AI summaryGateshead Cabinet agrees to accept £20 million Pride in Place Programme funding for 2026 to 2036, focused on Beacon Lough and Wrekenton, with £420,000 revenue and £117,000 capital for early years.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedStrategic Director to oversee delivery and contracts
Money£20 million programme, plus £420,000 revenue and £117,000 capitalOver 10 years 2026-2036, with early-year allocations
What happens nextNot stated
Who it affectsBeacon Lough and Wrekenton residentsHyper-local area of circa 10,000 population
What was decided
Cabinet agreed to accept £20 million of Pride in Place Programme funding for the period 2026 to 2036, and accepted £420,000 revenue funding for 2025/26 and 2026/27 plus £117,000 capital funding for 2026/27.
Cabinet delegated authority to the Strategic Director, Adult Social Care, Commissioning, Culture and Communities, in consultation with the Strategic Director, Resources and Digital, and the Chief Legal Officer, to oversee implementation, allocate funding, enter contracts and approve the Pride in Place Plan for submission to MHCLG.
Why
To enable access to funding from the Pride in Place Programme Fund for the benefit of residents and communities in Beacon Lough and Wrekenton. Report P4
Beacon Lough and Wrekenton were selected as a Pride in Place Programme Fund area through a metrics-based methodology using the Indices of Multiple Deprivation and the Community Needs Index, targeting neighbourhoods of circa 10,000 population that are doubly disadvantaged by high deprivation and weak social infrastructure. Report P2, P3, P4
The £5bn Pride in Place Programme was announced by Government on 25 September 2025, and Gateshead has also been selected for the separate Pride in Place Impact Fund, which allocates £1.5m over two years for immediate place improvements. Report P1, P6
What happens next
The Strategic Director will receive the funding, allocate it to third parties, enter into contracts as required, and approve and submit the Pride in Place Plan to MHCLG following approval by the Neighbourhood Board.
Impacts will be monitored through internal governance and the requirements of the funding, with regular reviews. Report P14
The money
£20 million Pride in Place Programme Fund over 10 years, 2026 to 2036 Report P2
£420,000 Revenue funding for 2025/26 and 2026/27
£117,000 Capital funding for 2026/27
£5bn Total Pride in Place Programme announced by Government on 25 September 2025 Report P1
£1.5m Pride in Place Impact Fund over two years for immediate work in Gateshead Report P6
Options considered
Chosen: Accept £20 million Pride in Place Programme funding 2026-2036 plus £420,000 revenue and £117,000 capital. To enable access to funding for Beacon Lough and Wrekenton residents and support local priorities in Gateshead
Implications
Equalities: Integrated Impact Assessment scores all protected characteristics, key inclusion groups, health and wellbeing, and socio-economic themes as 'long lasting or extensive positive impact'. Report P15, P16, P17, P19
Financial: Council will receive £20 million over a decade with £420,000 revenue in 2025/26 and 2026/27 and £117,000 capital in 2026/27, to be allocated to third parties and spent on contracts.
Other: Activity is grouped under Economy, Innovation and Growth and assessed as pre-project / initial idea stage, with the Pride in Place Plan still to be approved by the Neighbourhood Board before submission to MHCLG. Report P7, P10
Who and where
Residents of Beacon Lough and Wrekenton (circa 10,000 population), selected as the Pride in Place Programme Fund area Report P2, P4
All Gateshead residents, as the activity impacts all of Gateshead Report P8
Care experienced people, other vulnerable groups and people with complex needs Report P16
Groups covered by the socio-economic duty, including residents in financial difficulty, housing, digital inclusion, education, skills and employment Report P19
Timeline
25 September 2025: Government announced the £5bn Pride in Place Programme Report P1
2025/26 and 2026/27: Revenue funding of £420,000 to be spent
2026/27: Capital funding of £117,000 to be spent
2026 to 2036: Ten-year period for the £20 million Pride in Place Programme Fund Report P2
Plain English for the jargon
Pride in Place Programme Fund: Government fund providing up to £20 million over a decade to neighbourhoods of circa 10,000 people that face the highest deprivation and weakest social infrastructure.
Pride in Place Impact Fund: Separate government fund of £1.5m over two years for immediate work to improve places and spaces valued by local communities; Gateshead is a selected area.
MHCLG: Ministry of Housing, Communities and Local Government, the UK government department to which the Pride in Place Plan will be submitted.
Neighbourhood Board: Local body that must approve the Pride in Place Plan before it is submitted to MHCLG.
Indices of Multiple Deprivation and Community Needs Index: The data sources used to select Pride in Place Programme Fund areas.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC12
Resolved
i) Cabinet agreed to accept £20 million of Pride in Place Programme funding for the period 2026 to 2036. ii) Cabinet accept £420,000 revenue funding for 2025/26 and 2026/27 and £117,000 capital funding for 2026/27. iii) Cabinet agreed to delegate authority to the Strategic Director, Adult Social Care, Commissioning, Culture and Communities, in consultation with the Strategic Director, Resources and Digital, and the Chief Legal Officer, to oversee implementation of the , including: making all necessary arrangements to receive funding; allocating funding to third parties and entering into contracts as required to support programme delivery; and approving and submitting the Pride in Place Plan to MHCLG following approval by the Neighbourhood Board. The above decision was made for the following reasons: a) To enable access to funding from the Fund for the benefit of residents and communities in Beacon Lough and Wrekenton. b) To enable successful delivery of activity in Gateshead that will contribute to local priorities.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
Integrated Impact Assessment Details of the Activity Title of the activity: Pride in Place Funding Description of the activity: The £5bn Pride in Place Programme was announced by Government on 25 September 2025. There are two sets of funding that has been allocated by Government: Pride in Place Programme Fund and Pride in Place Impact Funding.
The Pride in Place Programme Fund is a hyper-local programme will deliver up to £20 million of funding over the next decade into areas that are ‘doubly disadvantaged’ by both the highest deprivation levels and weakest social infrastructure, focussed on neighbourhoods of circa 10,000 population.
The areas that have been selected have been determined through using a robust metrics-based methodology, using Indices of Multiple Deprivation and the Community Needs Index.
Beacon Lough and Wrekenton have been selected as a Pride in Place Programme Fund area.
The Pride in Place funding will put decision-making power in the hands of local people, offers the flexibility to respond to local needs and opportunities, and provides long-term funding so communities can put plans together to help rebuild and transform their neighbourhoods.
The Pride in Place Impact Fund will allocate £1.5m over two years to enable immediate work to improve places and spaces valued by local communities. Gateshead has been selected as one these areas.
Group: Economy, Innovation and Growth
Does the activity impact all of Gateshead or a specific ward? All of Gateshead
Which specific ward(s) in Gateshead does the activity impact? (if applicable) Not applicable
What stage is the activity/project at? Pre-project / initial idea
Data and Intelligence What data and intelligence has been used and how has this informed the activity? Index of Multiple Deprivation, Community Needs Index, Retail Health Checks, LIoN.
Also using the evidence from the development of the Young People Strategy, Health and Wellbeing Strategy, Local Economic Assessment, Regeneration Plan.
Summary of consultation/data/research undertaken to inform the assessment: Internal consultation with Council officers before consulting with external partners including communities.
How will you monitor the impacts and mitigating actions on an ongoing basis? Will regularly review through the requirements of the funding. This will be reviewed through internal governance that has been established to monitor the funding.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.