Resolved
To approve a capital budget of £102,000 for the development of a new Conway Road Play Area which is partially funded by external grant funding from FCC Communities Foundation Ltd.
Cabinet approved this item on Thursday 5 September 2019. Below is the council's own wording, with the papers it was decided on.
Resolved
To approve a capital budget of £102,000 for the development of a new Conway Road Play Area which is partially funded by external grant funding from FCC Communities Foundation Ltd.
Gedling Ward, Netherfield Ward, Trent Valley Ward
Purpose
To obtain Cabinet approval to establish a capital budget for the redevelopment of Conway Road Recreation Ground Play Area from funding provided by FCC Communities Foundation Ltd (formerly known as WREN – Waste Recycling Environmental Ltd)
Key Decision
This is not a key decision
Recommendation(s)
THAT:
Cabinet approve a capital budget of £102,000 for the development of a new Conway Road Play Area which is partially funded by external grant funding from FCC Communities Foundation Ltd.
1.1Netherfield Steering Group, in partnership with Gedling Borough Council Parks and Street Care submitted a funding bid for £94,500 to FCC Communities Foundation Ltd to fund the development of a new play area at Conway Road Recreation Ground, a park which is Gedling Borough Council owned. The Netherfield Steering Group oversees the development and implementation of Netherfield Locality Plan which was approved by Cabinet in 2013. The Steering Group held a series of consultation events within the Netherfield Ward namely Netherfield Primary School, St. Georges Centre and Conway Park Pavilion. The consultation events generated a lot of discussions around how the park should be improved. Discussions were also held with the two bowling clubs based at Conway Park who were keen to see the park improved and engaged with the process. The improvement works form part of a Development Plan setting out the strategic objective to improve the park with outline designs that were approved at the various consultation events held. [Appendix 1]. Also available is a “virtual reality fly through” developed to be used as part of any funding bids and to show residents what the park could like after the improvements had been implemented. The play area development is phase one of the project to improve the park. Funding is still being sought to improve the rest of the park. As part of the funding bid for phase one, FCC Communities Foundation Ltd require a contribution from a third party funding provider, this amount is 10.75% of the amount of total funding applied for. This amount is used to unlock the landfill tax from the central regulators. For this project the funding amount applied for is £94,500, therefore the amount of the 3rd party contributory payment is £10,200 which Gedling Borough Council have agreed to fund and will pay directly to FCC. Further costs of £7,500 to the Council will be the cost of the Contract Administration works being undertaken by the Environmental Management and Design Team at Via East Midlands who formed part of the original team that developed the Improvement Plan/Strategy for the Park as well as the outline designs. Via also helped with the bid submission by providing up to date figures for the bid based on recent tenders for similar projects within Nottinghamshire. Via has performed similar roles within the Borough.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Conway Park Development PlanAppendix 1 | 1.9 MB | Download |
PDF |
Post-Board Letter (Approved)CF-1488Appendix 2 | 225 KB | Download |
PDF |
Establish a budget for Conway Road Recreation Ground Play Area RedevelopmentReport | 102 KB | DownloadRead as text |
Follow Cabinet at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 16 Jul 2026 | Forward Plan1) To note the report. | Noted | Open |
| 16 Jul 2026 | Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... | Noted | Open |
| 16 Jul 2026 | Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... | Agreed | Open |
| 16 Jul 2026 | Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.