RESOLVED to: 1) Approve the General Fund Budget virements set out in Appendix 1 to the report; 2) Approve the amendments to the Capital programme set out in Appendix 3 to the report; 3) Note the use of reserves and funds and virements approved during quarter two as detailed in Appendix 2 to the report; 4) Agree the withdrawal of the Commercial Property Investment Strategy as detailed in paragraph 2.7 to the report and recommend it to Council for approval.
Word for word from the decision Gedling published for this meeting.Source: democracy.gedling.gov.uk
To update Cabinet on the forecast outturn for Revenue and Capital Budgets for 2020/21. The budgets include all approved carried forward amounts from the 2019/20 financial year. To request approval from Cabinet for the changes to the budget as set out in this report. To request approval for the withdrawal of the Commercial Property Investment Strategy.
Key Decision
This is a key decision.
Recommendation(s)
Members are recommended to:
1) approve the General Fund Budget virements set out in Appendix 1;
2) approve the amendments to the Capital programme set out in Appendix 3;
3) note the use of reserves and funds and virements approved during quarter three as detailed in Appendix 2;
4) agree the withdrawal of the Commercial Property Investment Strategy as detailed in paragraph 2.7 and recommend it to Council for approval. 1. Background
1.1The Council has made a commitment to closely align budget and performance management. This is in line with accepted good practice.
1.2To deliver this commitment, systems to monitor performance against revenue and capital budgets, improvement activity and performance indicators have all been brought together and are now embedded in the way the Council works. Whilst the budget and performance information is presented in 2 separate reports, they are reported to Cabinet together and will appear on the same agenda.
2. Proposal
2.1General Fund Revenue Budget Summary
The following table summarises the overall financial position of the General Fund Revenue Budget and the expected total spend for the year. This information has been compiled using the best information made available to Financial Services by the relevant spending officers as at 31 December 2020.
In summary the Council’s General Fund outturn is projected to be in line the approved budget of £11,602,700, including an overall contribution from earmarked reserves of £2,278,300. Members will recall approving at Quarter 1, the use of £420,600 of earmarked reserves to ensure the budget was maintained at its maximum due to the forecast budgetary impact of Covid-19. The position at quarter 2 included an approved transfer back to earmarked reserves of £100,000 enabled by the receipt of a fourth tranche of emergency Covid-19 grant funding announced by the Government. The latest position for quarter 3 includes further net budget pressures due to the continued Covid-19 related restrictions of £142,400. However, this has been contained within savings identified across portfolios.
General Fund Revenue Budget 2020/21 – Change Analysis
£
Net Council Budget for 2020-21 approved by Council 11,602,700 on 5 March 2020 and Cabinet’s Maximum Budget is:
Up to the end of December 2020 expenditure less income 6,746,856 totalled In the remaining 3 months of year we expect net 4,855,844 expenditure to be
Total net revenue spend for the year is expected to be 11,602,700
Total Projected Revenue (Under) / Overspend 2020/21 0
Appendix 1 outlines how the General Fund Revenue budget is divided between the Portfolios of the Council and includes a detailed variance analysis identifying the current proposed changes for quarter one against the approved budget for each Portfolio area. Cabinet is recommended to approve these changes.
The major variances detailed in Appendix 1 include:
Expenditure Variances:
Additional Covid-19 related pressures of £14,500 as set out in paragraph 2.2; Deferrals of the 2020/21 efficiency programme of £44,600 not related to the Covid-19 pandemic, as listed in the efficiency table in section 2.3; Vacancy savings of (£63,000) across Environment and Resources and Reputation.
Income Variances:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.