AI summaryGateshead Cabinet notes first quarter revenue position showing the budget is on target after management interventions, with a £3.111m Dedicated Schools Grant overspend flagged.
Written from the decision and the officer reportPDF Pro
OutcomeNotedOn target after management interventions
Money£346.005m net revenue budgetGross budget £588.306m for 2026/27
What happens nextQuarterly monitoring continuesProgress to be reported quarterly
Who it affectsAll Gateshead residentsRevenue spending supports whole-borough services
What was decided
Cabinet noted the council's revenue expenditure position at the end of the first quarter, as set out in Appendices 1 to 3. Report P13
The reason given was to contribute to sound financial management and the long-term financial sustainability of the council. Report P15
Why
The 2026/27 revenue budget was set at £346.005m on 26 February 2026, with £4.000m drawn from the Budget Sustainability Reserve to allow time for planned cuts and efficiencies. Report P3
Despite an overall balanced position, underlying pressures remain in social care and construction services, with Adult Social Care facing demand-led cost pressures and Construction Services facing reduced income and overhead recovery. Report P26, P27, P28, P29
What happens next
Virements have been actioned during the first quarter to reflect council operations and delegated use of contingency. Report P10, P23
It is the intention to deliver within the overall budget by the financial year end, with Finance and Governance Portfolio providing additional oversight. Report P8, P30
The money
£346.005m Net revenue budget for 2026/27 set on 26 February 2026 Report P3, P58
£588.306m Gross revenue budget for 2026/27 Report P3
£4.000m Council financing from the Budget Sustainability Reserve Report P3
£99.521m HRA income budget for 2026/27, including use of reserves Report P4
£1.058m Planned use of HRA reserves in 2026/27 Report P4
£3.111m Projected Dedicated Schools Grant overspend at first quarter Report P32
£147.289m Dedicated Schools Grant budget for 2026/27 Report P32
£6.903m Projected deficit on the DSG reserve Report P32
£6.446m Opening HRA reserve balance Report P38
£5.388m Forecast HRA reserve balance at year-end Report P38
Options considered
Chosen: Note the first quarter revenue position as set out in Appendices 1 to 3. To contribute to sound financial management and the long-term financial sustainability of the Council Report P13, P15
Rejected: No alternative options were proposed Report P40
Implications
Financial: Strategic Director, Resources and Digital confirms financial implications are as set out in the report and appendices. Report P42
Risk: Regular budget monitoring and action planning reduce the risk of overspending the agreed budget and support effective resource deployment. Report P43
Legal: Chief Legal Officer confirms there are no legal implications arising from this report. Report P44
Equalities: No equality and diversity implications arise from this report. Report P46
Staffing: No direct Human Resources implications arise from this report. Report P45
Other: The work supports the council in using resources in line with strategic objectives for residents to live healthy lives, with continued focus on prevention and reducing inequalities. Report P48
Who and where
All Gateshead residents, as revenue spending supports services across the whole borough Report P51
Adult Social Care service users, affected by demand-led cost pressures including transitions from Children's Services Report P27
Children in care, affected by a planned shift in placement mix to reduce reliance on higher-cost provision Report P28
High Needs Block recipients in Education, Schools and Inclusion, where mitigating actions are being developed Report P33
Council Finance and Resources Portfolio, consulted on the report and providing oversight Report P30, P39
Timeline
26 February 2026: Council agreed the 2026/27 revenue budget at £346.005m and the HRA budget at £99.521m Report P3, P4, P53
End of first quarter 2026/27: Revenue outturn forecast to be on target after management interventions Report P6
31 March 2028: Statutory override on the DSG deficit is due to end, after which the deficit would otherwise be charged to the General Fund Report P34
Financial year end 2026/27: HRA reserve balance forecast to reduce to £5.388m from an opening £6.446m Report P38
Plain English for the jargon
Revenue budget: The council's day-to-day spending budget, covering running costs of services
HRA: Housing Revenue Account, the ring-fenced account for income and spending on council housing
DSG: Dedicated Schools Grant, government funding for schools and related education services
High Needs Block: The part of the DSG that funds support for children and young people with special educational needs and disabilities
Virement: A transfer of budget between budget headings, carried out under delegated authority
Statutory override: A temporary government rule that keeps the DSG deficit separate from the council's general accounts
Contingency: Budget set aside centrally to manage unforeseen costs
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemC17
Resolved
i) To note the Council’s revenue expenditure position at the end of the first quarter, as set out in Appendices 1 to 3. The above decision was made for the following reason: a) To contribute to sound financial management and the long-term financial sustainability of the Council.
Word for word from the decision Gateshead published for this meeting.Source: democracy.gateshead.gov.uk
1. This report sets out the latest monitoring position on the 2026/27 revenue budget at the end of the first quarter. Cabinet is asked to note the Council’s revenue expenditure position at the end of the first quarter.
Background
2. As part of the Council’s budget and policy framework Cabinet receives quarterly reports on the agreed revenue budget so that any variances can be identified and addressed at an appropriate pace with Councillor oversight.
3. Council agreed the revenue budget for 2026/27 on 26 February 2026. This was set at £346.005m. The gross revenue budget for 2026/27 is £588.306m. The budget included £4.000m of Council financing from the Budget Sustainability Reserve to allow time for a planned schedule of cuts and efficiencies.
4. Council also agreed the HRA budget for 2026/27 on 26 February. This was set as a HRA income budget of £99.521m including the use of £1.058m HRA reserves.
Proposal
5. The projected revenue outturn for 2026/27 at the first quarter is forecast to be on target after management interventions. Service performance against budgets are shown in Appendix 2.
6. Achievement of the projected outturn at quarter one is reliant upon the successful delivery of management interventions.
7. It is the intention to outturn within the original budget by the financial year end and progress against this target will be reported quarterly.
Virements
8. Virements have been actioned during the first quarter to reflect the operations of the Council and delegated use of contingency.
1 of 7 Housing Revenue Account 9. At the first quarter review, the HRA budget is forecast to be on target after management interventions. HRA performance against budgets are shown in Appendix 3.
Recommendations
10. It is recommended that Cabinet
(i) Notes the Council’s revenue expenditure position at the end of the first quarter, as set out in Appendix 1 to 3.
for the following reason(s)
(i) To contribute to sound financial management and the long-term financial sustainability of the Council.
CONTACT: Darren Collins Extension: 3582
2 of 7 APPENDIX 1
Policy Context
1. This report meets the standards required to comply with the Accounts and Audit Regulations 2015 which represent financial management good practice, and recommend that councillors should receive regular reports on performance against revenue and capital budgets.
2. It is also consistent with the Council’s objectives of making Gateshead a place where everyone thrives by assisting in ensuring a sustainable financial position for the long term.
3. Appendix 2 details the projected outturn per service against budget for 2026/27. This position is after the application of reserves and management interventions.
Virements
4. Virements have been actioned during the first quarter to reflect the operations of the Council and delegated use of contingency.
Key Budget Challenges
5. Despite the overall balanced position, underlying budget pressures remain within a number of service areas. These pressures are being actively managed through service-led interventions and are reflected within the forecast outturn position.
6. The most significant areas of pressure continue to be within social care and construction services.
7. Within Adult Social Care, demand-led pressures associated with care packages, including transitions from Children’s Services continue to impact the cost base.
8. Children’s Social Care activity continues to be managed through a planned shift in placement mix, with a focus on achieving the best outcomes for children in care while reducing reliance on higher-cost provision.
9. Construction Services continues to face challenges associated with reduced levels of income and overhead recovery within the traded service.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
NEMSA Adult Skills Fund Acceptancei) To approve acceptance of grant funding from the North East Mayoral Strategic Authority for delivery of the Skills ...
Local Council Tax Support Scheme 2027/28i) To approve the consultation exercise set out in paragraphs 10 to 13 of the report. ii) To receive a further report...
Procurement and Contracts Reporti) To authorise the Strategic Director, Resources and Digital, to: a) Invite or negotiate tenders. b) Undertake other...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.