AI summaryCabinet approves demolition of Warwick Court and neighbouring Gloucester pub, planned for 2027, so the site can be redeveloped as part of Gateshead town centre regeneration.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedWarwick Court and the Gloucester pub to be knocked down
MoneyNot stated
What happens nextProcure demolition contractorAnd decant remaining tenants and temporary residents first
Who it affectsTenants, temporary residents, library usersAnd people living near the site in Regent Court
What was decided
Cabinet approved the demolition of Warwick Court and the neighbouring Gloucester pub, with works planned for 2027, and agreed to decant remaining tenants and temporary accommodation to allow this. Report P1
The cleared site will be considered as part of the wider Gateshead town centre regeneration planning. Report P1
Why
The HRA asset strategy 2022-2027 identified Warwick Court as a building that harmed the viability of the Housing Revenue Account, with data showing high repair frequency, arrears and voids. Report P5, P6
The buildings are in poor condition and have suffered from anti-social behaviour, which demolition is expected to reduce, and the site is needed for town centre regeneration and new, better-quality housing. Report P12, P16
What happens next
The Council will procure a demolition contractor, with works scheduled for 2027 after the Gloucester pub lease expires. Report P1, P11
Remaining tenants and temporary accommodation users will be moved to alternative housing, and the Council will support the Kittiwake Trust, currently based in the Gloucester pub, to find a new location if possible. Report P11, P13
Options considered
Rejected: Refurbishment of Warwick Court. Soft market testing and a cost plan on refurbishment and demolition options were considered; demolition was chosen to support regeneration and address HRA viability. Report P7
Implications
Legal: Planning permission will be required for the demolition works, with noise and dust controls to be set through the planning process. Report P12
Equalities: The closure of the Gloucester pub will affect non-English speakers, refugees and asylum seekers who use the Kittiwake Trust Multilingual library, although the Council says it has no obligation to relocate the Trust. Report P11
Risk: Demolition works carry a risk of increased anti-social behaviour at the site, and noise and dust will affect neighbouring Regent Court and passers-by. Report P12
Climate: Replacement housing is expected to be of higher quality and more energy efficient, improving housing stock standards. Report P13
Other: The car park at Warwick Court currently used for Council vans and large goods vehicles will be lost, with overall traffic volume at the site expected to reduce. Report P12
Who and where
Remaining tenants at Warwick Court
Temporary accommodation users at Warwick Court, including care leavers and people with complex needs Report P11
Users of the Kittiwake Trust Multilingual library in the Gloucester pub, including refugees and asylum seekers Report P11
Residents of neighbouring Regent Court Report P12
People working in or visiting Gateshead town centre Report P12
Timeline
2022: Consultation with residents as part of the HRA surplus declaration. Report P8
2027: Demolition of Warwick Court and the Gloucester pub planned, after the Gloucester pub lease expires. Report P1, P11
Plain English for the jargon
HRA: Housing Revenue Account, the council's landlord account for its own housing stock.
ASB: Anti-social behaviour.
LGV: Large goods vehicle.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC142
Resolved
i) the demolition of Warwick Court, with demolition planned for 2027, be approved. ii) that remaining tenants and temporary accommodation be decanted to enable demolition. iii) the site be considered as part of wider Gateshead town centre regeneration planning. The above decision was made for the following reasons: a) To support regeneration priorities and delivery of sustainable housing. b) To ensure investment is targeted towards long-term outcomes and community need. c) To make the site available as part of Gateshead Town Centre Regeneration.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
Integrated Impact Assessment Details of the Activity Title of the activity: Recommendation for the demolition of Warwick Court Description of the activity: The report is to seek approval from cabinet for the demolition of Warwick Court and neighbouring Gloucester . The report details an options appraisal and identifies the appropriate approval of this report from cabinet will allow the Council the ability to procure a demolition contractor to undertake the works in 2027. Group: Housing, Environment and Healthy Communities
Does the activity impact all of Gateshead or a specific ward? Specific ward in Gateshead
Which specific ward(s) in Gateshead does the activity impact? (if applicable) Not applicable
What stage is the activity/project at? Pre-project / initial idea
Data and Intelligence What data and intelligence has been used and how has this informed the activity? The HRA asset strategy 2022-2027 a business planning tool was utilised to assess the assets within the HRA, this identified Warwick Court as a building which negatively impacted HRA viability.
Intelligence from the HRA sustainability indicators were utilized to demonstrate the stock sustainability issues including repair frequency, arrear levels and voids.
Soft Market testing and a cost plan on options including refurbishment and demolition were considered.
Summary of consultation/data/research undertaken to inform the assessment: Consultation with residents was undertaken as part of the HRA surplus declaration in 2022.
Market testing was undertaken to understand market interest into refurbishment and future redevelopment of the scheme.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.