Gateshead Metropolitan Borough Council
Cabinet, Tuesday 24 February 2026 at 10.00am

Highway Asset Management Plan Annual Information Report

Noted Executive 1 paper

AI summaryCabinet approved revised targets for the Highway Asset Management Plan and changes to the Highway Safety Inspection Policy. Measures underway include a new pothole repair machine, LED traffic signal conversion, and carbon reduction in resurfacing materials.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRevised targets and inspection policy updates approved
Money£1.8 million DfT uplift for 2025/26Extra capital funding, with £380,000 held back pending compliance
What happens nextDrainage and decarbonisation strategies in 2026New HAMP document to be published in 2026
Who it affectsAll wards in GatesheadResidents, road users, emergency services, freight industry

What was decided

Cabinet noted progress updates and approved the revised HAMP targets, covering life cycle planning, pothole repair, drainage, and decarbonisation. Report P29, P37

Cabinet approved minor changes to the Highway Safety Inspection Policy, including a new definition for link roads and a reinstated CW4d inspection category. Report P34, P93, P94

Why

To optimise investment in the highway network, valued at £1.872 billion at replacement cost. Report P3

To support effective management and maintenance of highway assets, including the 560 mile road network, 740 miles of footway, and 289 structures. Report P43

To maximise external funding and reduce carbon impact, with 82.5 tons of CO2e saved in the 2024/25 resurfacing programme. Report P19, P77

What happens next

Demolition of Gateshead viaduct to commence in January 2026, with principal inspections of Redheugh Bridge, Blaydon viaduct, and Scotswood Bridge due in the same month. Report P24, P26

New drainage strategy and decarbonisation strategy for highway infrastructure to be completed in 2026, with a new HAMP document published in the new year. Report P22, P30, P82

LED conversion of the remaining 48 of 180 traffic signal sites to continue, and a five year Pothole Pro patching programme to proceed in 2025/26. Report P16, P20

The money

  • £ 1.872 billion Replacement cost of Gateshead highway asset Report P3
  • £1.8 million Extra DfT capital funding uplift for 2025/26 Report P9
  • £380,000 DfT funding held back subject to compliance report Report P9
  • 2,934,297 Total planned maintenance capital programme 2024/25 (£) Report P73
  • £2,203,150 Total value of 2024/25 resurfacing programme Report P77
  • 1,383,244 Reactive maintenance cost 2024/25 (£) Report P76

Options considered

  • Chosen: No alternative options were considered. Report states there are no alternative options Report P50

Implications

  • Financial: No direct financial implications arising from this report, confirmed by the Strategic Director, Resources and Digital. Report P52
  • Equalities: An Integrated Impact Assessment was completed, finding overall positive impact and reduced social exclusion for young, elderly, unemployed, and disabled residents. Report P56, P58
  • Climate: Warm lay and thin surface course materials are being used to reduce carbon, with a carbon reduction group established with Tarmac contractor. Report P19, P81
  • Risk: No risk management issues identified. Report P53
  • Legal: No legal implications, though policy detail can be challenged in court claims. Report P33, P54
  • Staffing: No human resource implications. Report P55

Who and where

  • All wards and areas of Gateshead Report P61
  • Residents and visitors using the road and footway network Report P2
  • Emergency services and the road freight industry Report P2
  • Young, elderly, unemployed or low waged people, and people with disabilities (per Integrated Impact Assessment) Report P56

Timeline

  • October 2025: Preparation commenced for demolition of Gateshead viaduct Report P24
  • January 2026: Demolition of Gateshead viaduct expected to commence Report P24
  • January 2026: Principal inspections due for Redheugh Bridge, Blaydon viaduct, and Scotswood Bridge Report P26
  • March 2026: DfT held-back funds expected to be released following compliance Report P9
  • 2026: New drainage strategy to be completed Report P22
  • 2026: Decarbonisation strategy for highway infrastructure to be completed Report P82
  • 2025/26: New Pothole Pro five year patching programme commenced Report P16
  • 2026/7: Full carriageway life cycle plan update scheduled Report P80

Plain English for the jargon

  • HAMP: Highway Asset Management Plan, the strategic framework for managing Gateshead's roads
  • TAMP: Transport Asset Management Plan, the regional plan covering Northeast authorities
  • NECA: Northeast Combined Authority, the regional body for transport devolution
  • DfT: Department for Transport, the UK government department providing highway maintenance funding
  • IIA: Integrated Impact Assessment, an assessment of equality, health, and other impacts
  • Pothole Pro: A specialist machine for high quality patching of large areas
  • CO2e: Carbon dioxide equivalent, the standard measurement of greenhouse gas emissions
  • PI: Principal Inspection, a detailed structural inspection of bridges and structures
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC143

Resolved

i) the progress updates be noted and the revised HAMP targets be approved. ii) the proposed changes to the Highway Safety Inspection Policy be approved. The above decision was made for the following reasons: a) To optimise investment in the highway network. b) To support effective management and maintenance of highway assets. c) To maximise opportunities for external funding and reduce carbon impact. d) To introduce measures to reduce carbon production in highway maintenance materials and operational maintenance procedures
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Purpose of the report

1. This report provides an annual information report to Cabinet outlining 2024/25 progress with the key targets and indicators involved in the delivery of the Gateshead Highway Asset Management Plan (HAMP) 2018-30 to effectively manage the council’s highway assets. It also recommends some minor changes to the Council’s Highway Inspection Policy.

Background

2. Gateshead’s road network provides a fundamental resource, essential to the economy of the area and for the quality of life for residents and visitors. Its effective management and maintenance have an impact on activity of all kinds, from day-to-day journeys to work, school, shopping or for leisure, through to the needs of the emergency services and the road freight industry. The HAMP provides the strategic framework for the management of this resource.

3 The highway network is the highest value asset in the authority’s ownership. As part of this year’s highways grant funding requirements the Department for Transport (DfT) requested an up-to-date assessment of the total value of our highway asset. The final figure based on the replacement cost was calculated at £ 1.872 billion.

4. The Gateshead HAMP must evidence how the Council are planning to utilise their highway maintenance funds and provide benchmarking data and progress reports on the Council’s key targets and policies. The Council’s HAMP forms part of the regional Transport Asset Management Plan (TAMP) and is one of the obligations of the devolution deal to access future highway maintenance funding from the new Northeast Combined Authority. (NECA)

Information and Proposals

5. The most recent monitoring data and update on progress with targets is summarised in Appendices 3 and 4, respectively.

Road Conditions in Gateshead 6 The latest road condition data is shown in Appendix 3 table1.The A, B and C roads in Gateshead are in very good condition; ranked in the highest road condition quartile of local highway authorities across the country. The Council can keep on top of repairs on these roads using capital planned maintenance budgets (see table 2).The condition of the much larger unclassified network (residential and industrial estates) is not as good although for the first time in a number of years the backlog of repairs has started to reduce with latest surveys showing 18% of this network now being of concern, this equates to some 123 km. (Appendix 3 table1).

7 As our neighbouring authorities have similar backlog issues on their unclassified roads the issue of historic underfunding in this area has been raised with NECA and is flagged up in the regional TAMP. We continue to target the unclassified network as shown in (Appendix 3 table 2) with almost 60 % of spend in that area but this is still less than 10 km of the 123 km backlog.

8 Extra Capital funding for 2025/26 from the (DfT) will provide a £1.8 million. uplift with some £380,000 being held back subject to the council demonstrating their compliance with good practice in highway asset management by virtue of a specified report. “The Transparency Report” was submitted in June 2025 and the funds are expected to be released in March 2026.

https://www.gateshead.gov.uk/article/33237/Local-Highway-Maintenance- Transparency-Report-2025-2026

The regional TAMP also provides certainty of funding and it is hoped this will draw the condition indicator down.

9 Appendix 3 table 3 provides up to date information on the Council’s reactive maintenance programmes. Gateshead’s highway and footpath network is inspected throughout the year based on the Council’s Highway Safety Inspection Policy available online:

https://www.gateshead.gov.uk/article/4502/Highways-Asset-Management-Plan

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highway Asset Management Plan Annual Information ReportReport 163 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 15 attended
MG
Councillor Martin GannonChair, present
GH
Councillor Gary HaleyVice-Chair, present
CD
Councillor Catherine DonovanCommittee Member, present
JA
Councillor John AdamsCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, apologies
AD
Councillor Angela DouglasCommittee Member, present
MH
Councillor Maria HallCommittee Member, present
LK
Councillor Leigh KirtonCommittee Member, present
JM
Councillor John McElroyCommittee Member, present
BO
Councillor Bernadette OliphantCommittee Member, present
MM
Melvyn Mallam-ChurchillSecretary, expected
DC
Darren CollinsOfficer, expected

All 15 on the meeting page

On this subject at Gateshead

Search all
  1. Highway Asset Management Plan Annual Information ReportThis decision
  2. Highway Asset Management Plan UpdateApproved
  3. Highway Asset Management Plan - Annual UpdateApproved
  4. Highway Asset Management Plan UpdateApproved
  5. Highway Asset Management Plan UpdateApproved
  6. Highway Asset Management Plan UpdateApproved

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies