Gedling Borough Council
Audit Committee, Tuesday 23 June 2026 at 5.30pm

Corporate Risk Management Strategic Framework

Approved Finance 3 papers

AI summaryAudit Committee has recommended Cabinet adopt the amended Risk Management Framework, which sets out how Gedling Borough Council identifies, scores, and manages risks, including a 4x4 risk matrix and a moderate overall risk appetite.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRecommend Cabinet adopts the amended framework
MoneyNot stated
What happens nextCabinet to decideCabinet will consider whether to adopt
Who it affectsCouncil staff and membersAll employees, Cabinet, SLT and partners

What was decided

The Audit Committee resolved to recommend that Cabinet adopt the amended Risk Management Framework at Appendix 1 of the report.

The framework was reviewed in June 2026, having originally been adopted in March 2024 and previously reviewed in December 2025. Report P1

The Audit Committee's defined role includes gaining assurance over the governance of risk, supporting the framework's development and review, and reviewing key risks through the Corporate Risk Register. Report P22

Why

The Council is required by the Accounts and Audit Regulations 2015 to have effective arrangements for the management of risk. Report P16

An internal audit of risk management led to a reassessment under the ALARM model, showing improved maturity scores in several categories since 2025. Report P29

The framework aims to embed risk management into the Council's culture and decision-making, supporting delivery of the Gedling Legacy Plan and progress through Local Government reorganisation. Report P8

What happens next

Cabinet will consider the recommendation to adopt the amended framework.

The Council is targeting a Level 5 (Driving) rating under the ALARM National Performance Model by the end of 2027. Report P29

A training and communication plan will be developed so the framework is embedded across the Council and understood by partners and contractors. Report P27, P8

Options considered

  • Chosen: Adopt the amended Risk Management Framework. Recommended to Cabinet following an internal audit and reassessment of ALARM maturity scores. Report P29
  • Chosen: Set the overall base risk appetite as Moderate. Cabinet agreed the Council stays open to innovative ways of working but prefers safe delivery, especially for statutory services. Report P36

Implications

  • Legal: The framework is needed to meet the Accounts and Audit Regulations 2015 requirement for effective arrangements to manage risk. Report P16
  • Governance: The framework is part of the Council's Governance Framework and is overseen by the Audit Committee, Cabinet and SLT, with the Chief Executive as sponsor. Report P8, P19, P22
  • Risk: Risks scoring above 12 (red) on the 4x4 matrix are escalated to the Corporate Risk Register; options above Moderate appetite need Statutory Officer sign-off and extra monitoring. Report P36, P75, P79
  • Staffing: All employees and members have a role in risk management, with risk owners (Assistant Directors and Senior Managers) reviewing risks at least four-monthly. Report P8, P24
  • Other: The framework uses the Institute of Internal Auditors' 3 Lines Model and the Government's Orange Book guidance for defining risks. Report P19, P61

Who and where

  • All employees and members of Gedling Borough Council Report P8, P22
  • Cabinet and Senior Leadership Team (SLT) Report P19, P22
  • Audit Committee Report P22
  • Assistant Directors and Senior Managers as risk owners Report P24
  • Internal Audit Report P25
  • Partners and contractors working with the Council Report P8, P27

Timeline

  • March 2024: Risk Management Framework originally adopted Report P1
  • April 2025: Target for Level 4 (Embedded and Working) ALARM rating in each category Report P29
  • December 2025: Framework reviewed Report P1
  • June 2026: Framework reviewed and amended version prepared Report P1
  • 2026-06-23: Audit Committee recommends adoption by Cabinet
  • End of 2027: Target for Level 5 (Driving) ALARM rating Report P29

Plain English for the jargon

  • ALARM: National Performance Model for Risk Management in Public Services, scoring maturity from 1 to 5.
  • SLT: Senior Leadership Team of the Council.
  • KRI: Key Risk Indicator, used to inform risk identification and mitigation success.
  • SMART: Specific, Measurable, Achievable, Relevant, Time-bound actions used in risk treatment plans.
  • SWOT: Strengths, Weaknesses, Opportunities, Threats analysis used in risk identification.
  • The Orange Book: UK Government guidance for the management of risk, used as the basis for writing risks.
  • 3 Lines Model: Institute of Internal Auditors model: 1st line operational management, 2nd line risk/compliance, 3rd line internal audit.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

To recommend to Cabinet, the adoption of the amended Risk Management Framework at Appendix 1 of the report.
Word for word from the decision Gedling published for this meeting. Source: democracy.gedling.gov.uk

Follow this further

Built from Gedling's papers

What the report saysPro

Report to Audit Committee

Risk Management Framework March 2024 Reviewed December 2025 Reviewed June 2026

Page 1 of 41 Contents

Introduction ................................................................................................................ 3 Part 1 - Risk Management Policy & Strategy ............................................................. 4 2. What is Risk Management ................................................................................... 6 3. Why does the Council need to carry out Risk Management? .............................. 6 4. Risk Management Strategy ................................................................................. 8 i. Governance and Infrastructure ........................................................................ 8 ii. Culture ....................................................................................................... 1211 5. Management of Risks .................................................................................... 1413 6. Risk Appetite Statement ................................................................................ 1413 7. Risk Matrix ..................................................................................................... 1615 Appendix 1 - ALARM National Performance Model for Risk Management in Public Services ............................................................................................................... 2019 Part 2 - Risk Management Toolkit ........................................................................ 2221 1. Risk Management Process ............................................................................ 2322 i. Risk Identification....................................................................................... 2524 ii. Analyse, assess and evaluate risks. .......................................................... 2725 iii. Review of controls and their effectiveness ................................................. 2826 iv. Response to Risk....................................................................................... 2927 v. Reporting, Monitoring and Communication ................................................ 3129 vi. Integration with Strategic Planning and Decision Making .......................... 3533 Appendix 2 – Corporate Risk Register Template 35

Page 2 of 41 Introduction

This Risk Management Framework pulls together a number of key elements to ensure that the Council establishes and maintains effective risk management. The overarching Framework includes; i) The Risk Management Policy, Strategy and Risk Appetite Statement which sets out the Council’s approach to risk management and; ii) The Risk Management Toolkit, which sets out the processes that managers will follow to deliver effective risk management.

Page 3 of 41 Part 1 - Risk Management Policy & Strategy

1. Risk Management Policy Statement

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
13a. Risk Management Framework Update June 2026Report 603 KB DownloadRead as text
PDF
13b. EIA-form June 26Report 204 KB Download
PDF
Corporate Risk Management Strategic FrameworkReport 145 KB Download

At this meeting

Whole meeting

Who was there

9 of 17 attended
RM
Councillor Ron McCrossenChair, present
RS
Councillor Ruth StrongVice-Chair, present
SB
Councillor Stuart BestwickCommittee Member, apologies, sent representative
DB
Councillor David BrocklebankCommittee Member, present
HG
Councillor Helen GreensmithCommittee Member, present
PH
Councillor Paul HughesCommittee Member, present
JN
Councillor Julie NajukCommittee Member, present
MS
Councillor Martin SmithCommittee Member, present
JC
Jonathan CaustonCo-Optee, present
FW
Francesca WhyleyOfficer, in attendance
TA
Tina AdamsOfficer, in attendance
CG
Cayte GoodallOfficer, in attendance

All 17 on the meeting page

On this subject at Gedling

Search all
  1. Corporate Risk Management Strategic FrameworkThis decision
  2. Corporate Risk Management Review Period 1 April - July 2026Noted
  3. Corporate Risk StrategyApproved
  4. Corporate Risk Management Review Quarter 4 2025/26Noted
  5. Corporate Risk Management Review - Quarter 3 2025/26Noted
  6. Corporate Risk Management Review - Quarter 3 2025/26Noted

More from Gedling Audit Committee

All decisions
MeetingDecisionOutcome
20 Oct 2026 To approve, as a correct record, the minutes of the meeting held on 23 June 2026That the minutes of the above meeting, having been circulated, be approved as a correct record. Approved Open
20 Oct 2026 BDO Internal Audit Progress ReportTo note the progress (completion) of the delivery against the 2026/27 Internal Audit Plan, including executive summar... Noted Open
20 Oct 2026 Mazars External Audit Draft Annual Report and Audit Strategy Memorandum Report 31 March 2026To note the Audit Strategy Memorandum dated 20 October 2026 and the draft Auditor’s Annual Report for the year ended ... Noted Open
20 Oct 2026 Statement of Accounts 2025-26 and Annual Governance StatementTo note the Council’s unaudited Statement of Accounts for 2025-26 and the key financial matters set out in this repor... Noted Open
20 Oct 2026 Corporate Risk Management Review Period 1 April - July 2026To note the operation of the revised Risk Management Framework, the current corporate risk position and the controls ... Noted Open