Gateshead Metropolitan Borough Council
Cabinet, Tuesday 17 March 2026 at 10.00am

Repairs to Maidens Walk Coal Drops

Agreed Executive 2 papers

AI summaryCabinet accepts grant funding and delegates authority to appoint consultants for repairs to Maidens Walk Coal Drops, described as a first step to wider regeneration.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedDelegated decisions on grant and RIBA Stage 2-4 consultants
MoneyNot stated
What happens nextConstruction contract to return to CabinetSeparate report needed once RIBA Stage 4 tender obtained
Who it affectsResidents and visitors in south GatesheadArea between Town Centre, Baltic, Glasshouse and Newcastle

What was decided

Cabinet agreed to accept the grant and delegated authority to the Director of Finance to sign the grant funding agreement.

Cabinet delegated authority to the Strategic Director of Economy, Innovation and Growth to appoint the relevant Consultants for RIBA Stages 2 to 4.

Cabinet noted that a further report will be brought back for approval to enter into a construction contract likely to exceed the constitutional procurement threshold once a tender has been obtained at RIBA Stage 4.

Why

To enable delivery of the repairs scheme within scope, timescales and budget.

To ensure the Council has funding to deliver its priorities as set out in the Corporate Plan and the Capital Programme.

The repairs are described as a first step to future regeneration and improved connections between the Town Centre, Baltic Centre for Contemporary Art, the Glasshouse and Newcastle. Report P11

What happens next

The Director of Finance will sign the grant funding agreement.

The Strategic Director of Economy, Innovation and Growth will appoint consultants to take the project through RIBA Stages 2 to 4.

A separate Cabinet report will be brought at a later date to approve a construction contract, once a tender is obtained at RIBA Stage 4.

Implications

  • Other: A possible increase in the visitor economy and more employment for Gateshead residents has been identified. Report P7
  • Other: Proposed art installations could improve the appearance of the built environment. Report P8
  • Other: Reopened pedestrian and cycle access may improve access to services and enable more walking and cycling. Report P9
  • Equalities: Temporary events could support community networks and social organisations in the area. Report P9
  • Other: Monitoring and evaluation will be needed to understand the actual health implications of the repairs. Report P11

Who and where

  • Gateshead residents Report P7, P11
  • Visitors to the area Report P7, P11
  • Community organisations between the Town Centre, Baltic Centre for Contemporary Art, the Glasshouse and Newcastle Report P9, P11

Timeline

  • 24th Feb 2026: Cabinet proposal date recorded on the report Report P5

Plain English for the jargon

  • RIBA Stages 2 to 4: Stages of design and cost work run by the project consultants, ending with a tender for construction.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC157

Resolved

i) Cabinet agreed to accept the grant and delegated authority to the Director of Finance to sign the grant funding agreement. ii) Cabinet delegated authority to the Strategic Director of Economy, Innovation and Growth to appoint the relevant Consultants for RIBA Stages 2 to 4. iii) Cabinet noted that approval would be sought at a later date, through a separate Cabinet report, for the Council to enter into a construction contract likely to exceed the constitutional procurement threshold once a tender has been obtained at RIBA Stage 4. The above decision was made for the following reasons: a) To enable delivery of the repairs scheme within scope, timescales and budget. b) To ensure that the Council has funding to deliver its priorities as identified in the Corporate Plan and the Council’s Capital Programme.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Cabinet

Integrated Impact Assessment Support

Directions: Please review this document that provides suggestions for the potential health and wellbeing impacts of this report. Please get in touch with [email removed] if you would like any clarification, support or to provide feedback on suggestions provided. Once you have reviewed the following suggestions, please amend your Integrated Impact Assessment and Health Implications paragraph as you see fit.

For approval prior to Cabinet, please update your report and Integrated Impact Assessment, and send the report to [email protected] , Alice Wiseman ([email protected]) and Louise Sweeney ([email protected]) for approval.

Please note: This is a working document and information within is subject to change.

Report Title: Repairs to Maidens Walk Coal Drops Cabinet Proposal Date: 24th Feb 2026 HiAP Support Provided By: Jamie Alisigwe

Health Implications Identified:

Impact Positive Health Impacts Negative Health Impacts Suggested solutions to Mitigate Negative Level Impacts Income and 5 May increase visitor Debt economy, which may lead for more changes of gained employment of Gateshead residents.

Built 5 Beautify the area with environment proposed art installations. Integrated Impact Assessment Support

Quality and 5 The reopened pedestrian access to and cycle lanes may Services improve access to services in the area. Transport 5 Allows for active transport in the forms of cycling and walking. Crime levels and community safety Air quality, noise, energy use, waste minimisation Climate change Social 5 The opportunity for support, temporary events may community arise, allowing for networks and gathering of community community organisations and social organisations support. Physical health Mental health Behaviours affecting health Integrated Impact Assessment Support

Suggested Health Implications Paragraph:

The repairs to Maidens Walk Coal Drops are a first step to future regeneration and developed connections between Town Centre, Baltic Centre for Contemporary Art, the Glasshouse and Newcastle. This may improve the area for visitors and residents alike, allowing for an increase in the visitor economy. This could directly impact the residents of Gateshead by increasing good employment opportunities in the area. While these results are proposed, monitoring and evaluation is needed to understand the health implications of the repairs to the Maidens Walk Coal Drops.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Repairs to Maidens Walk Coal Drops BReport 49 KB DownloadRead as text
PDF
Repairs to Maidens Walk Coal DropsReport 112 KB Download

At this meeting

Whole meeting

Who was there

10 of 14 attended
MG
Councillor Martin GannonChair, present
GH
Councillor Gary HaleyVice-Chair, present
CD
Councillor Catherine DonovanCommittee Member, present
JA
Councillor John AdamsCommittee Member, present
CB
Councillor Chris BuckleyCommittee Member, present
AD
Councillor Angela DouglasCommittee Member, present
MH
Councillor Maria HallCommittee Member, present
LK
Councillor Leigh KirtonCommittee Member, present
JM
Councillor John McElroyCommittee Member, present
BO
Councillor Bernadette OliphantCommittee Member, present
MM
Melvyn Mallam-ChurchillSecretary, in attendance
DC
Darren CollinsOfficer, in attendance

All 14 on the meeting page

More from Gateshead Cabinet

All decisions
MeetingDecisionOutcome
22 Sep 2026 Approval of Refreshed Resident Influence Strategyi) To approve the Resident Influence Strategy (Appendix 2). ii) To authorise implementation of the strategy supported... Approved Open
22 Sep 2026 Business North East Business Support Frameworki) To agree that the Council be included as a named delivery partner in NEMSA’s Business North East business case and... Agreed Open
22 Sep 2026 NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ... Approved Open
22 Sep 2026 Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report... Approved Open
22 Sep 2026 Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies