Regulatory Judgement Improvement Plan

Decided Scrutiny 1 paper

AI summaryGateshead's housing scrutiny committee noted progress on the Improvement Plan addressing 13 weaknesses identified by the Regulator of Social Housing following its C2 rating in April 2025.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeDecidedOn the Regulatory Judgement Improvement Plan update
MoneyNot stated
What happens nextNot stated
Who it affectsCouncil tenants and stakeholdersProgress published on the council's website for transparency

What was decided

The Committee provided its views and comments on the content of the report.

Why

The Council received a C2 rating from the Regulator of Social Housing in April 2025, indicating no failings but 13 areas of weakness requiring improvement. Report P2, P3

An Improvement Plan was developed with the Regulator to track progress against the weaknesses, covering stock condition, repairs, damp and mould, tenant communication and complaint handling. Report P4, P5, P7

The Regulator reviewed progress on 10 February 2026 and requested updates including RAG ratings, revised target dates and publication dates for tenant reports. Report P9, P10

What happens next

Quarterly meetings with the Regulator will continue, with the next expected in mid to late May 2026. Report P16

Updated versions of the Improvement Plan will be reported quarterly through governance channels and published on the council's website. Report P17

The Regulator has asked to meet the Chief Executive and Housing Portfolio Holder once the post-election period has settled. Report P11

Options considered

  • Chosen: Provide feedback and comment on the current position in implementing the areas of weakness. Standing scrutiny role in monitoring the Improvement Plan through governance arrangements Report P19, P7

Implications

  • Risk: Thirteen areas of weakness identified by the Regulator require sustained progress; the Council remains under regulatory oversight with quarterly review meetings. Report P3, P6, P9
  • Other: Stock condition survey target updated to completion by end of June 2026, with current completion at 84% as at end of January. Report P10, P14
  • Legal: Stricter statutory timescales under Awaab's Law apply to damp and mould work, which continues to be completed within the 55-day target. Report P14
  • Staffing: Additional staffing and operational changes have contributed to a 22% reduction in voids in work across November and December. Report P14

Who and where

  • Council tenants Report P3, P7, P14
  • Council stakeholders Report P7
  • Housing service staff Report P14
  • Regulator of Social Housing Report P6, P9

Timeline

  • January 2025: Inspection by the Regulator of Social Housing Report P1
  • April 2025: Council received C2 rating from the Regulator Report P2
  • November 2025: Previous update to HEHC OSC Report P13
  • October: Stock condition survey completion at 78% Report P14
  • End of January: Stock condition survey completion at 84%; access rates at 70% Report P14
  • February 2026: Strategic Housing Board considered Awaab's Law implementation report Report P14
  • End of quarter 3: Stage 1 complaint performance at 85% within 10 working days Report P14
  • 10 February 2026: Most recent meeting with the Regulator Report P9
  • Mid to late May 2026: Next quarterly meeting with the Regulator Report P16
  • End of June 2026: Target completion date for stock condition survey Report P10
  • April: Mandatory profile-update pop-ups rollout planned Report P14

Plain English for the jargon

  • C2 rating: A regulatory judgement indicating no failings but some weaknesses where improvement is required.
  • RSH: Regulator of Social Housing, the regulator of registered providers of social housing in England.
  • Awaab's Law: Statutory requirements on landlords to address damp and mould and other hazards within set timescales.
  • Decent Homes Standard: Government standard setting minimum criteria for the condition of social housing.
  • TSM: Tenant Satisfaction Measures, mandatory performance measures for social housing landlords.
  • RAG rating: Red, Amber, Green status indicator used to show progress against targets.
  • HEHC OSC: Housing, Environment and Healthy Communities Overview and Scrutiny Committee.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemCPL81

Resolved

RESOLVED that: i. the Committee provided its views and comments on the content of the report.
Word for word from the decision Gateshead published for this meeting. Source: democracy.gateshead.gov.uk

Follow this further

Built from Gateshead's papers

What the report saysPro

Report to Housing, Environment and Healthy Communities Overview and Scrutiny Committee

Purpose of the report

1. To provide an update on progress addressing areas of weakness identified in the Regulatory Judgement following the inspection by the Regulator of Social Housing (RSH) in January 2025.

Background

2. The Council received a C2 rating from the RSH in April 2025, indicating no failings but some weaknesses where improvement is required. Thirteen areas of weakness were identified:

• Physical stock condition survey of all homes • All homes meeting the Decent Homes Standard • Performance reporting on damp and mould • Improved outcomes for tenants in respect of damp and mould • Backlog of repairs • Timeliness of repairs and maintenance of empty homes • Accessibility of tenancy management policies • Making information available to tenants in a timely manner • Communicating how tenants’ views have been considered • Making information more accessible for tenants • Improving the quality and extent of customer profile data • Improving complaint handling (timeliness and quality of responses) • Strengthening learning from complaints to improve services

Regulatory Judgement Improvement Plan

3. An Improvement Plan was developed with the Regulator and refined early on to clarify intended outcomes, strengthen targets and improve transparency around risks, customer impact and evidence. This now forms the framework for tracking progress.

4. The Council meets with the Regulator regularly and this has now been formalised into a quarterly programme of review meetings, where service leads provide detailed updates on progress against each of the areas of weakness.

5. The Plan is monitored through established governance arrangements, including Housing Leadership Team, Corporate Management Team, Housing Portfolio and Strategic Housing Board/HEHC OSC, alongside the quarterly meetings with the Regulator. The Improvement Plan is updated quarterly and published on the Council’s website to ensure transparency for tenants and stakeholders.

Update from Meeting with the Regulator – 10 February 2026

6. At the most recent meeting, the Regulator welcomed the continued progress and the evidence provided. Service leads presented updates against each area of weakness, which were scrutinised in detail. The Regulator requested that the next iteration of the Improvement Plan:

• Includes a RAG rating against each target to clearly show status • Reflects revised target completion dates where any have changed • Updates the stock condition survey target to reflect completion by end of June 2026 • Includes publication dates for the Annual Tenants’ Report, TSM results 2024/25, and the Annual Complaints Report

7. The Regulator also indicated they would like to meet with the Council’s Chief Executive and Housing Portfolio Holder at an appropriate point in the new reporting cycle, once the post-election period has settled.

8. These updates have been incorporated into the Improvement Plan which is attached as the Appendix to this report.

9. The following progress has been made since the last update to HEHC OSC in November 2025:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Regulatory Judgement Improvement PlanReport 108 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 17 attended
BC
Councillor Brenda ClellandChair, present
SD
Councillor Sonya DickieVice-Chair, present
DB
Councillor Dot BurnettCommittee Member, present
VA
Councillor Vicky AndersonCommittee Member, present
LB
Councillor Leanne BrandCommittee Member, present
LC
Councillor Lynne CaffreyCommittee Member, apologies
KD
Councillor Kevin DoddsCommittee Member, apologies
SG
Councillor Sheila GallagherCommittee Member, apologies
AG
Councillor Alex GeddesCommittee Member, present
FG
Councillor Freda GeddesCommittee Member, present
HK
Councillor Hugh KellyCommittee Member, present
PM
Councillor Peter MaughanCommittee Member, absent

All 17 on the meeting page

On this subject at Gateshead

Search all
  1. Regulatory Judgement Improvement PlanThis decision
  2. Regulatory Judgement Improvement PlanDecided

More from Gateshead Housing, Environment and Healthy Communities Overview and Scrutiny Committee

All decisions
MeetingDecisionOutcome
29 Jun 2026 Introduction to Housing, Environment and Healthy Communities OSCRESOLVED ... view the full minutes text for item CPL3 Decided Open
29 Jun 2026 Performance Management and Improvement FrameworkRESOLVED that: i. the contents of the annual report at appendix 1 be noted. ii. the additional information will be ma... Noted Open
29 Jun 2026 Work ProgrammeRESOLVED that: i) The proposed work programme items to date be noted; ii) Work be carried out between the Chair and o... Noted Open
19 Jan 2026 Building Safety and ComplianceRESOLVED that: i. the Committee provided its views and comments on the content of the report. Decided Open
19 Jan 2026 Work ProgrammeRESOLVED that i . the Committee noted the . Noted Open