That the Service Manager, Development Services in conjunction with the Director of Organisational Development & Democratic Services be authorised to take all enforcement action required including the service of a Stop Notice and any other enforcement notices and proceedings through the courts, including an application for an injunction if necessary to ensure the unauthorised development and engineering works cease and the unauthorised works are removed and the land is returned to its former condition.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
1.1This matter relates to unauthorised development, engineering works and tipping on a site of approximately 9.6 hectares of woodland to the south of Longdale Lane, Ravenshead and to the east of Ravenshead Village and approximately 150 metres to the west of Rigg Lane crossroads with Longdale Lane.
1.2The Land lies within an area of countryside and also within the Nottinghamshire Green Belt. In addition it is part of a designated Site of Nature Conservation Interest. The area is extremely rural although at intervals there are some large detached dwellings in generous well screened secluded gardens along the south side of Longdale Lane.
1.3In February 2008 conditional planning permission was granted to the land for the re-establishment of an existing vehicular access into the woodland used for general management works and husbandry (Planning reference 2007/0988).
1.4On 15th June 2010, a Prior Notification application for forestry development was received by the Council from the land owner (Reference 2010/0527). The application was made seeking confirmation that the erection of three forestry buildings would constitute permitted development under the provisions of the Town and Country Planning General Permitted Development Order 1995 (GPDO); Schedule 2, parts 6 & 7; which relates to agriculture and forestry permitted development.
1.5On 7th July 2010, consent was given by the Council under the GPDO for the forestry buildings and the first building was erected in the summer of 2013 but no start was made on the other buildings.
1.6On the 28th February 2017, a pre application enquiry was received for the land from a planning consultant acting on behalf of the owner. (Reference 2017/0462PRE). The enquiry proposed 3 agricultural buildings and a secondary vehicular access into the site.
1.7A response was sent to the applicant on the 20th April 2017 advising the General Permitted Development Order (GPDO) approval given under reference 2010/0527 had lapsed due to the conditions attached to the GPDO which required the development to be “carried out” within a period of 5 years from the date approval was given.
1.8In May 2017 it came to the Council’s attention that despite this advice works had commenced on site to construct the second building. Officers attended at the site and it was noted a water supply had been brought to the development site, cavity wall foundations had been laid and excavation works had been carried out in preparation for a new access from the new building to Longdale Lane. In addition a large amount of hard-core had been tipped on the land to make a hard standing in front of the new building.
1.9On the 26th June 2017, a planning application was received for a change of use of the previously erected existing forestry building to allow it to be converted for 2 holiday lets.
1.10A further visit was carried out to the site by officers on Wednesday 2nd August 2017 when they met the owner and planning consultant who advised officers the existing barn was redundant and they believed they could still build the other two barns under the GPDO consent received in 2010. The planning consultant and the applicant have been advised in writing this is not the case and all work should cease as it is not permitted development and requires planning permission.
2 ASSESSMENT
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.