Resolved
1) To approve a revenue budget of £658,548 during 2025/26. 2) To approve a capital budget of £513,506 to enable expenditure of the £1.172m allocation during 2025/26.
Cabinet approved this item on Wednesday 19 March 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
1) To approve a revenue budget of £658,548 during 2025/26. 2) To approve a capital budget of £513,506 to enable expenditure of the £1.172m allocation during 2025/26.
All wards
Purpose
To obtain Cabinet approval to establish a revenue and capital budget for the new allocation of £1.172m from the EMCCA Mayor of the UK Shared Prosperity Fund.
Key Decision
This is a key decision.
Recommendation(s)
THAT:
1) Cabinet approve a revenue budget of £658,548 and a capital budget of £513,506 to enable expenditure of the £1.172m allocation during 2025/26.
1.1In April 2022 the former government launched a three year funding programme of £2.6b, the UK Shared Prosperity Fund (‘’the Fund’’) to support local investment. This funding was allocated via a funding formula rather than competitive bid with a “blended approach” being adopted to the allocation of funds which ensured that all places received significant continuity with EU structural funds. 70% was allocated on a per capita basis within each region based on Local Authority population size with 30% of the allocation uses the needs based index previously used to identify UK Community Renewal Fund Priority places including:
Productivity Household income Skills
1.2Gedling was awarded an allocation of £2,866,555, split between capital and revenue funding as part of the 2022-2025 UK Shared Prosperity Fund. Over the last three years, the funds have been invested into projects that have supported growth for the borough’s communities, businesses and residents, creating a meaningful impact and legacy. A brochure of key projects is provided at Appendix A.
1.3Further extension into a year four has been provided to the EMCCA Mayor. The £1.172m funding to Gedling was confirmed following ratification via the February EMCCA board.
1.4Each lead local authority is expected to continue its collaboration with a Local Partnership Group and to ensure that the panel routinely updated on progress throughout the duration of the programme.
1.5The Ministry of Housing, Communities and Local Government (MHCLG) will continue to oversee the Fund at UK level for the transition year, working in close partnership with the devolved governments and other UK government departments. The aim of the UKSPF extension year is to provide a smooth transition from the existing UKSPF programme to a new, future funding framework.
1.6Updated UKSPF guidance via Gov.Uk states that ‘In line with the delegated delivery model, we will not require lead local authorities to submit a revised investment plan - we simply ask that lead local authorities update us on their plans for 2025-26 through routine reporting’. Further information on the requirements are still outstanding, although anticipated imminently.
1.7In order to deliver on projects allocated within the SPF framework criteria, a budget must first be established in the revenue and capital programmes.
2 Proposal
2.1Approval is sought to establish a revenue budget of £658,548 and a capital budget of £513,506 to facilitate expenditure under year 4 of the UKSPF programme. 3 Alternative Options
3.1Not to set up revenue and capital budgets and return the money to the EMCCA Mayor. However, this option would adversely impact upon the delivery of grant funding to support businesses, skills and training, and the delivery of capital projects within the borough.
4.1As detailed above, the Council has been allocated £1,172,054 of UKSPF funding during 2025/26.
4.2The award of the grant will be subject to approval of 25/26 activity forecast, and the Council’s acceptance of the revised Memorandum of Understanding setting out Fund requirements and obligations.
4.3The establishment of an appropriate revenue and capital budget is required in accordance with the Council’s Financial Regulations, any specific project that requires an element of match funding which is not already identified will need to be approved according to Financial Regulations and may come forward as separate approvals as necessary.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Brocure of key projectsAppendix A | 27 MB | Download |
PDF |
EIAAppendix B | 164 KB | Download |
PDF |
CIAAppendix C | 312 KB | Download |
PDF |
Establish a budget for Year 4 of the UK Shared Prosperity FundReport | 169 KB | DownloadRead as text |
PDF |
Notice to the Chair of the Overview and Scrutiny Committee: UKSPFReport | 201 KB | Download |
Follow Cabinet at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 16 Jul 2026 | Forward Plan1) To note the report. | Noted | Open |
| 16 Jul 2026 | Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... | Noted | Open |
| 16 Jul 2026 | Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... | Agreed | Open |
| 16 Jul 2026 | Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.