capital resources. b) To accommodate changes to in-year capital expenditure plans. c) To ensure performance is assessed against approved Prudential Limits.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. This report sets out the latest position on the 2025/26 Capital Programme and Prudential Indicators at the end of the second quarter to 30 September 2025. The report assesses reasons for the variances from the approved programme and details the proposed financing of the Capital Programme. In addition, the report considers the impact of CIPFA’s Prudential Code on the Capital Programme and the monitoring of performance against the statutory Prudential Indicators.

Background

2. The original budget for the Capital Programme for 2025/26, as agreed by Council on 20 February 2025, totalled £157.2m. At the first quarter review, this reduced to £145.5m and at the second quarter review expenditure is now projected to be £136.6m, £100.6m General Fund and £36.0m HRA by year end.

3. The proposed changes to the 2025/26 Capital Programme are shown in appendix 2 and are summarised below.

Slippage • (£12.856m) HRA schemes – reprofiling of Communal Mechanical and Electrical, Digital Transformation and Energy and Carbon Net Zero schemes due to Building Safety Regulator requirements and reprofiling in Decent Homes schemes to enable a review of schemes scope and approach to delivery. • (£3.587m) City Regional Sustainable Transport Settlement – re-profiling of scheme. • (£1.003m) Street Lighting Column Replacement – re-profiling of scheme. • (£0.570m) Children’s Three Bed Residential Assessment Service (Fell View) – Works delayed and now expected to complete in July 2026.

Accelerated spend • £1.714m Local Transport Plan – Planned Maintenance • £1.479m School Basic Need Funding – re-profiling based on planned works • £0.576m School Condition Fund – re-profiling based on planned works • £1.487m High Street South – acquisitions and demolition of Computer House • £0.550m Railway Quarter – grant funded scheme • £0.544m Transforming Cities – tranche 2 • £0.510m Sister Winifred Laver

1 of 5 New projects added to the current year

• £0.653m UKSPF funded projects • £0.541m South Farm Barlow – land purchase for woodland creation

4. The other changes relate to minor amendments to realign the schemes within the programme based on updated forecasts from project leads.

5. It is also important to consider how a change in year impacts the five-year programme. Appendix 3 demonstrates how slippage in one year impacts future years as resources are realigned to the revised phasing of schemes. Whilst there is slippage of £20.6m forecast in the current year, over the five-year programme it is estimated that spend will be £41.1m more than the original £625.3m approved by Council in February 2025. The main reasons for this are:

• Additional grant funding on Transport schemes within Economy, Innovation and Growth • Additional grant funding for Schools SEN and additional spend on waste collection vehicles within Housing, Environment and Health Communities • Slippage from previous years and new grant funded projects.

6. Appendix 4 shows how the revised five-year programme is expected to be funded based on the information available. This position may change as we move towards outturn, particularly if further grant funding becomes available.

Proposal

7. The report identifies revised planned capital expenditure of £136.624m for the 2025/26 financial year. The expected resources required to fund the Capital Programme for each revision are shown below:

Original Qtr. 1 Qtr. 2 Budget Revised Revised £m Budget Budget £m £m Borrowing 70.483 50.066 48.220 Capital Grants & Contributions 41.654 45.267 51.060 General Fund Capital Receipts 0.750 1.326 1.326 Major Repairs Reserve (HRA) 18.868 20.886 20.886 HRA Capital Receipts 25.219 27.568 13.980 Capital Grants & Contributions (HRA) 0.258 0.420 1.152 Total 157.232 145.533 136.624

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme and Prudential Indicators: Second Quarter ReviewReport 692 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 16 attended
MG
Councillor Martin GannonChair, present
GH
Councillor Gary HaleyVice-Chair, present
CD
Councillor Catherine DonovanCommittee Member, present
JA
Councillor John AdamsCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MH
Councillor Maria HallCommittee Member, present
LK
Councillor Leigh KirtonCommittee Member, apologies
JM
Councillor John McElroyCommittee Member, present
BO
Councillor Bernadette OliphantCommittee Member, present
MM
Melvyn Mallam-ChurchillSecretary, in attendance
BF
Brian FaganOfficer, expected

All 16 on the meeting page

On this subject at Gateshead

Search all
  1. Capital Programme and Prudential Indicators - Second Quarter ReviewThis decision
  2. Capital Programme and Prudential Indicators - Year End Outturn 2025-26Noted
  3. Capital Programme and Prudential Indicators - First Quarter Review 2026-27Approved
  4. Capital Programme and Prudential Indicators – Year End Outturn 2025-26Approved
  5. Capital Programme and Prudential Indicators – First Quarter Review 2026-27Approved
  6. Transport Capital Programme Year End ReportApproved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open