Audit Completion Report Gedling Borough Council Year ended 31 March 2020 CONTENTS
1. Executive summary 2. Significant findings 3. Internal control recommendations 4. Summary of misstatements 5. Value for Money conclusion
Appendix A – Draft management representation letter Appendix B – Draft auditor’s report Appendix C – Independence
Our reports are prepared in the context of the ‘Statement of Responsibilities of auditors and audited bodies’ and the ‘Appointing Person Terms of Appointment’ issued by Public Sector Audit Appointments Limited. Reports and letters prepared by appointed auditors and addressed to the Council are prepared for the sole use of the Council and we take no responsibility to any member or officer in their individual capacity or to any third party. Mazars LLP is the UK firm of Mazars, an international advisory and accountancy group. Mazars LLP is registered by the Institute of Chartered Accountants in England and Wales.
1 Mazars LLP Park View House 58 The Ropewalk Nottingham NG1 5DW
Audit Committee Members Gedling Borough Council Civic Centre Arnot Hill Park Arnold Nottingham NG5 6LU 24 November 2020
Dear Members
Audit Completion Report – Year ended 31 March 2020
We are pleased to present our Audit Completion Report for the year ended 31 March 2020. The purpose of this document is to summarise our audit conclusions.
The scope of our work, including identified significant audit risks and other areas of management judgement, was outlined in our Audit Strategy Memorandum dated 6 February 2020. Since we issued our Audit Strategy Memorandum the UK has been subject to the challenges and restrictions of COVID-19. We have reviewed our Audit Strategy Memorandum and concluded that the original significant audit risks and other areas of management judgement remain appropriate.
One implication of COVID-19 for the Council was that the deadlines for submission of the draft and audited financial statements were pushed back to 31 August and 30 November respectively. Despite the revised deadlines we acknowledge the difficulties encountered by your team during accounts preparation and audit, and would like to express our thanks for the assistance of your team during our audit.
If you would like to discuss any matters in more detail then please do not hesitate to contact me on 0115 964 4744 .
Yours faithfully
David Hoose Mazars LLP
Mazars LLP – Park View House – 58 The Ropewalk, Nottingham, NG1 5DW Tel: +44 (0) 115 964 4744 – Fax: +44 (0) 115 964 4744 – www.mazars.co.uk Mazars LLP is the UK firm of Mazars, an integrated international advisory and accountancy organisation. Mazars LLP is a limited liability partnership registered in England and Wales with registered number OC308299 and with its registered office at Tower Bridge House, St Katharine’s Way, London E1W 1DD.
We are registered to carry on audit work in the UK by the Institute of Chartered Accountants in England and Wales. Details about our audit registration can be viewed at www.auditregister.org.uk under reference number C001139861. VAT number: 839 8356 73 1. EXECUTIVE SUMMARY
Purpose of this report and principal conclusions The Audit Completion Report sets out the findings from our audit of Gedling Borough Council (‘the Council’) for the year ended 31 March 2020, and forms the basis for discussion at the Audit Committee meeting on 24 November 2020.
The detailed scope of our work as your appointed auditor for 2019/20 is set out in the National Audit Office’s (NAO) Code of Audit Practice. Our responsibilities and powers are derived from the Local Audit and Accountability Act 2014 and, as outlined in our Audit Strategy Memorandum, our audit has been conducted in accordance with International Standards of Auditing (UK) and means we focus on audit risks that we have assessed as resulting in a higher risk of material misstatement.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Gedling Audit Completion Report: 17.11.2020 v2 LATESTReport | 807 KB | DownloadRead as text |
PDF |
Mazars External Audit Report 2019/20Report | 153 KB | Download |
Follow Audit Committee at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 20 Oct 2026 | BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... | Noted | Open |
| 20 Oct 2026 | Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... | Noted | Open |
| 20 Oct 2026 | Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... | Noted | Open |
| 20 Oct 2026 | Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.