Resolved
To adopt the Risk Management Framework at Appendix 1 to the report including the risk appetite statement which sets the Council’s overall risk appetite as moderate.
Cabinet approved this item on Thursday 28 March 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
To adopt the Risk Management Framework at Appendix 1 to the report including the risk appetite statement which sets the Council’s overall risk appetite as moderate.
All wards
Purpose
To seek adoption of a new Risk Management Framework which includes a policy, strategy, risk appetite statement and risk management toolkit.
Key Decision
This is not a key decision.
That Members:
1) Adopt the Risk Management Framework at Appendix 1 to this report including the risk appetite statement which sets the Council’s overall risk appetite as moderate.
1.1The Council’s current Risk Management Strategy was approved by Cabinet in October 2017 and provides guidance on the processes, procedures, roles and responsibilities for risk and sets out the context on how risks are managed within the Council.
1.2The Accounts and Audit Regulations 2015 require the Council to ensure that it has a sound system of internal controls which includes the effective management of risk. It is key that as the Council takes on more ambitious projects and transforms the way it works both in terms of digital improvements and service provision, that its risk management processes remain robust.
1.3Internal auditors have recommended that the Council review and update its current Risk management Strategy and Framework document with a deadline for completion of 31 March 2024. The current Strategy and Framework has been reviewed and a new Risk management Framework is attached at Appendix 1. This Framework is based on an approach which our internal auditors considered to be good practice and was considered by Audit Committee on 19th March 2024 and recommended for approval by Cabinet.
1.4The new Framework includes:
Risk management Policy Statement – which sets out the organisational approach to risk management and how it will be embedded into the Council’s governance framework and delivery of the Gedling Plan.
Risk Management Strategy – which sets out what risk management is, why it is important and the legal requirements, the roles and responsibilities of risk management within the Council from members to officers, how risk management will be embedded into the Council’s culture, and how risks are assessed and scored.
Risk Appetite Statement – which defines the overall level of risk as a Council we are prepared to accept.
Risk management Toolkit – which provides practical guidance on how risks are identified, scored and managed as well as guidance on appropriate controls to manage risk and how risks will be reported and communicated.
1.5As part of the Strategy element of the framework, the Council have used the ALARM National Performance Model for Risk Management in Public Services, which provides a self-assessment tool for authorities to grade themselves in terms of how well risk management is embedded within the organisation. The “rating” goes from 1 – 5 across 7 categories. Senior Leadership Team have assessed the Council’s current risk management position at level 3 “Working” – as there are adequate risk processes in place, however under the new Framework it is hoped that the Council will move into the level 4 category “Driving” within the Gedling Plan period to 2027.
1.6The Risk Appetite statement, is a declaration of the Council’s risk appetite and must be agreed, along with the Framework by Cabinet. Based on the new risk scoring matrix, it is proposed that the Council’s risk appetite level be set at Moderate – Tending always towards exposure to only modest level of risks in order to achieve acceptable outcomes. It is against this risk appetite level that risks will be assessed and scored. Whilst this is the Council’s overall risk appetite, every risk will be assessed and in some instances, a higher level of risk may be acceptable depending on the outcomes delivered. In practical terms this will be visible to Audit Committee through quarterly reporting of risks to the Committee, it will also be considered by the Executive through decision reports and Portfolio Holder meetings.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Risk Management Framework March 2024Appendix 1 | 731 KB | Download |
PDF |
Risk management strategy and frameworkReport | 166 KB | DownloadRead as text |
Follow Cabinet at Gedling and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | To approve, as a correct record, the minutes of the meeting held on 25.06.26.That the minutes of the above meeting, having been circulated, be approved as a correct record. | Approved | Open |
| 16 Jul 2026 | Forward Plan1) To note the report. | Noted | Open |
| 16 Jul 2026 | Housing Strategy 2026-2030That Cabinet: 1) Noted the representations and comments received during the public consultation, together with the of... | Noted | Open |
| 16 Jul 2026 | Gedling BC Asset Management Plan 2026-2028THAT Cabinet: 1) Agreed to adopt the Asset Management Strategy 2026-2028 at appendix 1. 2) Approved the proposals for... | Agreed | Open |
| 16 Jul 2026 | Gedling Economic Growth FrameworkThat Cabinet: 1) Approved the (2026–2030). 2) Noted the findings within the appendices which have been considered as ... | Approved | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.